Overview
ATS MARIGOLD
ATS REAL ESTATE BUILDERS PVT LTD · Gurugram
Completion2024-02-29Revised · Proposed 2024-02-29
Registered on2017-08-17
Valid to2027-02-28
Approvals16
Sections
| Property title & search report | |
|---|---|
| Approvals | 16 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 10 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 32 documents · 2 source links |
Registration
Registration
| Promoter | ATS REAL ESTATE BUILDERS PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 55 OF 2017 DATED 17.08.2017 | |
| Registered on | 2017-08-17 | |
| Valid to | 2027-02-28 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-02-29 | |
| Revised completion | 2024-02-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 87 of 2013(10-10-2017) | Town & Country Planning Department | |
| Layout Plan | 2014-06-06 | ||
| Building Plan | 2014-06-06 | ||
| I. FIRE FIGHTING (NOC) | 2014-12-29 | ||
| II. SERVICE ESTIMATE | 2016-01-08 | ||
| III. HEIGHT CLEARANCE (AAI) | 2014-01-02 | ||
| IV. NWBL NOC | 2014-06-12 | ||
| V. FOREST (ARAWALI) NOC | 2013-04-01 | ||
| VI. WATER NOC | 2013-11-28 | ||
| VII. STRUCTURE STABILITY | 2015-05-16 | ||
| VIII. ENVIRONMENT CLEARANCE | 2014-09-03 | ||
| IX. HARYANA STATE POLLUTION CONTROL BOARD | 2014-11-20 | ||
| X. SANCTION LETTER | 2016-06-06 | ||
| XI. TEMPORARY STRUCTURE APPROVAL | 2013-12-24 | ||
| XII. ZONING PLAN | 2013-10-11 | ||
| XIII. ELECTRIC POWER UNDERTAKING & APPLICATION | 2013-11-27 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,48,79,00,000 | |
|---|---|---|
| Construction | ₹2,43,10,50,000 | |
| Total | ₹7,65,39,52,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 175 |
|---|
Unit types
| Type |
|---|
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
| 10 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2024-02-29 | |
|---|---|---|
| Revised completion | 2024-02-29 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ATS REAL ESTATE BUILDERS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LTD | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/940
- Registration Certificate · 2017-08-17
- REGISTRATION FEE DEMAND DRAFT · 2020-02-17 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2019-12-12 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-12-12
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-12-12
- ZONING PLAN · 2019-12-12
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-12-12
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-12-12
- GIST OF THE IMPORTANT PROVISIONS OF DRAFT AGREEMENT · 2021-01-28 · Sign in to download
- AIRPORT HEIGHT CLEARANCE · 2020-02-07
- ATS MARIGOLD LOI · 2020-02-07 · Sign in to download
- BOARD RESOLUTION · 2020-02-07 · Sign in to download
- NON ENCUMBRANCE CERTIFICATE · 2020-02-07 · Sign in to download
- ENVIRONMENT CLEARANCE APPROVAL · 2020-02-07
- DEMARCATION PLAN · 2020-02-07
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-02-07
- FIRE NOC · 2020-02-07
- LICENSE ALONG WITH LAND SCHEDULE · 2020-02-07
- FOREST NOC · 2020-02-07
- LC-IV · 2020-02-07 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2021-06-01 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2021-07-22 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2021-07-22 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-07-22 · Sign in to download
- COD · 2021-07-27 · Sign in to download
- SERVICE PLAN ESTIMATES · 2021-07-28
- BUILDING PLAN APPROVAL LETTER (BR-III) · 2021-07-27
- RENEWAL OF LICENSE (MARIGOLD) · 2021-07-27
- DEFICIT FEES · 2021-07-27 · Sign in to download
- SERVICE PLAN ESTIMATES APPROVAL LETTER · 2021-07-28
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/55 of 2017/7(3)/2022/07 DATED 20.09.2022 · 2022-12-26 · Sign in to download
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/55 OF 2017/7(3)/2022/07 DATED 24.06.2024 · 2024-07-09 · Sign in to download