Overview
BHAGAYA GIRI APARTMENTS
NUTAN REALTORS PRIVATE LIMITED · Patna
Units47
Completion2020-10-27Proposed
Registered on2021-09-14
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 13 unit types |
| Construction & progress | 2 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 31 documents · 20 source links |
Registration
Registration
| Promoter | NUTAN REALTORS PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00640-1/491/R-337/2019 | |
| Registered on | 2021-09-14 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2020-10-27 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,20,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,916.62 | |
|---|---|---|
| Built-up (m²) | 4,425.65 | |
| FAR | 2.31 | |
| Towers | 3 | |
| Units | 47 |
Unit types
| 2.5 BHK | 1 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 2 BHK | 8 | BHAGYA GIRI APARTMENT |
| 2.5 BHK | 1 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 2.5 BHK | 1 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
| 3 BHK | 4 | BHAGYA GIRI APARTMENT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2013-12-27 | |
|---|---|---|
| Proposed completion | 2020-10-27 |
Quarterly progress
| 2025-Q1 | 2025-04-22 |
| 2024-Q4 | 2025-01-15 |
| 2024-Q3 | 2024-10-15 |
| 2024-Q2 | 2024-07-12 |
| 2024-Q1 | 2024-07-25 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-15 |
| 2022-Q4 | 2023-01-14 |
| 2022-Q3 | 2022-11-22 |
| 2022-Q2 | 2022-11-22 |
| 2022-Q1 | 2022-03-09 |
| 2021-Q4 | 2022-11-30 |
| 2021-Q3 | 2022-11-30 |
| 2021-Q1 | 2021-04-16 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | NUTAN REALTORS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP247201800640-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP247201800640-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2024-2025 · 2025-04-22
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-07-12
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-15
- Q3-Oct to Dec / 2022-2023 · 2023-01-14
- Q2-Jul to Sep / 2022-2023 · 2022-11-22
- Q1-Apr to Jun / 2022-2023 · 2022-11-22
- Q4-Jan to Mar / 2021-2022 · 2022-03-09
- Q3-Oct to Dec / 2021-2022 · 2022-11-30
- Q2-Jul to Sep / 2021-2022 · 2022-11-30
- Q4-Jan to Mar / 2020-2021 · 2021-04-16
- 2025-Q1 · 2025-04-22
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-07-12
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-15
- 2022-Q4 · 2023-01-14
- 2022-Q3 · 2022-11-22
- 2022-Q2 · 2022-11-22
- 2022-Q1 · 2022-03-09
- 2021-Q4 · 2022-11-30
- 2021-Q3 · 2022-11-30
- 2021-Q1 · 2021-04-16