Overview
Capkon Pristine
CAPKON DEVELOPERS PRIVATE LIMITED · Near Sree Karumakan Kavu, Chevarambalam-CWRDM Bypass Road, Chelavur P.O
Units84
Booked59 of 84
Construction progress15%
Completion2030-04-17Proposed
Registered on2024-12-30
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 5 unit types |
| Construction & progress | 3 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 33 documents · 5 source links |
Registration
Registration
| Promoter | CAPKON DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Kozhikode | |
| Locality | Near Sree Karumakan Kavu, Chevarambalam-CWRDM Bypass Road, Chelavur P.O | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/KKD/266/2024 | |
| Registered on | 2024-12-30 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2030-04-17 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/16653/2024 | 2024-12-18 | 2029-12-17 | Kozhikode Municipal Corporation |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,982.78 | |
|---|---|---|
| Built-up (m²) | 13,104.27 | |
| Towers | 1 | |
| Units | 84 | |
| Booked | 59 |
Unit types
| 2BHK | 14 | 10 | Capkon Pristine |
| 2BHK | 14 | 12 | Capkon Pristine |
| 2BHK | 14 | 10 | Capkon Pristine |
| 3BHK | 14 | 9 | Capkon Pristine |
| 3BHK | 28 | 18 | Capkon Pristine |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 15% | |
|---|---|---|
| Start | 2025-03-01 | |
| Proposed completion | 2030-04-17 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CAPKON DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 7 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | Arjun Associates |
| CA | Shinas and Associates |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11802
- https://rera.kerala.gov.in/projects?district=591&page=1
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=KEIFlyF%2F1mRKoLdUpQWMmhz7OwtILB8VOzl5EgVfBtNBhvFR793FrW%2BBXq8LH1qH28c9v2%2BJEGRioX5KoQNe4ni7r87UBCbYBhmXWP06GC8gQlMaKT44lfvHLG%2BQA%2FwmkhHIU7hRZBR4qpkWTXxtijnqbIX8IA4Nj03Xol%2Fd3zufHXgNBEKhEQ%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11802&Division=1&UserID=32926&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2024-12-30
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-12-21
- Copy of Valid Building Permit · 2024-12-21
- Detailed technical specifications to be adopted in the project · 2024-12-21 · Sign in to download
- Layout approval plan · 2024-12-21
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2024-12-21 · Sign in to download
- Site Plan / Site Map · 2024-12-21
- Other · 2024-12-21 · Sign in to download
- Clearance from Airport Authority of India · 2024-12-21 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2024-12-21 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2024-12-21 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2024-12-21
- Consent to establish (Clearance from Pollution Control Board) · 2024-12-21 · Sign in to download
- Environment Clearance · 2024-12-21 · Sign in to download
- Initial NOC from Fire and Rescue department · 2024-12-21
- Permission from Water and sewerage department · 2024-12-21 · Sign in to download
- Charts and the project schedule · 2024-12-21 · Sign in to download
- List and details of common amenities · 2024-12-21 · Sign in to download