Overview
AVINASH ELEGANCE
AVINASH DEVELOPERS PVT. LTD. · RAIPUR
Units98
Booked41 of 98As of 2026-06-30
Construction progress92%As of 2026-06-30
Completion2027-01-29Revised · Proposed 2026-09-29
Registered on2021-12-24
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 2 cost heads · 19 quarters |
| Technical report | |
| Site & area | 3 site details · 98 unit types |
| Construction & progress | 4 progress details · 19 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 118 documents · 7 source links |
Registration
Registration
| Promoter | AVINASH DEVELOPERS PVT. LTD. | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA241221001307 | |
| Registered on | 2021-12-24 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2026-09-29 | |
| Revised completion | 2027-01-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹14,59,62,000 | |
|---|---|---|
| Construction | ₹55,89,10,000 |
Quarterly money flows
| 2021-Q4 | ₹0 |
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹99,764 |
| 2022-Q3 | ₹99,292 |
| 2022-Q4 | ₹10,59,598 |
| 2023-Q1 | ₹20,89,664 |
| 2023-Q2 | ₹70,000 |
| 2023-Q3 | ₹7,56,700 |
| 2023-Q4 | ₹26,896 |
| 2024-Q1 | ₹1,47,038 |
| 2024-Q2 | ₹11,53,150 |
| 2024-Q3 | ₹3,27,018 |
| 2024-Q4 | ₹1,27,098 |
| 2025-Q1 | ₹60,100 |
| 2025-Q2 | ₹62,74,014 |
| 2025-Q3 | ₹79,36,126 |
| 2025-Q4 | ₹2,23,207 |
| 2026-Q1 | ₹89,64,555 |
| 2026-Q2 | ₹3,55,468 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 98 | |
|---|---|---|
| Booked | 41 | |
| Booked as of | 2026-06-30 |
Unit types
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 3BHK | 170.85 | 1 | 0 |
| 4BHK | 240.52 | 1 | 0 |
| 4BHK | 242.47 | 1 | 0 |
| 3BHK | 170.85 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 4BHK | 240.52 | 1 | 0 |
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 4BHK | 240.52 | 1 | 0 |
| 4BHK | 242.47 | 1 | 0 |
| 3BHK | 170.85 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 4BHK | 240.52 | 1 | 1 |
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 4BHK | 240.52 | 1 | 1 |
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 4BHK | 240.52 | 1 | 1 |
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 3BHK | 170.85 | 1 | 1 |
| 4BHK | 240.52 | 1 | 0 |
| 3BHK | 144 | 1 | 0 |
| 3BHK | 129.51 | 1 | 0 |
| 4BHK | 171.59 | 1 | 0 |
| 4BHK | 163.6 | 1 | 0 |
| 3BHK | 132.85 | 1 | 0 |
| 3BHK | 143.16 | 1 | 0 |
| 3BHK | 144 | 1 | 0 |
| 3BHK | 129.51 | 1 | 0 |
| 4BHK | 171.59 | 1 | 1 |
| 4BHK | 163.6 | 1 | 0 |
| 3BHK | 132.85 | 1 | 0 |
| 3BHK | 143.16 | 1 | 0 |
| 3BHK | 144 | 1 | 0 |
| 3BHK | 129.51 | 1 | 0 |
| 4BHK | 171.59 | 1 | 1 |
| 4BHK | 163.6 | 1 | 0 |
| 3BHK | 132.85 | 1 | 1 |
| 3BHK | 143.16 | 1 | 0 |
| 3BHK | 144 | 1 | 1 |
| 3BHK | 129.51 | 1 | 1 |
| 4BHK | 171.59 | 1 | 0 |
| 4BHK | 163.6 | 1 | 0 |
| 3BHK | 132.85 | 1 | 1 |
| 3BHK | 143.16 | 1 | 0 |
| 3BHK | 144 | 1 | 1 |
| 3BHK | 129.51 | 1 | 0 |
| 4BHK | 171.59 | 1 | 0 |
| 4BHK | 163.6 | 1 | 0 |
| 3BHK | 132.85 | 1 | 1 |
| 3BHK | 143.16 | 1 | 0 |
| 3BHK | 144 | 1 | 0 |
| 3BHK | 129.51 | 1 | 0 |
| 4BHK | 171.59 | 1 | 1 |
| 4BHK | 163.6 | 1 | 0 |
| 3BHK | 132.85 | 1 | 1 |
| 3BHK | 143.16 | 1 | 1 |
| 4BHK | 235.04 | 1 | 0 |
| 3BHK | 129.51 | 1 | 0 |
| 3BHK | 181.16 | 1 | 1 |
| 3BHK | 167.13 | 1 | 0 |
| 3BHK | 132.85 | 1 | 1 |
| 3BHK | 143.16 | 1 | 1 |
| 4BHK | 242.47 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 4BHK | 240.52 | 1 | 1 |
| 4BHK | 242.47 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 4BHK | 240.52 | 1 | 0 |
| 4BHK | 242.47 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 4BHK | 240.52 | 1 | 0 |
| 4BHK | 242.47 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 4BHK | 240.52 | 1 | 0 |
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 1 |
| 4BHK | 240.52 | 1 | 1 |
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 1 |
| 4BHK | 240.52 | 1 | 1 |
| 4BHK | 242.47 | 1 | 1 |
| 3BHK | 170.85 | 1 | 0 |
| 3BHK | 170.85 | 1 | 0 |
| 4BHK | 240.52 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 92% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2026-09-29 | |
| Revised completion | 2027-01-29 |
Quarterly progress
| 2021-Q4 | 0% |
| 2022-Q1 | 1% |
| 2022-Q2 | 2% |
| 2022-Q3 | 5% |
| 2022-Q4 | 7% |
| 2023-Q1 | 15% |
| 2023-Q2 | 16% |
| 2023-Q3 | 17% |
| 2023-Q4 | 20% |
| 2024-Q1 | 24% |
| 2024-Q2 | 27% |
| 2024-Q3 | 30% |
| 2024-Q4 | 32% |
| 2025-Q1 | 55% |
| 2025-Q2 | 69% |
| 2025-Q3 | 80% |
| 2025-Q4 | 85% |
| 2026-Q1 | 91% |
| 2026-Q2 | 92% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AVINASH DEVELOPERS PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 30 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTYxOQ==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities