Overview
Beverly Golf Avenue-Phase-1
MB Infrabuild Private Limited · Sahibzada Ajit Singh Nagar (Mohali)
Units255
Booked240 of 255As of 2026-03-31
Completion2021-07-31Proposed
Registered on2017-09-22
Valid to2021-07-31
Approvals16
Sections
| Property title & search report | |
|---|---|
| Approvals | 16 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details · 9 unit types |
| Construction & progress | 2 progress details · 24 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 64 documents · 42 source links |
Registration
Registration
| Promoter | MB Infrabuild Private Limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0111 | |
| Registered on | 2017-09-22 | |
| Valid to | 2021-07-31 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2021-07-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2021-11-05 | |
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2016-11-30 | |
| CLU Certificate | ||
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | Amendments (Received) | 2022-07-15 |
| Environment Clearance certificate/ NOC | Amendments (Received) | 2022-07-15 |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2022-07-15 |
| License as Promoter from competent Authority | 2016-03-20 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2024-07-05 | |
| NOC from Fire Department/ Chief Fire Officer | 2018-01-02 | |
| NOC from Mining Department | Permissions (Received) | 2016-04-07 |
| Other Document (PSPCL NOC) | 2022-01-21 | |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Received) | 2018-03-26 |
| Pollution Clearance from Punjab Pollution Control Board | 2024-08-28 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-08-28 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹2,67,02,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,661.33 | |
|---|---|---|
| Towers | 9 | |
| Maximum floors | 12 | |
| Units | 255 | |
| Booked | 240 | |
| Booked as of | 2026-03-31 |
Unit types
| Commercial Shops | 663.453 | 13 | 8 | TOWER 1 |
| 2BHK/3BHK/PENTHOUSE | 5,232.114 | 44 | 43 | TOWER 1 |
| 2BHK/3BHK/PENTHOUSE | 3,315.439 | 22 | 22 | TOWER 10 |
| 2BHK/3BHK/PENTHOUSE | 3,315.439 | 22 | 22 | TOWER 11 |
| 2BHK/3BHK/PENTHOUSE | 3,315.439 | 22 | 22 | TOWER 12 |
| 2BHK/3BHK/PENTHOUSE | 3,294.387 | 22 | 22 | TOWER 13 |
| 2BHK/3BHK/PENTHOUSE | 3,315.439 | 22 | 22 | TOWER 14 |
| 2BHK/3BHK/PENTHOUSE | 5,234.716 | 44 | 39 | TOWER 2 |
| 2BHK/3BHK/PENTHOUSE | 5,234.716 | 44 | 40 | TOWER 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-04-07 | |
|---|---|---|
| Proposed completion | 2021-07-31 |
Quarterly progress
| 2020-Q2 | 2020-11-24 | ||
| 2020-Q3 | 2021-01-29 | ||
| 2020-Q4 | 2021-05-04 | ||
| 2021-Q1 | 2021-08-31 | ||
| 2021-Q2 | 2021-09-30 | ||
| 2021-Q3 | 2021-12-25 | ||
| 2021-Q4 | 2022-04-02 | ||
| 2022-Q1 | 2022-07-20 | ||
| 2022-Q2 | 2022-11-26 | ||
| 2022-Q3 | 2022-12-16 | ||
| 2022-Q4 | 2023-02-08 | ||
| 2023-Q1 | 2023-06-30 | ||
| 2023-Q2 | 2023-08-16 | ||
| 2023-Q3 | 2023-10-27 | ||
| 2023-Q4 | 2024-02-27 | ||
| 2024-Q1 | 2024-09-03 | ||
| 2024-Q2 | 2024-10-30 | ||
| 2024-Q3 | 2025-02-07 | ||
| 2024-Q4 | 2025-03-11 | ||
| 2025-Q1 | 2025-07-17 | ||
| 2025-Q2 | 2025-09-28 | ||
| 2025-Q3 | 2025-10-28 | ||
| 2025-Q4 | 2026-01-17 | ||
| 2026-Q1 | 2026-07-16 | 0 | 4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MB Infrabuild Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=10446&inPromoter_ID=1342&inPromoterType=10446&inQUProject_ID=3723&inQUProject_DN=QUP2026F20263723&inQUProjectYear=2026&inQUProjectQTR=FirstQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10446&inPromoter_ID=1342&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2021-11-05
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2016-11-30
- Borewell Registration certificate from Central Ground Water Authority · 2024-10-25
- Borewell Registration certificate from Central Ground Water Authority · 2015-12-03
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2022-07-15
- Environment Clearance certificate/ NOC · 2022-07-15
- Environment Clearance certificate/ NOC · 2022-07-15
- License as Promoter from competent Authority · 2016-03-20
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-07-05
- NOC from Fire Department/ Chief Fire Officer · 2018-01-02
- NOC from Mining Department · 2016-04-07
- Other Document (PSPCL NOC) · 2022-01-21
- Pollution Clearance from Punjab Pollution Control Board · 2018-03-26
- Pollution Clearance from Punjab Pollution Control Board · 2024-08-28
- Pollution Clearance from Punjab Pollution Control Board · 2024-08-28
- Consent details of actual owner of Land · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2021-11-05
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2016-11-30
- CLU Certificate
- CLU Certificate
- Environment Clearance certificate/ NOC · 2022-07-15
- Environment Clearance certificate/ NOC · 2022-07-15
- Environment Clearance certificate/ NOC · 2022-07-15
- License as Promoter from competent Authority · 2016-03-20
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-07-05
- NOC from Fire Department/ Chief Fire Officer · 2018-01-02
- NOC from Mining Department · 2016-04-07
- Other Document (PSPCL NOC) · 2022-01-21
- Pollution Clearance from Punjab Pollution Control Board · 2018-03-26
- Pollution Clearance from Punjab Pollution Control Board · 2024-08-28
- Pollution Clearance from Punjab Pollution Control Board · 2024-08-28
- 2020-Q2 · 2020-11-24
- 2020-Q3 · 2021-01-29
- 2020-Q4 · 2021-05-04
- 2021-Q1 · 2021-08-31
- 2021-Q2 · 2021-09-30
- 2021-Q3 · 2021-12-25
- 2021-Q4 · 2022-04-02
- 2022-Q1 · 2022-07-20
- 2022-Q2 · 2022-11-26
- 2022-Q3 · 2022-12-16
- 2022-Q4 · 2023-02-08
- 2023-Q1 · 2023-06-30
- 2023-Q2 · 2023-08-16
- 2023-Q3 · 2023-10-27
- 2023-Q4 · 2024-02-27
- 2024-Q1 · 2024-09-03
- 2024-Q2 · 2024-10-30
- 2024-Q3 · 2025-02-07
- 2024-Q4 · 2025-03-11
- 2025-Q1 · 2025-07-17
- 2025-Q2 · 2025-09-28
- 2025-Q3 · 2025-10-28
- 2025-Q4 · 2026-01-17