Overview
BALAJI GREEN CITY
SHRI GANPATI CONSTRUCTION · BILASPUR
Units97
Booked45 of 97As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2025-05-30Revised · Proposed 2020-07-31
Registered on2018-06-28
Approvals2
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 30 quarters |
| Technical report | |
| Site & area | 3 site details · 97 unit types |
| Construction & progress | 4 progress details · 30 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 125 documents · 9 source links |
Registration
Registration
| Promoter | SHRI GANPATI CONSTRUCTION | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA280618000357 | |
| Registered on | 2018-06-28 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2020-07-31 | |
| Revised completion | 2025-05-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2024-02143 | CG RERA | Complaint | Disposed | 2024-05-20 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,57,42,000 | |
|---|---|---|
| Construction | ₹1,66,80,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹3,67,500 |
| 2020-Q1 | ₹3,67,500 |
| 2020-Q2 | ₹8,57,500 |
| 2020-Q3 | ₹8,57,500 |
| 2020-Q4 | ₹8,57,500 |
| 2021-Q1 | ₹12,04,000 |
| 2021-Q2 | ₹20,44,000 |
| 2021-Q3 | ₹27,61,500 |
| 2021-Q4 | ₹34,54,500 |
| 2022-Q1 | ₹46,83,000 |
| 2022-Q2 | ₹62,36,608 |
| 2022-Q3 | ₹70,93,023 |
| 2022-Q4 | ₹84,82,650 |
| 2023-Q1 | ₹90,62,494 |
| 2023-Q2 | ₹90,62,494 |
| 2023-Q3 | ₹90,62,494 |
| 2023-Q4 | ₹97,55,488.65 |
| 2024-Q1 | ₹0 |
| 2024-Q2 | ₹4,17,238 |
| 2024-Q3 | ₹4,17,238 |
| 2024-Q4 | ₹4,17,239 |
| 2025-Q1 | ₹10,03,138 |
| 2025-Q2 | ₹10,03,138 |
| 2025-Q3 | ₹10,03,138 |
| 2025-Q4 | ₹10,03,138 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 97 | |
|---|---|---|
| Booked | 45 | |
| Booked as of | 2025-12-31 |
Unit types
| RESIDENTIAL PLOT-1 | 1 | 0 |
| RESIDENTIAL PLOT-2 | 1 | 1 |
| RESIDENTIAL PLOT-3 | 1 | 1 |
| RESIDENTIAL PLOT-4 | 1 | 1 |
| RESIDENTIAL PLOT-5 | 1 | 1 |
| RESIDENTIAL PLOT-6 | 1 | 1 |
| RESIDENTIAL PLOT-7 | 1 | 1 |
| RESIDENTIAL PLOT-8 | 1 | 1 |
| RESIDENTIAL PLOT-9 | 1 | 1 |
| RESIDENTIAL PLOT-10 | 1 | 1 |
| RESIDENTIAL PLOT-11 | 1 | 1 |
| RESIDENTIAL PLOT-12 | 1 | 0 |
| RESIDENTIAL PLOT-13 | 1 | 1 |
| RESIDENTIAL PLOT-14 | 1 | 1 |
| RESIDENTIAL PLOT-15 | 1 | 0 |
| RESIDENTIAL PLOT-16 | 1 | 1 |
| RESIDENTIAL PLOT-17 | 1 | 0 |
| RESIDENTIAL PLOT-18 | 1 | 0 |
| RESIDENTIAL PLOT-19 | 1 | 1 |
| RESIDENTIAL PLOT-20 | 1 | 1 |
| RESIDENTIAL PLOT-21 | 1 | 0 |
| RESIDENTIAL PLOT-22 | 1 | 1 |
| RESIDENTIAL PLOT-23 | 1 | 1 |
| RESIDENTIAL PLOT-24 | 1 | 1 |
| RESIDENTIAL PLOT-25 | 1 | 1 |
| RESIDENTIAL PLOT-26 | 1 | 1 |
| RESIDENTIAL PLOT-27 | 1 | 1 |
| RESIDENTIAL PLOT-28 | 1 | 1 |
| RESIDENTIAL PLOT-29 | 1 | 1 |
| RESIDENTIAL PLOT-30 | 1 | 1 |
| RESIDENTIAL PLOT-31 | 1 | 1 |
| RESIDENTIAL PLOT-32 | 1 | 1 |
| RESIDENTIAL PLOT-33 | 1 | 0 |
| RESIDENTIAL PLOT-34 | 1 | 0 |
| RESIDENTIAL PLOT-35 | 1 | 1 |
| RESIDENTIAL PLOT-36 | 1 | 1 |
| RESIDENTIAL PLOT-37 | 1 | 1 |
| RESIDENTIAL PLOT-38 | 1 | 1 |
| RESIDENTIAL PLOT-39 | 1 | 0 |
| RESIDENTIAL PLOT-40 | 1 | 0 |
| RESIDENTIAL PLOT-41 | 1 | 1 |
| RESIDENTIAL PLOT-42 | 1 | 0 |
| RESIDENTIAL PLOT-43 | 1 | 0 |
| RESIDENTIAL PLOT-44 | 1 | 0 |
| RESIDENTIAL PLOT-45 | 1 | 1 |
| RESIDENTIAL PLOT-46 | 1 | 0 |
| RESIDENTIAL PLOT-47 | 1 | 1 |
| RESIDENTIAL PLOT-48 | 1 | 1 |
| RESIDENTIAL PLOT-49 | 1 | 1 |
| RESIDENTIAL PLOT-50 | 1 | 1 |
| RESIDENTIAL PLOT-51 | 1 | 1 |
| RESIDENTIAL PLOT-52 | 1 | 1 |
| RESIDENTIAL PLOT-53 | 1 | 1 |
| RESIDENTIAL PLOT-54 | 1 | 1 |
| RESIDENTIAL PLOT-55 | 1 | 0 |
| RESIDENTIAL PLOT-56 | 1 | 0 |
| RESIDENTIAL PLOT-57 | 1 | 1 |
| RESIDENTIAL PLOT-58 | 1 | 1 |
| RESIDENTIAL PLOT-59 | 1 | 1 |
| RESIDENTIAL PLOT-60 | 1 | 0 |
| RESIDENTIAL PLOT-61 | 1 | 0 |
| RESIDENTIAL PLOT-62 | 1 | 0 |
| RESIDENTIAL PLOT-63 | 1 | 0 |
| RESIDENTIAL PLOT-64 | 1 | 0 |
| RESIDENTIAL PLOT-65 | 1 | 0 |
| RESIDENTIAL PLOT-66 | 1 | 0 |
| RESIDENTIAL PLOT-67 | 1 | 0 |
| RESIDENTIAL PLOT-68 | 1 | 1 |
| RESIDENTIAL PLOT-69 | 1 | 0 |
| RESIDENTIAL PLOT-70 | 1 | 0 |
| RESIDENTIAL PLOT-71 | 1 | 0 |
| LIG-L 1 | 1 | 0 |
| LIG-L 2 | 1 | 0 |
| LIG-L 3 | 1 | 0 |
| LIG-L 4 | 1 | 0 |
| LIG-L 5 | 1 | 0 |
| LIG-L 6 | 1 | 0 |
| LIG-L 7 | 1 | 0 |
| LIG-L 8 | 1 | 0 |
| LIG-L 9 | 1 | 0 |
| LIG-L 10 | 1 | 0 |
| LIG-L 11 | 1 | 0 |
| LIG-L 12 | 1 | 0 |
| LIG-L 13 | 1 | 0 |
| LIG-L 14 | 1 | 0 |
| LIG-L 15 | 1 | 0 |
| LIG-L 16 | 1 | 0 |
| LIG-L 17 | 1 | 0 |
| LIG-L 18 | 1 | 0 |
| LIG-L 19 | 1 | 0 |
| LIG-L 20 | 1 | 0 |
| LIG-L 21 | 1 | 0 |
| LIG-L 22 | 1 | 0 |
| LIG-L 23 | 1 | 0 |
| LIG-L 24 | 1 | 0 |
| EWS-EWS | 1 | 1 |
| SERVICES-S 1 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-12-31 | |
| Proposed completion | 2020-07-31 | |
| Revised completion | 2025-05-30 |
Quarterly progress
| 2018-Q3 | 33% |
| 2018-Q4 | 33% |
| 2019-Q1 | 33% |
| 2019-Q2 | 33% |
| 2019-Q3 | 60% |
| 2019-Q4 | 60% |
| 2020-Q1 | 60% |
| 2020-Q2 | 60% |
| 2020-Q3 | 61% |
| 2020-Q4 | 61% |
| 2021-Q1 | 62% |
| 2021-Q2 | 62% |
| 2021-Q3 | 62% |
| 2021-Q4 | 62% |
| 2022-Q1 | 69% |
| 2022-Q2 | 69% |
| 2022-Q3 | 69% |
| 2022-Q4 | 74% |
| 2023-Q1 | 84% |
| 2023-Q2 | 90% |
| 2023-Q3 | 90% |
| 2023-Q4 | 90% |
| 2024-Q1 | 90% |
| 2024-Q2 | 93% |
| 2024-Q3 | 95% |
| 2024-Q4 | 98% |
| 2025-Q1 | 99% |
| 2025-Q2 | 99% |
| 2025-Q3 | 99% |
| 2025-Q4 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHRI GANPATI CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NDQ0
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2024-05-20 · Sign in to download
- Interim order · 2024-04-19 · Sign in to download
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities
- SM-EXP-2024-02143 · Sign in to download