Overview
CHANDESHWAR APARTMENT
KIBAKA CONSTRUCTIONS AND ENGINEERS PRIVATE LIMITED · Patna
Units40
Booked11 of 40As of 2026-06-30
Construction progress17%As of 2026-06-30
Completion2029-03-31Proposed
Registered on2024-08-06
Valid to2029-03-31
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 6 unit types |
| Construction & progress | 4 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 12 source links |
Registration
Registration
| Promoter | KIBAKA CONSTRUCTIONS AND ENGINEERS PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP03654-1/97/R-1743/2024 | |
| Registered on | 2024-08-06 | |
| Valid to | 2029-03-31 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2024-09-03 | PATNA METROPOLITAN AREA AUTHORITY | |
| Environment Clearance | 9999-12-31 | ||
| Fire NOC | 9999-12-31 | DIRECTOR,STATE FIRE SERVICES BIHAR | |
| Airport NOC | 9999-12-31 | ||
| Water Supply Permission | 9999-12-31 | ||
| Other approval | 9999-12-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹29,93,87,66,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,563.84 | |
|---|---|---|
| Built-up (m²) | 3,893.31 | |
| FAR | 2.48 | |
| Towers | 1 | |
| Units | 40 | |
| Booked | 11 | |
| Booked as of | 2026-06-30 |
Unit types
| 3 BHK | 8 | CHANDESHWAR APARTMENT |
| 2 BHK | 4 | CHANDESHWAR APARTMENT |
| 2 BHK | 16 | CHANDESHWAR APARTMENT |
| 3 BHK | 4 | CHANDESHWAR APARTMENT |
| 3 BHK | 4 | CHANDESHWAR APARTMENT |
| 2 BHK | 4 | CHANDESHWAR APARTMENT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 17% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2024-06-30 | |
| Proposed completion | 2029-03-31 |
Quarterly progress
| 2026-Q2 | 2026-07-28 | 17% | 11 |
| 2026-Q1 | 2026-04-29 | ||
| 2025-Q4 | 2026-01-14 | ||
| 2025-Q3 | 2025-11-21 | ||
| 2025-Q2 | 2025-08-18 | ||
| 2025-Q1 | 2025-04-13 | ||
| 2024-Q4 | 2025-01-14 | ||
| 2024-Q3 | 2024-10-13 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KIBAKA CONSTRUCTIONS AND ENGINEERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Axis Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP05242024203654-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP05242024203654&ld=pan&pj=RERAP05242024203654-1&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP05242024203654-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-28
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-29
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-14
- Q2 (Jul - Sep) / 2025-2026 · 2025-11-21
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-18
- Q4-Jan to Mar / 2024-2025 · 2025-04-13
- Q3-Oct to Dec / 2024-2025 · 2025-01-14
- Q2-Jul to Sep / 2024-2025 · 2024-10-13
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- 2026-Q1 · 2026-04-29
- 2025-Q4 · 2026-01-14
- 2025-Q3 · 2025-11-21
- 2025-Q2 · 2025-08-18
- 2025-Q1 · 2025-04-13
- 2024-Q4 · 2025-01-14
- 2024-Q3 · 2024-10-13