Overview
Bhawani Highway Mall
Jagdeep Bansal · Sangrur
Units106
Completion2030-03-31Proposed
Valid to2030-03-31
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 11 unit types |
| Construction & progress | 2 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 27 documents · 17 source links |
Registration
Registration
| Promoter | Jagdeep Bansal | |
|---|---|---|
| District | Sangrur | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SGR72-PC0391 | |
| Valid to | 2030-03-31 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2030-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| Electric Substation NOC | 2025-09-25 |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| NOC from NHAI/ PWD | 2024-11-12 |
| Other Document (Drainage NOC) | 2024-11-14 |
| Other Document (Forest NOC) | 2025-06-09 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-08-05 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹15,27,71,199 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 29,202.5 | |
|---|---|---|
| Units | 106 |
Unit types
| Plot No. 1 | 87.701 | 1 | COMMERCIALS PLOTS |
| Plot No. 2 to 12, 13 to 25, 30 to 42, 44 to 56, 61 to 71 | 73.085 | 61 | COMMERCIALS PLOTS |
| Plot No. 26, 29, 57, 60 | 88.921 | 4 | COMMERCIALS PLOTS |
| Plot No. 27 to 28, 58 to 59, 72 to 82 | 54.816 | 15 | COMMERCIALS PLOTS |
| Plot No. 43 | 743.896 | 1 | COMMERCIALS PLOTS |
| Plot No. 83 to 91 | 78.035 | 9 | COMMERCIALS PLOTS |
| Plot No. 92 | 57.132 | 1 | COMMERCIALS PLOTS |
| Plot No. 93 | 316.045 | 1 | COMMERCIALS PLOTS |
| Plot No. 94 to 99, 101 to 105 | 118.913 | 11 | COMMERCIALS PLOTS |
| Plot No. 100 | 1,025.644 | 1 | COMMERCIALS PLOTS |
| Plot No. 106 | 232.358 | 1 | COMMERCIALS PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-09-30 | |
|---|---|---|
| Proposed completion | 2030-03-31 |
Quarterly progress
| 2025-Q4 | 2026-01-16 |
| 2026-Q1 | 2026-07-15 |
| 2026-Q2 | 2026-07-15 |
| 2026-Q3 | 2026-10-09 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Jagdeep Bansal | |
|---|---|---|
| Type | Individual | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| CA | KHANDELWAL SUDHIR AND ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12476&inPromoter_ID=3386&inPromoterType=1
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-09-25
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2024-11-12
- Other Document (Architect Certificate for Non Applicability AAI EC) · 2025-10-03 · Sign in to download
- Other Document (Drainage NOC) · 2024-11-14
- Other Document (Forest NOC) · 2025-06-09
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-05
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2025-09-25
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2024-11-12
- Other Document (Drainage NOC) · 2024-11-14
- Other Document (Forest NOC) · 2025-06-09
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-05
- 2025-Q4 · 2026-01-16
- 2026-Q1 · 2026-07-15
- 2026-Q2 · 2026-07-15
- 2026-Q3 · 2026-10-09