Overview
B & M LEGACY
SERENITY DEVELOPERS · Krishna
Units80
Completion2027-04-19Proposed
Registered on2021-06-18
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 80 unit types |
| Construction & progress | 2 progress details · 16 quarters |
| Developer & finance | |
| Developer | 2 developer details · 1 professional firm |
| The evidence | |
| Sources | 24 documents · 10 source links |
Registration
Registration
| Promoter | SERENITY DEVELOPERS | |
|---|---|---|
| District | Krishna | |
| Regulator | AP RERA | |
| Registration number | P06170011649 | |
| Registered on | 2021-06-18 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2027-04-19 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1073/1306/B/VMC/MOGR/2020 | 2021-04-19 | Commissioner, ULB |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹55,55,74,666 | |
|---|---|---|
| Construction | ₹54,94,68,560 | |
| Total | ₹1,10,50,43,226 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,293.87 | |
|---|---|---|
| Built-up (m²) | 25,052.94 | |
| Towers | 5 | |
| Units | 80 |
Unit types
| 4BHK | 223.27 | 1 | BLOCK A | FIRST FLOOR |
| 4BHK | 221.11 | 1 | BLOCK A | FIRST FLOOR |
| 4BHK | 226.72 | 1 | BLOCK A | FIRST FLOOR |
| 4BHK | 222.49 | 1 | BLOCK A | FIRST FLOOR |
| 4BHK | 223.27 | 1 | BLOCK A | FOURTH FLOOR |
| 4BHK | 221.11 | 1 | BLOCK A | FOURTH FLOOR |
| 4BHK | 226.72 | 1 | BLOCK A | FOURTH FLOOR |
| 4BHK | 222.49 | 1 | BLOCK A | FOURTH FLOOR |
| 4BHK | 223.27 | 1 | BLOCK A | GROUND FLOOR |
| 4BHK | 221.11 | 1 | BLOCK A | GROUND FLOOR |
| 4BHK | 226.72 | 1 | BLOCK A | GROUND FLOOR |
| 4BHK | 222.49 | 1 | BLOCK A | GROUND FLOOR |
| 4BHK | 223.27 | 1 | BLOCK A | SECOND FLOOR |
| 4BHK | 221.11 | 1 | BLOCK A | SECOND FLOOR |
| 4BHK | 226.72 | 1 | BLOCK A | SECOND FLOOR |
| 4BHK | 222.49 | 1 | BLOCK A | SECOND FLOOR |
| 4BHK | 223.27 | 1 | BLOCK A | THIRD FLOOR |
| 4BHK | 221.11 | 1 | BLOCK A | THIRD FLOOR |
| 4BHK | 226.72 | 1 | BLOCK A | THIRD FLOOR |
| 4BHK | 222.49 | 1 | BLOCK A | THIRD FLOOR |
| 3BHK | 151.49 | 1 | BLOCK B | FIRST FLOOR |
| 3BHK | 148.26 | 1 | BLOCK B | FIRST FLOOR |
| 3BHK | 152.09 | 1 | BLOCK B | FIRST FLOOR |
| 3BHK | 148.08 | 1 | BLOCK B | FIRST FLOOR |
| 3BHK | 151.49 | 1 | BLOCK B | FOURTH FLOOR |
| 3BHK | 148.26 | 1 | BLOCK B | FOURTH FLOOR |
| 3BHK | 152.09 | 1 | BLOCK B | FOURTH FLOOR |
| 3BHK | 148.08 | 1 | BLOCK B | FOURTH FLOOR |
| 3BHK | 151.49 | 1 | BLOCK B | GROUND FLOOR |
| 3BHK | 148.26 | 1 | BLOCK B | GROUND FLOOR |
| 3BHK | 152.09 | 1 | BLOCK B | GROUND FLOOR |
| 3BHK | 148.08 | 1 | BLOCK B | GROUND FLOOR |
| 3BHK | 151.49 | 1 | BLOCK B | SECOND FLOOR |
| 3BHK | 148.26 | 1 | BLOCK B | SECOND FLOOR |
| 3BHK | 152.09 | 1 | BLOCK B | SECOND FLOOR |
| 3BHK | 148.08 | 1 | BLOCK B | SECOND FLOOR |
| 3BHK | 151.49 | 1 | BLOCK B | THIRD FLOOR |
| 3BHK | 148.26 | 1 | BLOCK B | THIRD FLOOR |
| 3BHK | 152.09 | 1 | BLOCK B | THIRD FLOOR |
| 3BHK | 148.08 | 1 | BLOCK B | THIRD FLOOR |
| 3BHK | 151.49 | 1 | BLOCK C | FIRST FLOOR |
| 3BHK | 148.26 | 1 | BLOCK C | FIRST FLOOR |
| 3BHK | 152.09 | 1 | BLOCK C | FIRST FLOOR |
| 3BHK | 148.08 | 1 | BLOCK C | FIRST FLOOR |
| 3BHK | 151.49 | 1 | BLOCK C | FOURTH FLOOR |
| 3BHK | 148.26 | 1 | BLOCK C | FOURTH FLOOR |
| 3BHK | 152.09 | 1 | BLOCK C | FOURTH FLOOR |
| 3BHK | 148.08 | 1 | BLOCK C | FOURTH FLOOR |
| 3BHK | 151.49 | 1 | BLOCK C | GROUND FLOOR |
| 3BHK | 148.26 | 1 | BLOCK C | GROUND FLOOR |
| 3BHK | 152.09 | 1 | BLOCK C | GROUND FLOOR |
| 3BHK | 148.08 | 1 | BLOCK C | GROUND FLOOR |
| 3BHK | 151.49 | 1 | BLOCK C | SECOND FLOOR |
| 3BHK | 148.26 | 1 | BLOCK C | SECOND FLOOR |
| 3BHK | 152.09 | 1 | BLOCK C | SECOND FLOOR |
| 3BHK | 148.08 | 1 | BLOCK C | SECOND FLOOR |
| 3BHK | 151.49 | 1 | BLOCK C | THIRD FLOOR |
| 3BHK | 148.26 | 1 | BLOCK C | THIRD FLOOR |
| 3BHK | 152.09 | 1 | BLOCK C | THIRD FLOOR |
| 3BHK | 148.08 | 1 | BLOCK C | THIRD FLOOR |
| 4BHK | 226.14 | 1 | BLOCK D | FIRST FLOOR |
| 4BHK | 222.28 | 1 | BLOCK D | FIRST FLOOR |
| 4BHK | 226.14 | 1 | BLOCK D | FOURTH FLOOR |
| 4BHK | 222.28 | 1 | BLOCK D | FOURTH FLOOR |
| 4BHK | 226.14 | 1 | BLOCK D | GROUND FLOOR |
| 4BHK | 222.28 | 1 | BLOCK D | GROUND FLOOR |
| 4BHK | 226.14 | 1 | BLOCK D | SECOND FLOOR |
| 4BHK | 222.28 | 1 | BLOCK D | SECOND FLOOR |
| 4BHK | 226.14 | 1 | BLOCK D | THIRD FLOOR |
| 4BHK | 222.28 | 1 | BLOCK D | THIRD FLOOR |
| 4BHK | 223.05 | 1 | BLOCK E | FIRST FLOOR |
| 4BHK | 219 | 1 | BLOCK E | FIRST FLOOR |
| 4BHK | 223.05 | 1 | BLOCK E | FOURTH FLOOR |
| 4BHK | 219 | 1 | BLOCK E | FOURTH FLOOR |
| 4BHK | 223.05 | 1 | BLOCK E | GROUND FLOOR |
| 4BHK | 219 | 1 | BLOCK E | GROUND FLOOR |
| 4BHK | 223.05 | 1 | BLOCK E | SECOND FLOOR |
| 4BHK | 219 | 1 | BLOCK E | SECOND FLOOR |
| 4BHK | 223.05 | 1 | BLOCK E | THIRD FLOOR |
| 4BHK | 219 | 1 | BLOCK E | THIRD FLOOR |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-04-19 | |
|---|---|---|
| Proposed completion | 2027-04-19 |
Quarterly progress
| 2021-Q3 | 2021-10-19 |
| 2021-Q4 | 2022-01-22 |
| 2022-Q1 | 2022-04-22 |
| 2022-Q2 | 2022-07-19 |
| 2022-Q3 | 2022-10-20 |
| 2022-Q4 | 2023-01-19 |
| 2023-Q1 | 2023-04-20 |
| 2023-Q2 | 2023-07-22 |
| 2023-Q3 | 2023-10-08 |
| 2023-Q4 | 2024-01-11 |
| 2024-Q1 | 2024-04-03 |
| 2024-Q2 | 2024-07-15 |
| 2024-Q3 | 2024-10-11 |
| 2024-Q4 | 2025-01-16 |
| 2025-Q1 | 2025-04-06 |
| 2025-Q2 | 2025-07-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SERENITY DEVELOPERS | |
|---|---|---|
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Contractor | SERENITY DEVELOPERS |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFRitwdRro2RiSm4eCW36L1KDkcUsfMxc8hx8nMoX5vJ25QJQ9XSgs7RKizgRcHHInwCkkNsD+/C5IW7uHVkswsADTksQtK2a/w7/j7xrQRlu
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjectClosureReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE