Overview
CELESTE RIVIERA
GALAXY BUILDERS · Pin Code 673008
Units96
Booked84 of 96
Construction progress27%
Completion2029-04-30Proposed
Registered on2024-05-10
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 5 unit types |
| Construction & progress | 3 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 67 documents · 5 source links |
Registration
Registration
| Promoter | GALAXY BUILDERS | |
|---|---|---|
| District | Kozhikode | |
| Locality | Pin Code 673008 | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/KKD/089/2024 | |
| Registered on | 2024-05-10 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2029-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | SC4-BA(124427)/2024 | 2024-04-11 | 2029-04-10 | OLAVANNA GRAMA PANCHAYAT |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,592.1 | |
|---|---|---|
| Built-up (m²) | 29,657.5 | |
| Towers | 1 | |
| Units | 96 | |
| Booked | 84 |
Unit types
| 2BHK | 30 | 30 | CELESTE RIVIERA |
| 3BHK | 30 | 30 | CELESTE RIVIERA |
| 4BHK | 30 | 21 | CELESTE RIVIERA |
| 4BHK | 3 | 0 | CELESTE RIVIERA |
| 5 BHK and More | 3 | 3 | CELESTE RIVIERA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 27% | |
|---|---|---|
| Start | 2024-05-15 | |
| Proposed completion | 2029-04-30 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GALAXY BUILDERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | IDBI BANK | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11573
- https://rera.kerala.gov.in/projects?district=591&page=2
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=S8FmR9Db5PGh5sekc%2BRxT0ey%2FC5FTnonZ98gPFYyvhaUP1ppTX9iTIj8pIrlgSwwpO8rPdRsKi1%2BnCRoE%2FJL1mnpUAm5v86Dz9vR5QWDkyoxxxkuiK5ecl4BtuQH6Gxf89HRAOzUxjIryvmtCrmWJ3oIw5PVxbGfUUv6xFxNxl8gsWx9Ez7wgQ%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11573&Division=1&UserID=30237&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2024-05-10
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-04-13
- Copy of Valid Building Permit · 2024-04-13
- Copy of Valid Development Permit (For villa projects & plot development projects) · 2024-04-13
- Detailed technical specifications to be adopted in the project · 2024-04-12 · Sign in to download
- Detailed technical specifications to be adopted in the project · 2024-04-30 · Sign in to download
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2024-04-12 · Sign in to download
- Site Plan / Site Map · 2024-04-13
- Other · 2024-04-16 · Sign in to download
- Other · 2024-04-16 · Sign in to download
- Other · 2024-04-16 · Sign in to download
- Other · 2024-04-29 · Sign in to download
- Clearance from Airport Authority of India · 2024-04-15 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2024-04-15 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2024-04-15 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2024-04-13 · Sign in to download
- Environment Clearance · 2024-04-13 · Sign in to download
- Initial NOC from Fire and Rescue department · 2024-04-13
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- List and details of common amenities · 2024-04-12 · Sign in to download
- List and details of common amenities · 2024-04-30 · Sign in to download
- Other Plans to be executed in the proposed project · 2024-04-15
- Other Plans to be executed in the proposed project · 2024-04-15
- Plan for Drinking water service to be executed in the proposed project · 2024-04-15
- Plan of firefighting to be executed in the proposed project · 2024-04-15
- Plan of Use of renewable energy to be executed in the proposed project · 2024-04-15