Overview
AVINASH SMART CITY EAXTENSION
AVINASH BUILDERS · RAIPUR
Units347
Booked258 of 347As of 2025-06-30
Construction progress100%As of 2025-06-30
Completion2027-10-23Revised · Proposed 2027-06-23
Registered on2022-07-08
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 2 cost heads · 12 quarters |
| Technical report | |
| Site & area | 3 site details · 347 unit types |
| Construction & progress | 4 progress details · 12 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 96 documents · 7 source links |
Registration
Registration
| Promoter | AVINASH BUILDERS | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA080722001470 | |
| Registered on | 2022-07-08 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2027-06-23 | |
| Revised completion | 2027-10-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹31,05,35,000 | |
|---|---|---|
| Construction | ₹11,36,15,000 |
Quarterly money flows
| 2022-Q3 | ₹16,22,414 |
| 2022-Q4 | ₹19,52,778 |
| 2023-Q1 | ₹4,48,534 |
| 2023-Q2 | ₹80,672 |
| 2023-Q3 | ₹5,02,571 |
| 2023-Q4 | ₹1,47,034 |
| 2024-Q1 | ₹4,25,024 |
| 2024-Q2 | ₹1,50,134 |
| 2024-Q3 | ₹73,494 |
| 2024-Q4 | ₹22,87,373 |
| 2025-Q1 | ₹57,658 |
| 2025-Q2 | ₹5,51,809 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 347 | |
|---|---|---|
| Booked | 258 | |
| Booked as of | 2025-06-30 |
Unit types
| A-24A | 1 | 1 |
| A-24B | 1 | 1 |
| A-24C | 1 | 0 |
| A-31A | 1 | 1 |
| A-31B | 1 | 0 |
| A-31C | 1 | 0 |
| A-54 | 1 | 0 |
| A-55 | 1 | 1 |
| A-56 | 1 | 1 |
| A-57 | 1 | 1 |
| A-58 | 1 | 1 |
| A-59 | 1 | 0 |
| A-60 | 1 | 0 |
| A-61 | 1 | 0 |
| A-62 | 1 | 0 |
| A-63 | 1 | 0 |
| A-64 | 1 | 0 |
| A-65 | 1 | 0 |
| A-66 | 1 | 0 |
| A-67 | 1 | 0 |
| A-68 | 1 | 0 |
| A-69 | 1 | 1 |
| A-70 | 1 | 1 |
| A-71 | 1 | 1 |
| A-72 | 1 | 1 |
| A-73 | 1 | 1 |
| A-74 | 1 | 1 |
| A-75 | 1 | 1 |
| A-76 | 1 | 1 |
| A-77 | 1 | 1 |
| A-78 | 1 | 1 |
| A-79 | 1 | 1 |
| A-80 | 1 | 0 |
| A-81 | 1 | 0 |
| A-82 | 1 | 0 |
| A-83 | 1 | 0 |
| A-84 | 1 | 0 |
| A-85 | 1 | 0 |
| A-86 | 1 | 0 |
| A-87 | 1 | 0 |
| A-88 | 1 | 0 |
| A-89 | 1 | 0 |
| A-90 | 1 | 0 |
| A-91 | 1 | 0 |
| A-92 | 1 | 0 |
| A-93 | 1 | 0 |
| A-94 | 1 | 0 |
| A-95 | 1 | 0 |
| A-96 | 1 | 0 |
| A-97 | 1 | 0 |
| A-98 | 1 | 0 |
| A-99 | 1 | 0 |
| A-100 | 1 | 0 |
| A-101 | 1 | 0 |
| A-102 | 1 | 0 |
| A-103 | 1 | 0 |
| A-104 | 1 | 0 |
| A-105 | 1 | 0 |
| A-106 | 1 | 0 |
| A-107 | 1 | 0 |
| A-108 | 1 | 0 |
| A-109 | 1 | 0 |
| A-110 | 1 | 0 |
| A-111 | 1 | 0 |
| A-112 | 1 | 0 |
| A-113 | 1 | 0 |
| A-114 | 1 | 0 |
| A-115 | 1 | 0 |
| A-116 | 1 | 0 |
| A-117 | 1 | 0 |
| A-118 | 1 | 0 |
| B-73 | 1 | 0 |
| B-74 | 1 | 1 |
| B-75 | 1 | 1 |
| B-76 | 1 | 1 |
| B-77 | 1 | 1 |
| B-78 | 1 | 1 |
| B-79 | 1 | 1 |
| B-80 | 1 | 1 |
| B-81 | 1 | 1 |
| B-82 | 1 | 1 |
| B-83 | 1 | 1 |
| B-84 | 1 | 1 |
| B-85 | 1 | 1 |
| B-86 | 1 | 1 |
| B-87 | 1 | 1 |
| B-88 | 1 | 1 |
| B-89 | 1 | 1 |
| B-90 | 1 | 1 |
| B-91 | 1 | 1 |
| B-92 | 1 | 1 |
| B-93 | 1 | 1 |
| B-94 | 1 | 1 |
| B-95 | 1 | 1 |
| B-96 | 1 | 1 |
| B-97 | 1 | 1 |
| B-98 | 1 | 1 |
| B-99 | 1 | 1 |
| B-100 | 1 | 1 |
| B-101 | 1 | 1 |
| B-102 | 1 | 1 |
| B-103 | 1 | 1 |
| B-104 | 1 | 1 |
| B-105 | 1 | 1 |
| B-106 | 1 | 0 |
| B-107 | 1 | 0 |
| B-108 | 1 | 0 |
| B-109 | 1 | 1 |
| B-110 | 1 | 1 |
| B-111 | 1 | 1 |
| B-112 | 1 | 1 |
| B-113 | 1 | 1 |
| C-80 | 1 | 1 |
| C-81 | 1 | 1 |
| C-82 | 1 | 1 |
| C-83 | 1 | 1 |
| C-84 | 1 | 1 |
| C-85 | 1 | 1 |
| C-86 | 1 | 1 |
| C-87 | 1 | 1 |
| C-88 | 1 | 1 |
| C-89 | 1 | 1 |
| C-90 | 1 | 1 |
| C-91 | 1 | 1 |
| C-92 | 1 | 1 |
| C-93 | 1 | 1 |
| C-94 | 1 | 1 |
| C-95 | 1 | 1 |
| C-96 | 1 | 1 |
| C-97 | 1 | 1 |
| C-98 | 1 | 1 |
| C-99 | 1 | 1 |
| C-100 | 1 | 1 |
| C-101 | 1 | 1 |
| C-102 | 1 | 1 |
| C-103 | 1 | 1 |
| C-104 | 1 | 1 |
| C-105 | 1 | 1 |
| C-106 | 1 | 1 |
| C-107 | 1 | 1 |
| C-108 | 1 | 1 |
| C-109 | 1 | 1 |
| C-110 | 1 | 0 |
| C-A-110 | 1 | 0 |
| C-111 | 1 | 0 |
| C-112 | 1 | 0 |
| C-113 | 1 | 0 |
| C-114 | 1 | 1 |
| C-115 | 1 | 1 |
| C-116 | 1 | 1 |
| C-117 | 1 | 1 |
| C-118 | 1 | 1 |
| C-119 | 1 | 1 |
| C-120 | 1 | 1 |
| C-121 | 1 | 1 |
| C-122 | 1 | 0 |
| C-123 | 1 | 0 |
| C-124 | 1 | 0 |
| C-125 | 1 | 0 |
| C-126 | 1 | 0 |
| C-127 | 1 | 0 |
| C-128 | 1 | 0 |
| C-129 | 1 | 0 |
| C-130 | 1 | 1 |
| C-131 | 1 | 1 |
| C-132 | 1 | 1 |
| C-133 | 1 | 1 |
| C-134 | 1 | 1 |
| C-135 | 1 | 1 |
| C-136 | 1 | 0 |
| C-A-136 | 1 | 1 |
| C-137 | 1 | 0 |
| C-138 | 1 | 0 |
| C-139 | 1 | 0 |
| C-140 | 1 | 0 |
| C-141 | 1 | 0 |
| C-142 | 1 | 0 |
| C-143 | 1 | 0 |
| C-144 | 1 | 0 |
| C-145 | 1 | 0 |
| F-1 | 1 | 0 |
| F-2 | 1 | 1 |
| F-3 | 1 | 1 |
| F-4 | 1 | 0 |
| F-5 | 1 | 1 |
| F-6 | 1 | 1 |
| F-7 | 1 | 1 |
| F-8 | 1 | 1 |
| F-9 | 1 | 0 |
| F-10 | 1 | 1 |
| F-11 | 1 | 1 |
| F-12 | 1 | 1 |
| F-13 | 1 | 1 |
| F-14 | 1 | 1 |
| F-15 | 1 | 1 |
| F-16 | 1 | 1 |
| F-17 | 1 | 1 |
| F-18 | 1 | 1 |
| F-19 | 1 | 1 |
| F-20 | 1 | 1 |
| F-21 | 1 | 1 |
| F-22 | 1 | 1 |
| F-23 | 1 | 1 |
| F-24 | 1 | 1 |
| F-25 | 1 | 1 |
| F-26 | 1 | 1 |
| F-27 | 1 | 1 |
| F-28 | 1 | 1 |
| F-29 | 1 | 1 |
| F-30 | 1 | 1 |
| F-31 | 1 | 1 |
| F-32 | 1 | 1 |
| F-33 | 1 | 1 |
| F-34 | 1 | 1 |
| F-35 | 1 | 1 |
| F-36 | 1 | 1 |
| F-37 | 1 | 1 |
| F-38 | 1 | 0 |
| F-39 | 1 | 1 |
| F-40 | 1 | 1 |
| F-41 | 1 | 1 |
| F-42 | 1 | 0 |
| F-43 | 1 | 1 |
| F-44 | 1 | 1 |
| F-45 | 1 | 1 |
| F-46 | 1 | 1 |
| F-47 | 1 | 1 |
| F-48 | 1 | 0 |
| F-49 | 1 | 0 |
| F-50 | 1 | 1 |
| F-51 | 1 | 1 |
| F-52 | 1 | 1 |
| F-53 | 1 | 1 |
| F-54 | 1 | 1 |
| F-55 | 1 | 1 |
| F-56 | 1 | 1 |
| F-57 | 1 | 1 |
| F-58 | 1 | 1 |
| F-59 | 1 | 1 |
| F-60 | 1 | 1 |
| F-61 | 1 | 1 |
| F-62 | 1 | 1 |
| F-63 | 1 | 1 |
| F-64 | 1 | 1 |
| F-65 | 1 | 1 |
| F-66 | 1 | 1 |
| F-67 | 1 | 1 |
| F-68 | 1 | 1 |
| F-69 | 1 | 1 |
| F-70 | 1 | 1 |
| F-71 | 1 | 0 |
| F-72 | 1 | 1 |
| F-73 | 1 | 1 |
| F-74 | 1 | 1 |
| F-75 | 1 | 1 |
| F-76 | 1 | 1 |
| F-77 | 1 | 1 |
| F-78 | 1 | 1 |
| F-79 | 1 | 1 |
| F-80 | 1 | 1 |
| F-81 | 1 | 1 |
| F-82 | 1 | 1 |
| F-83 | 1 | 1 |
| F-84 | 1 | 1 |
| F-85 | 1 | 1 |
| F-86 | 1 | 1 |
| E-9 | 1 | 1 |
| E-10 | 1 | 1 |
| E-11 | 1 | 1 |
| E-12 | 1 | 1 |
| E-13 | 1 | 1 |
| E-14 | 1 | 1 |
| E-15 | 1 | 1 |
| E-16 | 1 | 1 |
| E-17 | 1 | 1 |
| E-18 | 1 | 1 |
| E-19 | 1 | 1 |
| E-20 | 1 | 1 |
| E-21 | 1 | 1 |
| E-22 | 1 | 1 |
| E-23 | 1 | 1 |
| E-24 | 1 | 1 |
| E-25 | 1 | 1 |
| E-26 | 1 | 1 |
| E-27 | 1 | 1 |
| E-28 | 1 | 1 |
| E-33 | 1 | 1 |
| E-34 | 1 | 1 |
| E-35 | 1 | 1 |
| E-36 | 1 | 1 |
| E-37 | 1 | 1 |
| E-38 | 1 | 1 |
| E-39 | 1 | 1 |
| E-40 | 1 | 1 |
| E-41 | 1 | 1 |
| E-42 | 1 | 1 |
| E-43 | 1 | 1 |
| E-44 | 1 | 1 |
| E-45 | 1 | 1 |
| E-46 | 1 | 1 |
| E-47 | 1 | 1 |
| E-48 | 1 | 1 |
| E-49 | 1 | 1 |
| E-64 | 1 | 1 |
| E-65 | 1 | 1 |
| E-66 | 1 | 1 |
| E-67 | 1 | 1 |
| E-68 | 1 | 1 |
| E-69 | 1 | 1 |
| E-70 | 1 | 1 |
| E-71 | 1 | 1 |
| E-72 | 1 | 1 |
| E-73 | 1 | 1 |
| E-74 | 1 | 1 |
| E-75 | 1 | 1 |
| E-76 | 1 | 1 |
| E-77 | 1 | 1 |
| E-78 | 1 | 1 |
| E-79 | 1 | 1 |
| E-80 | 1 | 1 |
| E-A-89 | 1 | 1 |
| E-B-89 | 1 | 1 |
| E-C-89 | 1 | 1 |
| E-D-89 | 1 | 1 |
| E-105 | 1 | 1 |
| E-106 | 1 | 1 |
| E-107 | 1 | 1 |
| E-108 | 1 | 1 |
| E-109 | 1 | 1 |
| E-110 | 1 | 1 |
| E-111 | 1 | 1 |
| E-112 | 1 | 1 |
| E-113 | 1 | 1 |
| E-114 | 1 | 1 |
| E-115 | 1 | 1 |
| E-116 | 1 | 1 |
| E-117 | 1 | 1 |
| E-118 | 1 | 1 |
| E-119 | 1 | 1 |
| E-120 | 1 | 1 |
| E-121 | 1 | 1 |
| E-122 | 1 | 1 |
| E-123 | 1 | 1 |
| E-124 | 1 | 0 |
| E-125 | 1 | 1 |
| E-126 | 1 | 1 |
| E-127 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-06-30 | |
| Proposed completion | 2027-06-23 | |
| Revised completion | 2027-10-23 |
Quarterly progress
| 2022-Q3 | 30% |
| 2022-Q4 | 35% |
| 2023-Q1 | 37% |
| 2023-Q2 | 38% |
| 2023-Q3 | 45% |
| 2023-Q4 | 48% |
| 2024-Q1 | 52% |
| 2024-Q2 | 60% |
| 2024-Q3 | 77% |
| 2024-Q4 | 80% |
| 2025-Q1 | 100% |
| 2025-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AVINASH BUILDERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 6 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTgwMA==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities