Overview
BALAJI PLAZA
BANSAL GUDAKHU UDYOG · BILASPUR
Construction progress100%As of 2021-03-31
Completion2024-04-30Revised · Proposed 2023-07-31
Registered on2018-12-14
Approvals3
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 10 quarters |
| Technical report | |
| Site & area | 1 unit type |
| Construction & progress | 4 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 78 documents · 8 source links |
Registration
Registration
| Promoter | BANSAL GUDAKHU UDYOG | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA141218000872 | |
| Registered on | 2018-12-14 | |
| Project type | Commercial | |
| Status (as filed) | New | |
| Proposed completion | 2023-07-31 | |
| Revised completion | 2024-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2024-02460 | CG RERA | Complaint | Disposed | 2024-07-26 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,24,20,000 | |
|---|---|---|
| Construction | ₹6,22,11,000 |
Quarterly money flows
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹24,95,500 |
| 2019-Q2 | ₹10,08,000 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹10,82,200 |
| 2020-Q1 | ₹7,28,000 |
| 2020-Q2 | ₹15,84,100 |
| 2020-Q3 | ₹1,06,750 |
| 2020-Q4 | ₹13,68,500 |
| 2021-Q1 | ₹31,49,650 |
Site & area
What does the land measure?
Site & area
Unit types
| Type | Carpet (m²) | Units | Booked |
|---|---|---|---|
| Commercial | 3,718.06 | 118 | 98 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2021-03-31 | |
| Proposed completion | 2023-07-31 | |
| Revised completion | 2024-04-30 |
Quarterly progress
| 2018-Q4 | 0% |
| 2019-Q1 | 4% |
| 2019-Q2 | 23% |
| 2019-Q3 | 27% |
| 2019-Q4 | 45% |
| 2020-Q1 | 56% |
| 2020-Q2 | 62% |
| 2020-Q3 | 79% |
| 2020-Q4 | 93% |
| 2021-Q1 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BANSAL GUDAKHU UDYOG | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Kotak Mahindra Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=OTgw
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2024-07-26 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- SM-EXP-2024-02460 · Sign in to download