Overview
BCC GREENS
ATTRACTIVE NIRMAN PRIVATE LIMITED · Lucknow
Units1,056
Completion2022-03-18Revised · Proposed 2021-09-19
Registered on2018-04-11
Valid to2022-03-18
Approvals6
Complaints41As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Disputes & cases | 41 project complaints · 49 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 60 unit types |
| Construction & progress | 3 progress details · 8 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 24 documents · 15 source links |
Registration
Registration
| Promoter | ATTRACTIVE NIRMAN PRIVATE LIMITED | |
|---|---|---|
| District | Lucknow | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ15533 | |
| Registered on | 2018-04-11 | |
| Valid to | 2022-03-18 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2021-09-19 | |
| Revised completion | 2022-03-18 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Original permit | 337 | 2013-09-20 | 2018-09-19 | Any Other Competent Authority |
| Original permit | 337 | 2013-09-20 | 2018-09-19 | Any Other Competent Authority |
| Original permit | 337 | 2013-09-20 | 2018-09-19 | Any Other Competent Authority |
| Revalidated permit | 337 | 2013-09-20 | 2018-09-19 | Any Other Competent Authority |
| Original permit | 337 | 2013-09-20 | 2018-09-19 | Any Other Competent Authority |
| Revalidated permit | 337 | 2013-09-20 | Any Other Competent Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 41 | |
|---|---|---|
| Promoter | 49 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹97,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 20,680 | |
|---|---|---|
| Towers | 5 | |
| Maximum floors | 12 | |
| Units | 1,056 |
Unit types
| 1 BHK | 43.587 | 24 | A | 1 |
| 1 BHK | 43.587 | 24 | A | 2 |
| 1 BHK | 43.587 | 24 | A | 3 |
| 1 BHK | 43.587 | 24 | A | 4 |
| 1 BHK | 43.587 | 24 | A | 5 |
| 1 BHK | 43.587 | 24 | A | 6 |
| 1 BHK | 43.587 | 24 | A | 7 |
| 1 BHK | 43.587 | 24 | A | 8 |
| 1 BHK | 43.587 | 24 | A | 9 |
| 1 BHK | 43.587 | 24 | A | 10 |
| 1 BHK | 43.587 | 24 | A | 11 |
| 1 BHK | 43.587 | 24 | A | 12 |
| 2 BHK | 64.149 | 18 | B | 1 |
| 2 BHK | 64.149 | 18 | B | 2 |
| 2 BHK | 64.149 | 18 | B | 3 |
| 2 BHK | 64.149 | 18 | B | 4 |
| 2 BHK | 64.149 | 18 | B | 5 |
| 2 BHK | 64.149 | 18 | B | 6 |
| 2 BHK | 64.149 | 18 | B | 7 |
| 2 BHK | 64.149 | 18 | B | 8 |
| 2 BHK | 64.149 | 18 | B | 9 |
| 2 BHK | 64.149 | 18 | B | 10 |
| 2 BHK | 64.149 | 18 | B | 11 |
| 2 BHK | 64.149 | 18 | B | 12 |
| 2 BHK | 64.149 | 18 | C | 1 |
| 2 BHK | 64.149 | 18 | C | 2 |
| 2 BHK | 64.149 | 18 | C | 3 |
| 2 BHK | 64.149 | 18 | C | 4 |
| 2 BHK | 64.149 | 18 | C | 5 |
| 2 BHK | 64.149 | 18 | C | 6 |
| 2 BHK | 64.149 | 18 | C | 7 |
| 2 BHK | 64.149 | 18 | C | 8 |
| 2 BHK | 64.149 | 18 | C | 9 |
| 2 BHK | 64.149 | 18 | C | 10 |
| 2 BHK | 64.149 | 18 | C | 11 |
| 2 BHK | 64.149 | 18 | C | 12 |
| 3 BHK | 86.52 | 14 | D | 1 |
| 3 BHK | 86.52 | 14 | D | 2 |
| 3 BHK | 85.24 | 14 | D | 3 |
| 3 BHK | 86.52 | 14 | D | 4 |
| 3 BHK | 86.52 | 14 | D | 5 |
| 3 BHK | 86.52 | 14 | D | 6 |
| 3 BHK | 86.52 | 14 | D | 7 |
| 3 BHK | 86.52 | 14 | D | 8 |
| 3 BHK | 86.52 | 14 | D | 9 |
| 3 BHK | 86.52 | 14 | D | 10 |
| 3 BHK | 86.52 | 14 | D | 11 |
| 3 BHK | 86.52 | 14 | D | 12 |
| 3 BHK | 86.52 | 14 | E | 1 |
| 3 BHK | 86.52 | 14 | E | 2 |
| 3 BHK | 86.52 | 14 | E | 3 |
| 3 BHK | 86.52 | 14 | E | 4 |
| 3 BHK | 86.52 | 14 | E | 5 |
| 3 BHK | 86.52 | 14 | E | 6 |
| 3 BHK | 86.52 | 14 | E | 7 |
| 3 BHK | 86.52 | 14 | E | 8 |
| 3 BHK | 86.52 | 14 | E | 9 |
| 3 BHK | 86.52 | 14 | E | 10 |
| 3 BHK | 86.52 | 14 | E | 11 |
| 3 BHK | 86.52 | 14 | E | 12 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2014-01-07 | |
|---|---|---|
| Proposed completion | 2021-09-19 | |
| Revised completion | 2022-03-18 |
Quarterly progress
| 2020-Q2 | 100% |
| 2020-Q3 | 100% |
| 2020-Q4 | 100% |
| 2021-Q1 | 100% |
| 2021-Q2 | 100% |
| 2021-Q3 | 100% |
| 2021-Q4 | 100% |
| 2022-Q1 | 100% |
Extensions
| Valid to | Reason |
|---|---|
| 2022-03-18 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ATTRACTIVE NIRMAN PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=yXlQOwcuRog=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=WrOtKWyFLbt/0XUJYt5EIw==&PaURJEMAN4=ZL9MNERkNdZ/1DmmcQ4pjg==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=LUCKNOW
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=yXlQOwcuRog=
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- 2020-Q2
- 2020-Q3
- 2020-Q4
- 2021-Q1
- 2021-Q2
- 2021-Q3
- 2021-Q4
- 2022-Q1