Overview
Beverly Golf Avenue Phase-2
MB Infrabuild Private Limited · Sahibzada Ajit Singh Nagar (Mohali)
Units172
Completion2023-07-31Proposed
Valid to2026-01-30
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 6 unit types |
| Construction & progress | 2 progress details · 24 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 20 documents · 35 source links |
Registration
Registration
| Promoter | MB Infrabuild Private Limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0451 | |
| Valid to | 2026-01-30 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2023-07-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2016-11-30 | |
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | Clearances (Received) | 2016-03-21 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2018-01-02 | |
| NOC from Mining Department | Permissions (Received) | 2016-04-07 |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Received) | 2018-03-26 |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹2,27,11,26,214 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 13,164.42 | |
|---|---|---|
| Towers | 6 | |
| Maximum floors | 11 | |
| Units | 172 |
Unit types
| 2BHK/3BHK/PENTHOUSE | 5,138.29 | 44 | TOWER 4 |
| 3BHK, 4BHK PENTHOUSE | 5,234.738 | 44 | TOWER 5 |
| 3BHK/4BHK/PENTHOUSE | 4,003.809 | 22 | TOWER 6 |
| 3BHK/4BHK/PENTHOUSE | 3,829.706 | 20 | TOWER 7 |
| 3BHK/4BHK/PENTHOUSE | 3,829.706 | 20 | TOWER 8 |
| 3BHK/4BHK/PENTHOUSE | 4,003.809 | 22 | TOWER 9 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-10-01 | |
|---|---|---|
| Proposed completion | 2023-07-31 |
Quarterly progress
| 2020-Q2 | 2020-11-24 |
| 2020-Q3 | 2021-01-29 |
| 2020-Q4 | 2021-05-04 |
| 2021-Q1 | 2021-08-31 |
| 2021-Q2 | 2021-09-30 |
| 2021-Q3 | 2021-12-25 |
| 2021-Q4 | 2022-04-02 |
| 2022-Q1 | 2022-07-20 |
| 2022-Q2 | 2022-11-28 |
| 2022-Q3 | 2022-12-16 |
| 2022-Q4 | 2023-02-08 |
| 2023-Q1 | 2023-06-30 |
| 2023-Q2 | 2023-08-16 |
| 2023-Q3 | 2023-10-27 |
| 2023-Q4 | 2024-04-29 |
| 2024-Q1 | 2024-09-03 |
| 2024-Q2 | 2024-10-29 |
| 2024-Q3 | 2025-02-07 |
| 2024-Q4 | 2025-02-13 |
| 2025-Q1 | 2025-07-17 |
| 2025-Q2 | 2025-09-28 |
| 2025-Q3 | 2025-10-28 |
| 2025-Q4 | 2026-01-17 |
| 2026-Q1 | 2026-06-18 |
Extensions
| Valid to |
|---|
| 2026-01-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MB Infrabuild Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES Bank Limited | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10646&inPromoter_ID=1342&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2016-11-30
- Borewell Registration certificate from Central Ground Water Authority · 2015-12-03
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2016-03-21
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-01-02
- NOC from Mining Department · 2016-04-07
- Pollution Clearance from Punjab Pollution Control Board · 2018-03-26
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Extension of Registration Certificate · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2016-11-30
- CLU Certificate
- Environment Clearance certificate/ NOC · 2016-03-21
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-01-02
- NOC from Mining Department · 2016-04-07
- Pollution Clearance from Punjab Pollution Control Board · 2018-03-26
- Consent details of actual owner of Land
- Extension order · Sign in to download
- 2020-Q2 · 2020-11-24
- 2020-Q3 · 2021-01-29
- 2020-Q4 · 2021-05-04
- 2021-Q1 · 2021-08-31
- 2021-Q2 · 2021-09-30
- 2021-Q3 · 2021-12-25
- 2021-Q4 · 2022-04-02
- 2022-Q1 · 2022-07-20
- 2022-Q2 · 2022-11-28
- 2022-Q3 · 2022-12-16
- 2022-Q4 · 2023-02-08
- 2023-Q1 · 2023-06-30
- 2023-Q2 · 2023-08-16
- 2023-Q3 · 2023-10-27
- 2023-Q4 · 2024-04-29
- 2024-Q1 · 2024-09-03
- 2024-Q2 · 2024-10-29
- 2024-Q3 · 2025-02-07
- 2024-Q4 · 2025-02-13
- 2025-Q1 · 2025-07-17
- 2025-Q2 · 2025-09-28
- 2025-Q3 · 2025-10-28
- 2025-Q4 · 2026-01-17
- 2026-Q1 · 2026-06-18