Overview
BRISTOL HOMES
VIPAN KUMAR BANSAL · Sahibzada Ajit Singh Nagar (Mohali)
Units176
Booked9 of 176As of 2026-09-30
Completion2028-06-14Proposed
Registered on2024-07-02
Valid to2028-06-14
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details · 8 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 32 documents · 23 source links |
Registration
Registration
| Promoter | VIPAN KUMAR BANSAL | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0918 | |
| Registered on | 2024-07-02 | |
| Valid to | 2028-06-14 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-06-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| Electric Substation NOC | 2023-04-19 |
| Environment Clearance certificate/ NOC | 2025-02-10 |
| License as Promoter from competent Authority | 2022-10-10 |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2022-10-31 |
| NOC from NHAI/ PWD | 2023-09-13 |
| Other Document (DRAINAGE NOC) | 2023-12-13 |
| Other Document (FOREST NOC) | 2022-12-16 |
| Pollution Clearance from Punjab Pollution Control Board | 2023-12-05 |
| Pollution Clearance from Punjab Pollution Control Board | 2023-01-13 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-08-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹64,01,67,261 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 11,432.342 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 4 | |
| Units | 176 | |
| Booked | 9 | |
| Booked as of | 2026-09-30 |
Unit types
| Flat 4 BHK First Floor no. 43 to 44 | 101.39 | 2 | 0 | BRISTOL HOMES |
| Flat 4 BHK Second Floor no. 43 to 44 | 101.39 | 2 | 0 | BRISTOL HOMES |
| Flat 4 BHK Fourth Floor no. 43 to 44 | 101.39 | 2 | 0 | BRISTOL HOMES |
| Flat 4 BHK Third Floor no. 43 to 44 | 101.39 | 2 | 0 | BRISTOL HOMES |
| Flat 3BHK Fourth Floor 1 to 42 | 90.67 | 42 | 1 | BRISTOL HOMES |
| Flat 3BHK Third Floor no. 1 to 42 | 90.67 | 42 | 2 | BRISTOL HOMES |
| Flat 3BHK Second Floor no. 1 to 42 | 90.67 | 42 | 3 | BRISTOL HOMES |
| Flat 3BHK First floor no. 1 to 42 | 90.67 | 42 | 3 | BRISTOL HOMES |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-06-15 | |
|---|---|---|
| Proposed completion | 2028-06-14 |
Quarterly progress
| 2024-Q3 | 2025-08-08 | ||
| 2024-Q4 | 2025-08-08 | ||
| 2025-Q1 | 2025-08-08 | ||
| 2025-Q2 | 2025-08-08 | ||
| 2025-Q4 | 2026-02-11 | ||
| 2025-Q3 | 2026-02-16 | ||
| 2026-Q1 | 2026-04-29 | ||
| 2026-Q2 | 2026-07-22 | ||
| 2026-Q3 | 2026-10-14 | 0 | 6 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VIPAN KUMAR BANSAL | |
|---|---|---|
| Type | Individual | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=11763&inPromoter_ID=2642&inPromoterType=11763&inQUProject_ID=6729&inQUProject_DN=QUP2026T20266729&inQUProjectYear=2026&inQUProjectQTR=ThirdQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11763&inPromoter_ID=2642&inPromoterType=1
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2023-04-19
- Environment Clearance certificate/ NOC · 2025-02-10
- License as Promoter from competent Authority · 2022-10-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-10-31
- NOC from NHAI/ PWD · 2023-09-13
- Other Document (DRAINAGE NOC) · 2023-12-13
- Other Document (FOREST NOC) · 2022-12-16
- Other Document (Solid Waste and construction and Demolation waste) · 2022-10-28 · Sign in to download
- Other Document (UNDERTAKING FOR WATER SUPPLY STORM AND SEWERAGE) · 2024-01-04 · Sign in to download
- Other Document (WATER SUPPLY LAYOUT PLAN) · 2023-12-14
- Pollution Clearance from Punjab Pollution Control Board · 2023-12-05
- Pollution Clearance from Punjab Pollution Control Board · 2023-01-13
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-01
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- Annual Report (Form-5 CA Certificate)
- CLU Certificate
- Electric Substation NOC · 2023-04-19
- Environment Clearance certificate/ NOC · 2025-02-10
- License as Promoter from competent Authority · 2022-10-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2022-10-31
- NOC from NHAI/ PWD · 2023-09-13
- Other Document (DRAINAGE NOC) · 2023-12-13
- Other Document (FOREST NOC) · 2022-12-16
- Pollution Clearance from Punjab Pollution Control Board · 2023-12-05
- Pollution Clearance from Punjab Pollution Control Board · 2023-01-13
- Pollution Clearance from Punjab Pollution Control Board · 2025-08-01
- 2024-Q3 · 2025-08-08
- 2024-Q4 · 2025-08-08
- 2025-Q1 · 2025-08-08
- 2025-Q2 · 2025-08-08
- 2025-Q4 · 2026-02-11
- 2025-Q3 · 2026-02-16
- 2026-Q1 · 2026-04-29
- 2026-Q2 · 2026-07-22