Overview
BHAGWAN KAILASH AWAS
KOSUT BUILDERS AND DEVELPOERS PVT.LTD · Patna
Units10
Completion2025-04-30Proposed
Registered on2020-08-18
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 1 unit type |
| Construction & progress | 2 progress details · 13 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 20 documents · 17 source links |
Registration
Registration
| Promoter | KOSUT BUILDERS AND DEVELPOERS PVT.LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00530-3/718/R-1016/2020 | |
| Registered on | 2020-08-18 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2025-04-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,976.43 | |
|---|---|---|
| Built-up (m²) | 4,622.01 | |
| FAR | 2.33 | |
| Towers | 2 | |
| Units | 10 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 10 | BHAGWAN KAILASH AWAS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-03-01 | |
|---|---|---|
| Proposed completion | 2025-04-30 |
Quarterly progress
| 2023-Q1 | 2023-04-10 |
| 2022-Q4 | 2023-01-04 |
| 2022-Q3 | 2023-01-04 |
| 2022-Q2 | 2022-07-11 |
| 2022-Q1 | 2022-04-18 |
| 2021-Q4 | 2022-01-09 |
| 2021-Q3 | 2021-10-11 |
| 2021-Q2 | 2021-07-13 |
| 2021-Q1 | 2021-04-10 |
| 2020-Q4 | 2021-01-13 |
| 2020-Q3 | 2020-10-15 |
| 2020-Q2 | 2020-10-15 |
| 2020-Q1 | 2020-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KOSUT BUILDERS AND DEVELPOERS PVT.LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | Allahabad Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP246201800530-3
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP246201800530-3
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2022-2023 · 2023-04-10
- Q3-Oct to Dec / 2022-2023 · 2023-01-04
- Q2-Jul to Sep / 2022-2023 · 2023-01-04
- Q1-Apr to Jun / 2022-2023 · 2022-07-11
- Q4-Jan to Mar / 2021-2022 · 2022-04-18
- Q3-Oct to Dec / 2021-2022 · 2022-01-09
- Q2-Jul to Sep / 2021-2022 · 2021-10-11
- Q1-Apr to Jun / 2021-2022 · 2021-07-13
- Q4-Jan to Mar / 2020-2021 · 2021-04-10
- Q3-Oct to Dec / 2020-2021 · 2021-01-13
- Q2-Jul to Sep / 2020-2021 · 2020-10-15
- Q1-Apr to Jun / 2020-2021 · 2020-10-15
- Q4-Jan to Mar / 2019-2020 · 2020-10-15
- 2023-Q1 · 2023-04-10
- 2022-Q4 · 2023-01-04
- 2022-Q3 · 2023-01-04
- 2022-Q2 · 2022-07-11
- 2022-Q1 · 2022-04-18
- 2021-Q4 · 2022-01-09
- 2021-Q3 · 2021-10-11
- 2021-Q2 · 2021-07-13
- 2021-Q1 · 2021-04-10
- 2020-Q4 · 2021-01-13
- 2020-Q3 · 2020-10-15
- 2020-Q2 · 2020-10-15
- 2020-Q1 · 2020-10-15