Overview
CHORDIA'S THE KAIRO
SHIVVILAS REALHOME PRIVATE LIMITED · Village- Madrampura, Sodala, Ajmer Road
Units209
Booked0 of 209As of 2026-06-30
Completion2031-04-30Revised · Proposed 2025-11-24
Registered on2025-12-16
Valid to2031-04-30
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 7 site details · 63 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 45 documents · 7 source links |
Registration
Registration
| Promoter | SHIVVILAS REALHOME PRIVATE LIMITED | |
|---|---|---|
| District | Jaipur | |
| Locality | Village- Madrampura, Sodala, Ajmer Road | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2025/4539 | |
| Registered on | 2025-12-16 | |
| Valid to | 2031-04-30 | |
| Project type | Commercial | |
| Status (as filed) | INPROGRESS | |
| Proposed completion | 2025-11-24 | |
| Revised completion | 2031-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date | Valid to | Authority |
|---|---|---|---|
| Building Plan | 2025-10-17 | 2032-10-17 | JAIPUR DEVELOPMENT AUTHORITY |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹76,16,03,301 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹1,45,16,03,301 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2026-Q2 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,402.02 | |
|---|---|---|
| Built-up (m²) | 28,420 | |
| Towers | 209 | |
| Maximum floors | 17 | |
| Units | 209 | |
| Booked | 0 | |
| Booked as of | 2026-06-30 |
Unit types
| 1001 | 336.8 | 1 | 0 | CHORDIA'S THE KAIRO |
| 1002 | 267.1 | 1 | 0 | CHORDIA'S THE KAIRO |
| 1003 | 257.7 | 1 | 0 | CHORDIA'S THE KAIRO |
| 1004 | 256.4 | 1 | 0 | CHORDIA'S THE KAIRO |
| 101 | 46.3 | 1 | 0 | CHORDIA'S THE KAIRO |
| 102 | 46.3 | 1 | 0 | CHORDIA'S THE KAIRO |
| 103 | 62.9 | 1 | 0 | CHORDIA'S THE KAIRO |
| 104 | 62.9 | 1 | 0 | CHORDIA'S THE KAIRO |
| 105 | 59.5 | 1 | 0 | CHORDIA'S THE KAIRO |
| 106 | 52.3 | 1 | 0 | CHORDIA'S THE KAIRO |
| 107 | 133.5 | 1 | 0 | CHORDIA'S THE KAIRO |
| 108 | 133.5 | 1 | 0 | CHORDIA'S THE KAIRO |
| 109 | 60.5 | 1 | 0 | CHORDIA'S THE KAIRO |
| 110 | 60.4 | 1 | 0 | CHORDIA'S THE KAIRO |
| 1101 | 1,219.3 | 1 | 0 | CHORDIA'S THE KAIRO |
| 111,112 | 63.4 | 2 | 0 | CHORDIA'S THE KAIRO |
| 113 | 46.6 | 1 | 0 | CHORDIA'S THE KAIRO |
| 114 | 46.7 | 1 | 0 | CHORDIA'S THE KAIRO |
| 1201 | 315.66 | 1 | 0 | CHORDIA'S THE KAIRO |
| 201 TO 601, 202 TO 602 | 21.2 | 10 | 0 | CHORDIA'S THE KAIRO |
| 203 TO 603 | 28.9 | 5 | 0 | CHORDIA'S THE KAIRO |
| 204 TO 604 | 29.9 | 5 | 0 | CHORDIA'S THE KAIRO |
| 205 TO 605 | 27 | 5 | 0 | CHORDIA'S THE KAIRO |
| 206 TO 606 | 19.8 | 5 | 0 | CHORDIA'S THE KAIRO |
| 207 TO 607 | 38.2 | 5 | 0 | CHORDIA'S THE KAIRO |
| 208 TO 608 | 38.8 | 5 | 0 | CHORDIA'S THE KAIRO |
| 209 TO 609 | 35.6 | 5 | 0 | CHORDIA'S THE KAIRO |
| 210 TO 610 | 36.1 | 5 | 0 | CHORDIA'S THE KAIRO |
| 211 TO 611 | 35.6 | 5 | 0 | CHORDIA'S THE KAIRO |
| 212 TO 612 | 39.1 | 5 | 0 | CHORDIA'S THE KAIRO |
| 213 TO 613 | 38.2 | 5 | 0 | CHORDIA'S THE KAIRO |
| 214 TO 614, 215 TO 615 | 26.4 | 10 | 0 | CHORDIA'S THE KAIRO |
| 216 TO 616, 217 TO 617 | 27.8 | 10 | 0 | CHORDIA'S THE KAIRO |
| 218 TO 618, 219 TO 619 | 20.4 | 10 | 0 | CHORDIA'S THE KAIRO |
| 220 TO 620, 221 TO 621 | 20.8 | 10 | 0 | CHORDIA'S THE KAIRO |
| 222 TO 622,223 TO 623 | 28.3 | 10 | 0 | CHORDIA'S THE KAIRO |
| 224 TO 624 | 26.9 | 5 | 0 | CHORDIA'S THE KAIRO |
| 225 TO 625, 226 TO 626, 227 TO 627 | 27 | 15 | 0 | CHORDIA'S THE KAIRO |
| 228 TO 628, 229 TO 629 | 28.3 | 10 | 0 | CHORDIA'S THE KAIRO |
| 230 TO 630, 231 TO 631 | 20.8 | 10 | 0 | CHORDIA'S THE KAIRO |
| 232 TO 632 | 128.9 | 5 | 0 | CHORDIA'S THE KAIRO |
| 701 | 94 | 1 | 0 | CHORDIA'S THE KAIRO |
| 702 | 126.3 | 1 | 0 | CHORDIA'S THE KAIRO |
| 703 | 114 | 1 | 0 | CHORDIA'S THE KAIRO |
| 704 | 146.6 | 1 | 0 | CHORDIA'S THE KAIRO |
| 705 | 149.1 | 1 | 0 | CHORDIA'S THE KAIRO |
| 706 | 123.3 | 1 | 0 | CHORDIA'S THE KAIRO |
| 707 | 127.3 | 1 | 0 | CHORDIA'S THE KAIRO |
| 708 | 79.9 | 1 | 0 | CHORDIA'S THE KAIRO |
| 709 | 128.9 | 1 | 0 | CHORDIA'S THE KAIRO |
| 801,901 | 179.4 | 2 | 0 | CHORDIA'S THE KAIRO |
| 802,902 | 159.2 | 2 | 0 | CHORDIA'S THE KAIRO |
| 803,903 | 145 | 2 | 0 | CHORDIA'S THE KAIRO |
| 804,904 | 149.1 | 2 | 0 | CHORDIA'S THE KAIRO |
| 805,905 | 165.5 | 2 | 0 | CHORDIA'S THE KAIRO |
| 806,906 | 181.7 | 2 | 0 | CHORDIA'S THE KAIRO |
| 807,907 | 128.9 | 2 | 0 | CHORDIA'S THE KAIRO |
| GF SHOWROOM-1 | 307 | 1 | 0 | CHORDIA'S THE KAIRO |
| GF SHOWROOM-2 | 310.4 | 1 | 0 | CHORDIA'S THE KAIRO |
| GF SHOWROOM-3 | 307.7 | 1 | 0 | CHORDIA'S THE KAIRO |
| LG SHOWROOM-1 | 307 | 1 | 0 | CHORDIA'S THE KAIRO |
| LG SHOWROOM-2 | 310.4 | 1 | 0 | CHORDIA'S THE KAIRO |
| LG SHOWROOM-3 | 307.7 | 1 | 0 | CHORDIA'S THE KAIRO |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-10-17 | |
|---|---|---|
| Proposed completion | 2025-11-24 | |
| Revised completion | 2031-04-30 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2026-Q2 | 2026-07-31 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHIVVILAS REALHOME PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LIMITED | |
| Other projects in this city pack | 6 |
Professional firms
| Role | Firm |
|---|---|
| CA | VINOD KUNAL N ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=lMzag8ZgqxA7gK3I-YngtQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/lMzag8ZgqxA7gK3I-YngtQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=lMzag8ZgqxA7gK3I%2BYngtQ%3D%3D&QuarterIdEnc=lA2coA4x9us9F40n4lwpZg%3D%3D&PT=3&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=e1ggPdJUuj0%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · 2025-11-24 · Sign in to download
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · 2025-11-24 · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Flowchart · Sign in to download
- Declaration with respect to NOC
- NOC from Airport Authority of India
- Board Resolution Letter · Sign in to download
- Audited Balance Sheet of the Promoter for the preceding financial year · Sign in to download
- Declaration in FORM A · Sign in to download
- Declaration of criminal record · Sign in to download
- Declaration of Existing Consultants and or to be appointed in future · Sign in to download
- Declaration of Project Litigation · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Other than Plotted)
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- Bankaffidavit · Sign in to download
- FormR7orR8
- RCertificate
- MCAdata · Sign in to download
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- unitsPlanPath
- Upload_Undertaking · Sign in to download
- R1_filepath · Sign in to download
- R2_filepath · Sign in to download
- R3_filepath · Sign in to download
- RERABankStatementUpload · Sign in to download
- NoLienCertificateUpload
- Building Plan · 2025-10-17