Overview
BMS BUSINESS PARK
ANJANI DEVELOPERS · BASTAR
Units57
Booked26 of 57As of 2025-03-31
Construction progress99%As of 2025-03-31
Completion2026-08-02Revised · Proposed 2021-06-30
Registered on2018-06-13
Approvals4
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 2 cases |
| Contract & costs | 2 cost heads · 26 quarters |
| Technical report | |
| Site & area | 3 site details · 57 unit types |
| Construction & progress | 4 progress details · 26 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 133 documents · 12 source links |
Registration
Registration
| Promoter | ANJANI DEVELOPERS | |
|---|---|---|
| District | BASTAR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA130618000128 | |
| Registered on | 2018-06-13 | |
| Project type | Commercial | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2021-06-30 | |
| Revised completion | 2026-08-02 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXA-2026-03495 | CG RERA | Complaint | Disposed | 2026-04-13 |
| M-COM-2019-00362 | CG RERA | Complaint | Disposed | 2019-04-25 |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,00,00,000 | |
|---|---|---|
| Construction | ₹35,61,34,000 |
Quarterly money flows
| 2018-Q3 | ₹36,000 |
| 2018-Q4 | ₹35,822 |
| 2019-Q1 | ₹1.5 |
| 2019-Q2 | ₹50,002 |
| 2019-Q3 | ₹49,961 |
| 2019-Q4 | ₹49,931 |
| 2020-Q1 | ₹49,902 |
| 2020-Q2 | ₹49,901 |
| 2020-Q3 | ₹0.49 |
| 2020-Q4 | ₹49,547 |
| 2021-Q1 | ₹49,547.7 |
| 2021-Q2 | ₹49,547.7 |
| 2021-Q3 | ₹49,547.7 |
| 2021-Q4 | ₹49,547.7 |
| 2022-Q1 | ₹49,547.7 |
| 2022-Q2 | ₹49,547.7 |
| 2022-Q3 | ₹49,547.7 |
| 2022-Q4 | ₹49,400.2 |
| 2023-Q1 | ₹49,252.2 |
| 2023-Q2 | ₹49,252.2 |
| 2023-Q3 | ₹49,400 |
| 2023-Q4 | ₹49,400 |
| 2024-Q1 | ₹49,400 |
| 2024-Q2 | ₹49,400 |
| 2024-Q4 | ₹6,400 |
| 2025-Q1 | ₹6,400 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 57 | |
|---|---|---|
| Booked | 26 | |
| Booked as of | 2025-03-31 |
Unit types
| COMMERCIAL | 74.04 | 1 | 0 |
| COMMERCIAL | 36.33 | 1 | 1 |
| COMMERCIAL | 36.33 | 1 | 1 |
| COMMERCIAL | 36.33 | 1 | 0 |
| COMMERCIAL | 36.33 | 1 | 0 |
| COMMERCIAL | 36.33 | 1 | 0 |
| COMMERCIAL | 36.33 | 1 | 0 |
| COMMERCIAL | 37.07 | 1 | 0 |
| COMMERCIAL | 36.52 | 1 | 0 |
| COMMERCIAL | 36.52 | 1 | 1 |
| COMMERCIAL | 36.52 | 1 | 1 |
| COMMERCIAL | 36.52 | 1 | 1 |
| COMMERCIAL | 36.52 | 1 | 1 |
| COMMERCIAL | 36.52 | 1 | 1 |
| COMMERCIAL | 36.52 | 1 | 1 |
| COMMERCIAL | 36.6 | 1 | 1 |
| COMMERCIAL | 36.79 | 1 | 1 |
| COMMERCIAL | 469.91 | 1 | 0 |
| COMMERCIAL | 37.16 | 1 | 0 |
| COMMERCIAL | 36.7 | 1 | 0 |
| COMMERCIAL | 36.7 | 1 | 0 |
| COMMERCIAL | 36.7 | 1 | 0 |
| COMMERCIAL | 36.7 | 1 | 0 |
| COMMERCIAL | 36.7 | 1 | 0 |
| COMMERCIAL | 36.7 | 1 | 0 |
| COMMERCIAL | 36.7 | 1 | 0 |
| COMMERCIAL | 37.35 | 1 | 0 |
| COMMERCIAL | 18.03 | 1 | 0 |
| COMMERCIAL | 14.31 | 1 | 1 |
| COMMERCIAL | 36.51 | 1 | 1 |
| COMMERCIAL | 36.89 | 1 | 1 |
| COMMERCIAL | 36.89 | 1 | 1 |
| COMMERCIAL | 36.89 | 1 | 1 |
| COMMERCIAL | 36.89 | 1 | 1 |
| COMMERCIAL | 36.89 | 1 | 1 |
| COMMERCIAL | 36.98 | 1 | 1 |
| COMMERCIAL | 40.7 | 1 | 1 |
| COMMERCIAL | 545.53 | 1 | 0 |
| COMMERCIAL | 70.33 | 1 | 0 |
| COMMERCIAL | 34.65 | 1 | 0 |
| COMMERCIAL | 34.65 | 1 | 0 |
| COMMERCIAL | 34.65 | 1 | 0 |
| COMMERCIAL | 34.65 | 1 | 0 |
| COMMERCIAL | 34.65 | 1 | 0 |
| COMMERCIAL | 34.65 | 1 | 0 |
| COMMERCIAL | 35.4 | 1 | 0 |
| COMMERCIAL | 46.73 | 1 | 1 |
| COMMERCIAL | 37.44 | 1 | 0 |
| COMMERCIAL | 36.51 | 1 | 0 |
| COMMERCIAL | 36.88 | 1 | 0 |
| COMMERCIAL | 36.88 | 1 | 1 |
| COMMERCIAL | 36.88 | 1 | 1 |
| COMMERCIAL | 36.88 | 1 | 1 |
| COMMERCIAL | 36.88 | 1 | 1 |
| COMMERCIAL | 36.98 | 1 | 1 |
| COMMERCIAL | 37.16 | 1 | 1 |
| COMMERCIAL | 598.95 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 99% | |
|---|---|---|
| As of | 2025-03-31 | |
| Proposed completion | 2021-06-30 | |
| Revised completion | 2026-08-02 |
Quarterly progress
| 2018-Q3 | 42% |
| 2018-Q4 | 48% |
| 2019-Q1 | 61% |
| 2019-Q2 | 64% |
| 2019-Q3 | 64% |
| 2019-Q4 | 64% |
| 2020-Q1 | 76% |
| 2020-Q2 | 78% |
| 2020-Q3 | 0% |
| 2020-Q4 | 79% |
| 2021-Q1 | 92% |
| 2021-Q2 | 92% |
| 2021-Q3 | 92% |
| 2021-Q4 | 93% |
| 2022-Q1 | 95% |
| 2022-Q2 | 95% |
| 2022-Q3 | 97% |
| 2022-Q4 | 97% |
| 2023-Q1 | 97% |
| 2023-Q2 | 99% |
| 2023-Q3 | 99% |
| 2023-Q4 | 99% |
| 2024-Q1 | 99% |
| 2024-Q2 | 99% |
| 2024-Q4 | 99% |
| 2025-Q1 | 99% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ANJANI DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MjQy
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Audit Report
- CA Certificate
- Engg Certificate
- Architect Certificate
- Audit Report
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-04-13 · Sign in to download
- Final order · 2019-04-25 · Sign in to download
- Interim order · 2026-03-30 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities
- SM-EXA-2026-03495 · Sign in to download