Overview
Aura Homes
Aura Builders & Developers · Sahibzada Ajit Singh Nagar (Mohali)
Units102
Completion2021-03-31Proposed
Valid to2021-03-31
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details · 35 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 41 source links |
Registration
Registration
| Promoter | Aura Builders & Developers | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0236 | |
| Valid to | 2021-03-31 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2021-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| CLU Certificate |
| License to develop colony or society from Competent Authority |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹13,30,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 16,713.5153 | |
|---|---|---|
| Units | 102 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| PLOTS | 9,897.774 | 102 | AURA HOMES |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-04-01 | |
|---|---|---|
| Proposed completion | 2021-03-31 |
Quarterly progress
| 2018-Q1 | 2021-05-05 |
| 2018-Q2 | 2021-05-05 |
| 2018-Q3 | 2021-05-05 |
| 2018-Q4 | 2021-05-05 |
| 2019-Q1 | 2021-05-05 |
| 2019-Q2 | 2021-05-05 |
| 2019-Q3 | 2021-05-05 |
| 2019-Q4 | 2021-05-05 |
| 2020-Q1 | 2021-05-05 |
| 2020-Q2 | 2021-05-05 |
| 2020-Q3 | 2021-05-05 |
| 2020-Q4 | 2021-05-05 |
| 2021-Q4 | 2022-02-26 |
| 2021-Q1 | 2022-02-28 |
| 2021-Q2 | 2022-02-28 |
| 2021-Q3 | 2022-02-28 |
| 2022-Q1 | 2022-08-31 |
| 2022-Q2 | 2022-08-31 |
| 2022-Q3 | 2023-07-06 |
| 2022-Q4 | 2023-07-06 |
| 2023-Q1 | 2023-07-06 |
| 2023-Q2 | 2023-07-06 |
| 2023-Q3 | 2023-10-04 |
| 2023-Q4 | 2024-07-19 |
| 2024-Q1 | 2024-07-19 |
| 2024-Q2 | 2024-07-19 |
| 2024-Q3 | 2024-11-06 |
| 2024-Q4 | 2025-02-05 |
| 2025-Q1 | 2025-06-30 |
| 2025-Q2 | 2025-09-18 |
| 2025-Q3 | 2025-12-20 |
| 2025-Q4 | 2026-01-29 |
| 2026-Q1 | 2026-06-20 |
| 2026-Q2 | 2026-09-07 |
| 2026-Q3 | 2026-10-05 |
Extensions
| Valid to |
|---|
| 2022-09-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Aura Builders & Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | IndusInd Bank Limited | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10111&inPromoter_ID=1102&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License to develop colony or society from Competent Authority
- Other Document (Regularization C ertificate) · 2017-09-01 · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- CLU Certificate
- License to develop colony or society from Competent Authority
- Extension order · Sign in to download
- 2018-Q1 · 2021-05-05
- 2018-Q2 · 2021-05-05
- 2018-Q3 · 2021-05-05
- 2018-Q4 · 2021-05-05
- 2019-Q1 · 2021-05-05
- 2019-Q2 · 2021-05-05
- 2019-Q3 · 2021-05-05
- 2019-Q4 · 2021-05-05
- 2020-Q1 · 2021-05-05
- 2020-Q2 · 2021-05-05
- 2020-Q3 · 2021-05-05
- 2020-Q4 · 2021-05-05
- 2021-Q4 · 2022-02-26
- 2021-Q1 · 2022-02-28
- 2021-Q2 · 2022-02-28
- 2021-Q3 · 2022-02-28
- 2022-Q1 · 2022-08-31
- 2022-Q2 · 2022-08-31
- 2022-Q3 · 2023-07-06
- 2022-Q4 · 2023-07-06
- 2023-Q1 · 2023-07-06
- 2023-Q2 · 2023-07-06
- 2023-Q3 · 2023-10-04
- 2023-Q4 · 2024-07-19
- 2024-Q1 · 2024-07-19
- 2024-Q2 · 2024-07-19
- 2024-Q3 · 2024-11-06
- 2024-Q4 · 2025-02-05
- 2025-Q1 · 2025-06-30
- 2025-Q2 · 2025-09-18
- 2025-Q3 · 2025-12-20
- 2025-Q4 · 2026-01-29
- 2026-Q1 · 2026-06-20
- 2026-Q2 · 2026-09-07
- 2026-Q3 · 2026-10-05