Overview
CENTRAL PARK THE ORCHARD
ST PATRICKS REALTY PRIVATE LIMITED · Gurugram
Units380
Completion2026-06-30Proposed
Registered on2023-01-23
Valid to2026-06-30
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 7 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 3 source links |
Registration
Registration
| Promoter | ST PATRICKS REALTY PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/672/404/2023/16 DATED 23.01.2023 | |
| Registered on | 2023-01-23 | |
| Valid to | 2026-06-30 | |
| Status (as filed) | Registered | |
| Proposed completion | 2026-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 104 OF 2021 (13.12.2021) | Town & Country Planning Department | |
| Layout Plan | 2021-12-13 | ||
| Building Plan | 2023-01-12 | ||
| I. ENVIRONMENT CLEARANCE | 2022-08-19 | ||
| II. DTCP LICENSE | 2021-12-10 | ||
| III. LAYOUT PLAN APPROVAL | 2021-12-13 | ||
| IV. ELECTRICITY LOAD SANCTIONED | 2021-03-19 | ||
| V. SERVICE ESTIMATE | 2022-05-16 | ||
| VI. ZONING PLAN | 2022-08-10 | ||
| VII. FOREST NOC | 2021-12-29 | ||
| VIII. BR-III | 2022-12-29 | ||
| IX. LOI | 2021-09-24 | ||
| X. LC-IV | 2021-12-10 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹55,96,47,000 | |
|---|---|---|
| Construction | ₹3,22,36,71,000 | |
| Total | ₹4,35,40,14,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 16,701.3764 | |
|---|---|---|
| FAR | 2.64 | |
| Units | 380 |
Unit types
| Plot | 68 | |
| Plot | 8 | |
| Apartment/Shops/Other Buildings | 123.185 | 104 |
| Apartment/Shops/Other Buildings | 124.207 | 128 |
| Apartment/Shops/Other Buildings | 133.683 | 32 |
| Apartment/Shops/Other Buildings | 123.835 | 20 |
| Apartment/Shops/Other Buildings | 123.649 | 20 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-02-01 | |
|---|---|---|
| Proposed completion | 2026-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ST PATRICKS REALTY PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | INDUSIND BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2116
- https://nominatim.openstreetmap.org/search?q=sector+32%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2023-01-23
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2022-09-14
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2022-09-14 · Sign in to download
- ZONING PLAN · 2022-09-14
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2022-09-14 · Sign in to download
- ELECTRICAL LOAD APPROVAL LETTER · 2022-09-14
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2022-09-15 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2022-09-15
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2022-09-15
- ROAD LAYOUT PLAN · 2023-01-25
- CA CERTIFICATE · 2023-01-25 · Sign in to download
- LC-IV 47.759 · 2023-01-25 · Sign in to download
- BR III · 2023-01-25 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2023-01-25 · Sign in to download
- DRAINAGE PLAN · 2023-01-25
- DUAL PLUMBING PLAN · 2023-01-25
- ENVIRONMENT CLEARANCE LETTER · 2023-01-25
- FIRE FIGHTING PLAN · 2023-01-25
- LOI 47.759 ACRES · 2023-01-25 · Sign in to download
- SEWERAGE PLAN · 2023-01-25
- WATER SUPPLY PLAN · 2023-01-25
- OC uploaded · 2026-04-17 · Sign in to download