DOSLChhattisgarh Workspace

Overview

AVINASH CHITWAN PHASE-4

M/S AIM INFRASTRUCTURE AND DEVELOPERS · RAIPUR
Units12
Booked2 of 12As of 2026-06-30
Construction progress7%As of 2026-06-30
Completion2029-05-15Revised · Proposed 2029-01-15
Registered on2024-03-01
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 10 quarters
Technical report
Site & area3 site details · 12 unit types
Construction & progress4 progress details · 10 quarters
Developer & finance
Developer3 developer details
The evidence
Sources54 documents · 7 source links

Registration

Registration

PromoterM/S AIM INFRASTRUCTURE AND DEVELOPERS
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA010324001741
Registered on2024-03-01
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2029-01-15
Revised completion2029-05-15