Overview
AVINASH CHITWAN SE
M/S AIM INFRASTRUCTURE AND DEVELOPERS · RAIPUR
Units124
Booked56 of 124As of 2026-06-30
Construction progress27%As of 2026-06-30
Completion2028-04-30Revised · Proposed 2027-12-31
Registered on2023-09-11
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 2 cost heads · 12 quarters |
| Technical report | |
| Site & area | 3 site details · 124 unit types |
| Construction & progress | 4 progress details · 12 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 78 documents · 7 source links |
Registration
Registration
| Promoter | M/S AIM INFRASTRUCTURE AND DEVELOPERS | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA110923001671 | |
| Registered on | 2023-09-11 | |
| Project type | Commercial | |
| Status (as filed) | New | |
| Proposed completion | 2027-12-31 | |
| Revised completion | 2028-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,58,71,000 | |
|---|---|---|
| Construction | ₹14,31,00,000 |
Quarterly money flows
| 2023-Q3 | ₹3,15,000 |
| 2023-Q4 | ₹4,47,570 |
| 2024-Q1 | ₹77,170 |
| 2024-Q2 | ₹5,28,370 |
| 2024-Q3 | ₹13,49,103 |
| 2024-Q4 | ₹15,67,503 |
| 2025-Q1 | ₹4,22,503 |
| 2025-Q2 | ₹2,65,221 |
| 2025-Q3 | ₹5,36,799 |
| 2025-Q4 | ₹1 |
| 2026-Q1 | ₹1,05,100 |
| 2026-Q2 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 124 | |
|---|---|---|
| Booked | 56 | |
| Booked as of | 2026-06-30 |
Unit types
| COMMERCIAL | 60.29 | 1 | 1 |
| COMMERCIAL | 78.97 | 1 | 0 |
| COMMERCIAL | 19.88 | 1 | 1 |
| COMMERCIAL | 19.88 | 1 | 0 |
| COMMERCIAL | 26.76 | 1 | 1 |
| COMMERCIAL | 63.17 | 1 | 0 |
| COMMERCIAL | 63.64 | 1 | 0 |
| COMMERCIAL | 21.65 | 1 | 1 |
| COMMERCIAL | 22.76 | 1 | 0 |
| COMMERCIAL | 22.76 | 1 | 1 |
| COMMERCIAL | 58.81 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 13.94 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 85.47 | 1 | 0 |
| COMMERCIAL | 37.44 | 1 | 0 |
| COMMERCIAL | 39.3 | 1 | 0 |
| COMMERCIAL | 19.88 | 1 | 1 |
| COMMERCIAL | 19.88 | 1 | 1 |
| COMMERCIAL | 21.37 | 1 | 1 |
| COMMERCIAL | 63.17 | 1 | 0 |
| COMMERCIAL | 63.64 | 1 | 0 |
| COMMERCIAL | 21.65 | 1 | 0 |
| COMMERCIAL | 21.65 | 1 | 1 |
| COMMERCIAL | 18.77 | 1 | 1 |
| COMMERCIAL | 66.05 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 13.94 | 1 | 1 |
| COMMERCIAL | 200.02 | 1 | 0 |
| COMMERCIAL | 133.5 | 1 | 0 |
| COMMERCIAL | 31.12 | 1 | 1 |
| COMMERCIAL | 141.21 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 13.94 | 1 | 1 |
| COMMERCIAL | 728.63 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 40.04 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 36.51 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.12 | 1 | 1 |
| COMMERCIAL | 40.04 | 1 | 0 |
| COMMERCIAL | 40.88 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 1 |
| COMMERCIAL | 34 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 1 |
| COMMERCIAL | 13.94 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 40.04 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 36.51 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.12 | 1 | 1 |
| COMMERCIAL | 40.04 | 1 | 0 |
| COMMERCIAL | 40.88 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 1 |
| COMMERCIAL | 34 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 1 |
| COMMERCIAL | 13.94 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 1 |
| COMMERCIAL | 40.04 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 36.51 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 1 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.12 | 1 | 1 |
| COMMERCIAL | 40.04 | 1 | 1 |
| COMMERCIAL | 40.88 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 1 |
| COMMERCIAL | 34 | 1 | 1 |
| COMMERCIAL | 32.33 | 1 | 1 |
| COMMERCIAL | 13.94 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 40.04 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 36.51 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.12 | 1 | 0 |
| COMMERCIAL | 40.04 | 1 | 0 |
| COMMERCIAL | 40.88 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 0 |
| COMMERCIAL | 34 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 0 |
| COMMERCIAL | 13.94 | 1 | 1 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 33.17 | 1 | 0 |
| COMMERCIAL | 40.04 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 36.51 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.58 | 1 | 0 |
| COMMERCIAL | 35.12 | 1 | 0 |
| COMMERCIAL | 40.04 | 1 | 0 |
| COMMERCIAL | 40.88 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 0 |
| COMMERCIAL | 34 | 1 | 0 |
| COMMERCIAL | 32.33 | 1 | 0 |
| COMMERCIAL | 13.94 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 27% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2027-12-31 | |
| Revised completion | 2028-04-30 |
Quarterly progress
| 2023-Q3 | 2% |
| 2023-Q4 | 5% |
| 2024-Q1 | 10% |
| 2024-Q2 | 13% |
| 2024-Q3 | 17% |
| 2024-Q4 | 19% |
| 2025-Q1 | 19% |
| 2025-Q2 | 21% |
| 2025-Q3 | 24% |
| 2025-Q4 | 24% |
| 2026-Q1 | 25% |
| 2026-Q2 | 27% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S AIM INFRASTRUCTURE AND DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 8 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTk4Mw==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities