Overview
CAPKON HILLORA-1
CAPKON DEVELOPERS PRIVATE LIMITED · OPPOSITE INDUSTRIAL PARK
Units70
Booked14 of 70
Construction progress1%
Completion2031-09-10Proposed
Registered on2026-07-29
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 5 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 34 documents · 5 source links |
Registration
Registration
| Promoter | CAPKON DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Kozhikode | |
| Locality | OPPOSITE INDUSTRIAL PARK | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/KKD/116/2026 | |
| Registered on | 2026-07-29 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2031-09-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/70629/2026 | 2026-05-18 | 2031-05-17 | KOZHIKODE MUNICIPAL CORPORATION |
| Development Permit | BP/70629/2026 | 2026-05-18 | 2031-05-17 | MUNICIPAL CORPORATION KOZHIKODE |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,770.35 | |
|---|---|---|
| Built-up (m²) | 12,862.21 | |
| Towers | 0 | |
| Units | 70 | |
| Booked | 14 |
Unit types
| 2BHK | 14 | 5 | CAPKON HILLORA-1 |
| 2BHK | 14 | 2 | CAPKON HILLORA-1 |
| 2BHK | 14 | 2 | CAPKON HILLORA-1 |
| 3BHK | 14 | 2 | CAPKON HILLORA-1 |
| 3BHK | 14 | 3 | CAPKON HILLORA-1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 1% | |
|---|---|---|
| Start | 2026-08-01 | |
| Proposed completion | 2031-09-10 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CAPKON DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 7 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | Arjun Associates |
| CA | Shinas and Associates |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/12174
- https://rera.kerala.gov.in/projects?district=591&page=1
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=FIQHNPtk1Ru96M0wXXpSFGpzb0ImO64yk7XtdmgUTt1DPIoVtSfp1px93icOk%2FiYVE0YtgkXsoIn3n%2BRAhEcjJKniWjxg3zrAZLtjLRv8zaU%2BAilHJc2E1Snt8E7%2B6PMU2v1B9nSsBfPZi42mHcm%2Fz2OW0gnNspoDWwH5Z%2F3s8iXLS47yDbuZA%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=12174&Division=1&UserID=32926&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2026-07-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-06-13
- Copy of Valid Building Permit · 2026-06-13
- Copy of Valid Development Permit (For villa projects & plot development projects) · 2026-06-13
- Detailed technical specifications to be adopted in the project · 2026-06-13 · Sign in to download
- Layout approval plan · 2026-06-13
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2026-06-13 · Sign in to download
- Site Plan / Site Map · 2026-06-13
- Other · 2026-06-13 · Sign in to download
- Clearance from Airport Authority of India · 2026-06-13 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2026-06-13 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2026-06-13 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2026-06-13
- Consent to establish (Clearance from Pollution Control Board) · 2026-06-13 · Sign in to download
- Environment Clearance · 2026-06-13 · Sign in to download
- Initial NOC from Fire and Rescue department · 2026-06-13
- Others · 2026-06-29 · Sign in to download
- Others · 2026-06-29 · Sign in to download
- Charts and the project schedule · 2026-06-13 · Sign in to download
- List and details of common amenities · 2026-06-13 · Sign in to download
- List and details of common amenities · 2026-06-13 · Sign in to download
- Plan of firefighting to be executed in the proposed project · 2026-06-13