Overview
AURA VALLEY
THE FIRE STONE ASSETS · Sahibzada Ajit Singh Nagar (Mohali)
Units231
Booked80 of 231As of 2026-09-30
Completion2029-01-24Proposed
Registered on2024-06-11
Valid to2029-01-24
Approvals15
Sections
| Property title & search report | |
|---|---|
| Approvals | 15 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 35 unit types |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 40 documents · 28 source links |
Registration
Registration
| Promoter | THE FIRE STONE ASSETS | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0950 | |
| Registered on | 2024-06-11 | |
| Valid to | 2029-01-24 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-01-24 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2025-05-19 | |
| CLU Certificate | ||
| Electric Substation NOC | 2024-06-28 | |
| License as Promoter from competent Authority | 2023-08-03 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2023-07-18 | |
| NOC from NHAI/ PWD | 2026-06-30 | |
| Other Document (AFFIDAVIT FOR NOCs) | Legal Documents (Received) | 2024-05-02 |
| Other Document (DRAINAGE NOC) | 2024-01-22 | |
| Other Document (FOREST NOC) | 2023-08-09 | |
| Other Document (FOREST NOC) | 2024-07-19 | |
| Other Document (LATEST AFFIDAVIT FOR NOC FOR REVISION) | Legal Documents (Received) | 2026-08-11 |
| Other Document (TREATED WASTE WATER NOC) | 2024-01-18 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-05-16 | |
| Pollution Clearance from Punjab Pollution Control Board | 2026-08-20 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹20,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 34,445.073 | |
|---|---|---|
| Towers | 3 | |
| Units | 231 | |
| Booked | 80 | |
| Booked as of | 2026-09-30 |
Unit types
| PLOT NO 1 and 48 | 196.56 | 2 | 0 | RESIDENTIAL PLOTS |
| Plot no . 2 to 47 | 4,328.53 | 46 | 25 | RESIDENTIAL PLOTS |
| PLOT NO. 49-57 | 851.59 | 9 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 58 | 98.83 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO 59-66 | 740.24 | 8 | 4 | RESIDENTIAL PLOTS |
| PLOT NO. 67, 74, 75, 82 | 462.36 | 4 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 68 TO 73 | 662.17 | 6 | 1 | RESIDENTIAL PLOTS |
| PLOT NO 76-81 | 662.17 | 6 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 83 and 100 | 197.49 | 2 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 84-99 | 1,589.22 | 16 | 3 | RESIDENTIAL PLOTS |
| PLOT NO. 101and 102 | 171.82 | 2 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 103-118 | 1,940.52 | 16 | 5 | RESIDENTIAL PLOTS |
| PLOT NO. 119 | 125.46 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 120 - 132 | 1,467.935 | 13 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 133 AND 140 | 228.63 | 2 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 134-139 | 613.38 | 6 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 141 - 153 | 1,467.935 | 13 | 4 | RESIDENTIAL PLOTS |
| PLOT NO. 154, 160, 161 | 250.93 | 3 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 155 | 96.19 | 1 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 156, 159 | 243.82 | 2 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 157 and 158 | 241.36 | 2 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 163-166 | 443.31 | 4 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 176-179 | 443.31 | 4 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 193 | 95.3 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 194 | 96.27 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 195 | 97.24 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 196 | 98.24 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 197 | 99.21 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 198 | 100.18 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 199 | 100.62 | 1 | 0 | RESIDENTIAL PLOTS |
| PLOT NO. 200 | 102.11 | 1 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 201 | 105.7 | 1 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 162,167 TO 175 AND 180 TO 192 | 1,923.79 | 23 | 18 | EWS PLOTS |
| PLOT NO. S01 TO S10 | 278.81 | 10 | 0 | COMMERCIAL PLOTS |
| PLOT NO. S11 TO S30 | 529.75 | 20 | 1 | COMMERCIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-01-25 | |
|---|---|---|
| Proposed completion | 2029-01-24 |
Quarterly progress
| 2024-Q2 | 2024-08-03 | ||
| 2024-Q3 | 2024-10-21 | ||
| 2024-Q4 | 2025-01-31 | ||
| 2025-Q1 | 2025-05-21 | ||
| 2025-Q2 | 2025-08-05 | ||
| 2025-Q3 | 2025-11-04 | ||
| 2025-Q4 | 2026-01-29 | ||
| 2026-Q1 | 2026-04-25 | ||
| 2026-Q2 | 2026-07-31 | ||
| 2026-Q3 | 2026-10-11 | 13 | 3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | THE FIRE STONE ASSETS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | NIRMAAN ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=11896&inPromoter_ID=2787&inPromoterType=11896&inQUProject_ID=6157&inQUProject_DN=QUP2026T20266157&inQUProjectYear=2026&inQUProjectQTR=ThirdQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11896&inPromoter_ID=2787&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-19
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-06-28
- License as Promoter from competent Authority · 2023-08-03
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-07-18
- NOC from NHAI/ PWD · 2026-06-30
- Other Document (AUTHORITY LETTER) · 2024-02-12 · Sign in to download
- Other Document (Bank account opening letter) · 2024-05-02 · Sign in to download
- Other Document (DRAINAGE NOC) · 2024-01-22
- Other Document (FOREST NOC) · 2023-08-09
- Other Document (FOREST NOC) · 2024-07-19
- Other Document (LATEST INDEMNITY BOND FOR REVISION ) · 2026-08-11 · Sign in to download
- Other Document (Solid waste and Construction and Demolation waste) · 2024-01-18 · Sign in to download
- Other Document (TREATED WASTE WATER NOC) · 2024-01-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-05-16
- Pollution Clearance from Punjab Pollution Control Board · 2026-08-20
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Annual Report (Form-5 CA Certificate)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-19
- CLU Certificate
- Electric Substation NOC · 2024-06-28
- License as Promoter from competent Authority · 2023-08-03
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-07-18
- NOC from NHAI/ PWD · 2026-06-30
- Other Document (AFFIDAVIT FOR NOCs) · 2024-05-02
- Other Document (DRAINAGE NOC) · 2024-01-22
- Other Document (FOREST NOC) · 2023-08-09
- Other Document (FOREST NOC) · 2024-07-19
- Other Document (LATEST AFFIDAVIT FOR NOC FOR REVISION) · 2026-08-11
- Other Document (TREATED WASTE WATER NOC) · 2024-01-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-05-16
- Pollution Clearance from Punjab Pollution Control Board · 2026-08-20
- 2024-Q2 · 2024-08-03
- 2024-Q3 · 2024-10-21
- 2024-Q4 · 2025-01-31
- 2025-Q1 · 2025-05-21
- 2025-Q2 · 2025-08-05
- 2025-Q3 · 2025-11-04
- 2025-Q4 · 2026-01-29
- 2026-Q1 · 2026-04-25
- 2026-Q2 · 2026-07-31