Overview
BANGARI GUDDADAMANE LAYOUT
GOPAL BANGARI GUDDADAMANE · Uttara Kannada
Construction progress100%
Completion2026-12-31Proposed
Registered on2026-02-10
Valid to2026-12-31
Approvals12
Complaints0
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 3 cost heads · 2 quarters |
| Technical report | |
| Construction & progress | 3 progress details · 2 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 105 documents · 15 source links |
Registration
Registration
| Promoter | GOPAL BANGARI GUDDADAMANE | |
|---|---|---|
| District | Uttara Kannada | |
| Regulator | K-RERA | |
| Registration number | PRM/KA/RERA/1274/352/PR/100226/008462 | |
| Registered on | 2026-02-10 | |
| Valid to | 2026-12-31 | |
| Project type | Plotted Development | |
| Status (as filed) | APPROVED | |
| Proposed completion | 2026-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approved Plan | 17/2024-25/339-40 | 2024-09-26 | Sirsi Planning Authority |
| Approval Layout Order / Technical Sanction Letter ( Annexure - 76 ) | |||
| NOC from ESCOMs ( Annexure - 95 ) | |||
| NOC for Water ( Annexure - 96 ) | |||
| 3 Horticulture NOC | |||
| 3 Panchayath Work Completion NOC | |||
| 3 Water and Electricity NOC | |||
| Water NOC | |||
| 8 Panchayath Work Completion NOC | |||
| 9 Horticulture NOC | |||
| Completion Certificate | |||
| NOC from Grama Panchayath |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹10,66,296 | |
|---|---|---|
| Construction | ₹20,10,000 | |
| Total | ₹42,07,553 |
Quarterly money flows
| Quarter | Received |
|---|---|
| 2025-26-Q4 | ₹0 |
| 2026-27-Q1 | ₹0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| Start | 2024-10-01 | |
| Proposed completion | 2026-12-31 |
Quarterly progress
| Quarter | Filed on | Progress |
|---|---|---|
| 2025-26-Q4 | 2026-07-13 | 99% |
| 2026-27-Q1 | 2026-07-13 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GOPAL BANGARI GUDDADAMANE | |
|---|---|---|
| Type | Individual | |
| Escrow bank | YES BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://mahitikanaja.karnataka.gov.in/Rera/api/Rera/ProjectViewDetails
- https://rera.karnataka.gov.in/projectDetails
- https://rera.karnataka.gov.in/projectViewDetails
- https://rera.karnataka.gov.in/viewAllProjects?language=en
- Registration Certificate ( Annexure - 1 )
- Other · Sign in to download
- GST Certificate ( Annexure - 3 ) · Sign in to download
- Other · Sign in to download
- Board Resolution for Authorized Signatory/Certificate of Authorization ( Annexure - 5 ) · Sign in to download
- Other · Sign in to download
- Certificate issued by CA Form 1 ( Annexure - 59 ) · Sign in to download
- Certificate issued by Engineer Form 3 ( Annexure - 60 ) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Balance Sheet ( Annexure - 70 ) · Sign in to download
- Balance Sheet ( Annexure - 70 ) · Sign in to download
- Balance Sheet ( Annexure - 70 ) · Sign in to download
- Audited Profit and Loss Statement ( Annexure - 71 ) · Sign in to download
- Audited Profit and Loss Statement ( Annexure - 71 ) · Sign in to download
- Audited Profit and Loss Statement ( Annexure - 71 ) · Sign in to download
- Income Tax Return Acknowledgement ( Annexure - 72 ) · Sign in to download
- Income Tax Return Acknowledgement ( Annexure - 72 ) · Sign in to download
- Income Tax Return Acknowledgement ( Annexure - 72 ) · Sign in to download
- Approval Layout Order / Technical Sanction Letter ( Annexure - 76 )
- Approved Layout Plan/Demarcation Plan ( Annexure - 77 )
- Project Specifications ( Annexure - 84 ) · Sign in to download
- Brochure ( Annexure - 85 ) · Sign in to download
- Declaration (Form B) ( Annexure - 89 ) · Sign in to download
- Advocate Search Report ( Annexure - 92 ) · Sign in to download
- NOC from ESCOMs ( Annexure - 95 )
- NOC for Water ( Annexure - 96 )
- KSPCB (If Applicable) ( Annexure - 97 ) · Sign in to download
- SEIAA (If Applicable) ( Annexure - 98 ) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Document ( Annexure - 113 ) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- 1 Registration Certificate · 2025-10-30
- Financial_Compilation Report_Gopal_Bangari_2025 · 2025-10-30 · Sign in to download
- Form 1 Bangari Guddadamane Layout · 2025-10-30 · Sign in to download
- Form 1 Bangari Guddadamane Layout · 2025-10-30 · Sign in to download
- Land Tribunal Order - 12-04-1977 · 2025-10-30 · Sign in to download
- Other · 2025-10-30 · Sign in to download
- Other · 2025-10-30 · Sign in to download
- Approved Plan - Gopal guddadamane · 2025-10-30
- Other · 2025-10-30 · Sign in to download
- 3 HESCOM execution and Work Completion Cert · 2025-10-30 · Sign in to download
- 3 Horticulture NOC · 2025-10-30
- 3 Panchayath Work Completion NOC · 2025-10-30
- 3 Water and Electricity NOC · 2025-10-30
- Water NOC · 2025-10-30
- 5 CDP Demarcation - Sirsi Master Plan · 2025-10-30
- Other · 2025-10-30 · Sign in to download
- Other · 2025-10-30 · Sign in to download
- Other · 2025-12-05 · Sign in to download
- 2 Project Photos with GPS · 2025-12-05 · Sign in to download
- Other · 2025-12-05 · Sign in to download
- 4 HESCOM execution and Work Completion Cert · 2025-12-05 · Sign in to download
- Other · 2025-12-05 · Sign in to download
- 7 CDP Demarcation - Sirsi Master Plan · 2025-12-05
- 8 Panchayath Work Completion NOC · 2025-12-05
- 9 Horticulture NOC · 2025-12-05
- Other · Sign in to download
- Form-4 Certificate issued by Chartered Accountant · 2026-07-13
- Form-6 Certificate issued by Structural Engineer · 2026-07-13
- Other · 2026-07-13 · Sign in to download
- Other · 2026-07-13 · Sign in to download
- Other · 2026-07-13 · Sign in to download
- Form-4 Certificate issued by Chartered Accountant · 2026-07-13
- Form-6 Certificate issued by Structural Engineer · 2026-07-13
- Other · 2026-07-13 · Sign in to download
- Other · 2026-07-13 · Sign in to download
- Other · 2026-07-13 · Sign in to download
- Final plan technical sanction Letter
- Final layout plan sanctioned
- Completion Certificate
- Site release order Copies(1st,2nd phase and final release order) · Sign in to download
- Certificate issued by P.W.D/ Panchayath Raj/Urban Local Bodies for completion of Road · Sign in to download
- Certificate issued by the Karnataka Urban Water supply · Sign in to download
- Certificate issued by the concerned power supply(ESCOM'S) · Sign in to download
- Certificate issued by KSPCB, consent for operation of STP plant
- Other · Sign in to download
- Brief description of Water supply and Underground drainage works · Sign in to download
- Whether the transformer has been erected within layout and copy of power sanctioned to the layout issued by ESCOM's · Sign in to download
- Chartered Accountant Certificate (Form-4)
- Architect's Certificate (Form-5)
- Engineer's Certificate (Form-6)
- Engineer's Certificate (Form-6)
- NOC from Grama Panchayath
- Registration certificate
- Registration Certificate
- Approval Layout Order / Technical Sanction Letter ( Annexure - 76 )
- NOC from ESCOMs ( Annexure - 95 )
- NOC for Water ( Annexure - 96 )
- 3 Horticulture NOC
- 3 Panchayath Work Completion NOC
- 3 Water and Electricity NOC
- Water NOC
- 8 Panchayath Work Completion NOC
- 9 Horticulture NOC
- Completion Certificate
- NOC from Grama Panchayath