Overview
BD ENCLAVE
BD DEVELOPERS · Gurdaspur
Units111
Completion2030-12-17Proposed
Valid to2030-12-17
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 19 unit types |
| Construction & progress | 2 progress details · 3 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 29 documents · 18 source links |
Registration
Registration
| Promoter | BD DEVELOPERS | |
|---|---|---|
| District | Gurdaspur | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-GSP27-PR1329 | |
| Valid to | 2030-12-17 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2030-12-17 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | Permissions (Applied) | 2025-12-26 |
| License as Promoter from competent Authority | 2025-02-11 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2025-05-14 |
| NOC from NHAI/ PWD | Permissions (Received) | 2025-06-10 |
| Other Document (Affidavit cum Declaration regarding NOCs) | Legal Documents (Received) | 2025-12-26 |
| Other Document (Application for exemption reg. AAI HT NOC) | Legal Documents (Received) | 2026-02-04 |
| Other Document (NOC from ADC Development, Gurdaspur) | Permissions (Received) | 2025-06-09 |
| Other Document (NOC from Forest Department) | Permissions (Received) | 2026-01-19 |
| Other Document (Regarding Drainage Department NOC) | Permissions (Received) | 2026-01-19 |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Applied) | 2026-01-06 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹8,39,20,063 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 22,206.93 | |
|---|---|---|
| Units | 111 |
Unit types
| Plot No.1 | 90.11 | 1 | RESIDENTIAL PLOTS |
| Plot No.2 | 91.97 | 1 | RESIDENTIAL PLOTS |
| Plot No.3 | 102 | 1 | RESIDENTIAL PLOTS |
| Plot No.4 to 13 | 1,254.18 | 10 | RESIDENTIAL PLOTS |
| Plot No.14 | 122.75 | 1 | RESIDENTIAL PLOTS |
| Plot No.15 to 42 | 3,511.7 | 28 | RESIDENTIAL PLOTS |
| Plot No.43 to 72 | 3,762.54 | 30 | RESIDENTIAL PLOTS |
| Plot No.73 | 111.47 | 1 | RESIDENTIAL PLOTS |
| Plot No.74 to 101 | 3,511.7 | 28 | RESIDENTIAL PLOTS |
| Plot No.102 | 111.47 | 1 | RESIDENTIAL PLOTS |
| Plot No.103 | 89.04 | 1 | RESIDENTIAL PLOTS |
| Plot No.104 | 92.6 | 1 | RESIDENTIAL PLOTS |
| Plot No.105 | 96.15 | 1 | RESIDENTIAL PLOTS |
| Plot No.106 | 99.49 | 1 | RESIDENTIAL PLOTS |
| Plot No.107 | 103.05 | 1 | RESIDENTIAL PLOTS |
| Plot No.108 | 106.6 | 1 | RESIDENTIAL PLOTS |
| Plot No.109 | 110.05 | 1 | RESIDENTIAL PLOTS |
| Plot No.110 | 113.6 | 1 | RESIDENTIAL PLOTS |
| Plot No.111 | 107.05 | 1 | RESIDENTIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-12-18 | |
|---|---|---|
| Proposed completion | 2030-12-17 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2026-Q1 | 2026-04-16 |
| 2026-Q2 | 2026-07-13 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BD DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12609&inPromoter_ID=3523&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-12-26
- License as Promoter from competent Authority · 2025-02-11
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2025-05-14
- NOC from NHAI/ PWD · 2025-06-10
- Other Document (Application for exemption reg. AAI HT NOC) · 2026-02-04
- Other Document (Application for exemption reg. EC) · 2025-12-22 · Sign in to download
- Other Document (Architect Certificate for HT and EC) · 2026-01-02 · Sign in to download
- Other Document (NOC from ADC Development, Gurdaspur) · 2025-06-09
- Other Document (NOC from Forest Department) · 2026-01-19
- Other Document (Regarding Drainage Department NOC) · 2026-01-19
- Other Document (Reply to observation ) · 2026-02-04 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2026-01-06
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2025-12-26
- License as Promoter from competent Authority · 2025-02-11
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2025-05-14
- NOC from NHAI/ PWD · 2025-06-10
- Other Document (Affidavit cum Declaration regarding NOCs) · 2025-12-26
- Other Document (Application for exemption reg. AAI HT NOC) · 2026-02-04
- Other Document (NOC from ADC Development, Gurdaspur) · 2025-06-09
- Other Document (NOC from Forest Department) · 2026-01-19
- Other Document (Regarding Drainage Department NOC) · 2026-01-19
- Pollution Clearance from Punjab Pollution Control Board · 2026-01-06
- 2026-Q1 · 2026-04-16
- 2026-Q2 · 2026-07-13
- 2026-Q3 · 2026-10-15