Overview
CHOUHAN GREEN VALLEY
CHOUHAN HOUSING PVT. LTD. · DURG
Units213
Booked183 of 213As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2026-10-04Revised · Proposed 2021-04-29
Registered on2018-05-25
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 30 quarters |
| Technical report | |
| Site & area | 3 site details · 213 unit types |
| Construction & progress | 4 progress details · 30 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 170 documents · 6 source links |
Registration
Registration
| Promoter | CHOUHAN HOUSING PVT. LTD. | |
|---|---|---|
| District | DURG | |
| Regulator | CG RERA | |
| Registration number | PCGRERA250518000015 | |
| Registered on | 2018-05-25 | |
| Project type | Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2021-04-29 | |
| Revised completion | 2026-10-04 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹20,27,88,000 | |
|---|---|---|
| Construction | ₹2,81,00,000 |
Quarterly money flows
| 2018-Q3 | ₹10,174 |
| 2018-Q4 | ₹10,174 |
| 2019-Q1 | ₹8,935 |
| 2019-Q2 | ₹8,345 |
| 2019-Q3 | ₹7,755 |
| 2019-Q4 | ₹5,985 |
| 2020-Q1 | ₹0 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹11,443 |
| 2021-Q4 | ₹10,379 |
| 2022-Q1 | ₹14,335 |
| 2022-Q2 | ₹11,614 |
| 2022-Q3 | ₹15,914 |
| 2022-Q4 | ₹14,913 |
| 2023-Q1 | ₹14,264 |
| 2023-Q2 | ₹14,087 |
| 2023-Q3 | ₹14,087 |
| 2023-Q4 | ₹14,087 |
| 2024-Q1 | ₹10,479 |
| 2024-Q2 | ₹10,479 |
| 2024-Q3 | ₹10,479 |
| 2024-Q4 | ₹10,479 |
| 2025-Q1 | ₹9,830 |
| 2025-Q2 | ₹10,130 |
| 2025-Q3 | ₹10,130 |
| 2025-Q4 | ₹10,130 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 213 | |
|---|---|---|
| Booked | 183 | |
| Booked as of | 2025-12-31 |
Unit types
| A-1 | 1 | 1 |
| A-2 | 1 | 0 |
| A-3 | 1 | 0 |
| A-4 | 1 | 1 |
| A-5 | 1 | 1 |
| A-6 | 1 | 1 |
| A-7 | 1 | 0 |
| A-13 | 1 | 1 |
| A-15 | 1 | 1 |
| A-16 | 1 | 1 |
| A-50 | 1 | 0 |
| A-53 | 1 | 0 |
| B-30 | 1 | 0 |
| B-60 | 1 | 0 |
| B-61 | 1 | 0 |
| B-66 | 1 | 0 |
| B-67 | 1 | 1 |
| B-69 | 1 | 1 |
| B-70 | 1 | 0 |
| B-71 | 1 | 0 |
| B-72 | 1 | 0 |
| B-76 | 1 | 0 |
| B-77 | 1 | 0 |
| B-78 | 1 | 1 |
| B-79 | 1 | 1 |
| B-80 | 1 | 1 |
| C-14 | 1 | 0 |
| C-39 | 1 | 0 |
| L-11 | 1 | 0 |
| L-14 | 1 | 1 |
| L-15 | 1 | 1 |
| L-16 | 1 | 0 |
| L-17 | 1 | 0 |
| L-18 | 1 | 0 |
| L-19 | 1 | 0 |
| L-20 | 1 | 0 |
| L-21 | 1 | 0 |
| L-22 | 1 | 0 |
| L-23 | 1 | 0 |
| L-24 | 1 | 0 |
| L-25 | 1 | 0 |
| L-26 | 1 | 0 |
| L-27 | 1 | 0 |
| L-28 | 1 | 0 |
| L-29 | 1 | 1 |
| A-8 | 1 | 1 |
| A-9 | 1 | 1 |
| A-10 | 1 | 1 |
| A-11 | 1 | 1 |
| A-12 | 1 | 1 |
| A-14 | 1 | 1 |
| A-17 | 1 | 1 |
| A-18 | 1 | 1 |
| A-19 | 1 | 1 |
| A-20 | 1 | 1 |
| A-21 | 1 | 1 |
| A-22 | 1 | 1 |
| A-23 | 1 | 1 |
| A-24 | 1 | 1 |
| A-25 | 1 | 1 |
| A-26 | 1 | 1 |
| A-27 | 1 | 1 |
| A-28 | 1 | 1 |
| A-29 | 1 | 1 |
| A-30 | 1 | 1 |
| A-31 | 1 | 1 |
| A-32 | 1 | 1 |
| A-33 | 1 | 1 |
| A-34 | 1 | 1 |
| A-35 | 1 | 1 |
| A-36 | 1 | 1 |
| A-37 | 1 | 1 |
| A-38 | 1 | 1 |
| A-39 | 1 | 1 |
| A-40 | 1 | 1 |
| A-41 | 1 | 1 |
| A-42 | 1 | 1 |
| A-43 | 1 | 1 |
| A-44 | 1 | 1 |
| A-45 | 1 | 1 |
| A-46 | 1 | 1 |
| A-47 | 1 | 1 |
| A-48 | 1 | 1 |
| A-49 | 1 | 1 |
| A-51 | 1 | 1 |
| A-52 | 1 | 1 |
| A-54 | 1 | 1 |
| B-1 | 1 | 1 |
| B-2 | 1 | 1 |
| B-3 | 1 | 1 |
| B-4 | 1 | 1 |
| B-5 | 1 | 1 |
| B-6 | 1 | 1 |
| B-7 | 1 | 1 |
| B-8 | 1 | 1 |
| B-9 | 1 | 1 |
| B-10 | 1 | 1 |
| B-11 | 1 | 1 |
| B-12 | 1 | 1 |
| B-13 | 1 | 1 |
| B-14 | 1 | 1 |
| B-15 | 1 | 1 |
| B-16 | 1 | 1 |
| B-17 | 1 | 1 |
| B-18 | 1 | 1 |
| B-19 | 1 | 1 |
| B-20 | 1 | 1 |
| B-21 | 1 | 1 |
| B-22 | 1 | 1 |
| B-23 | 1 | 1 |
| B-24 | 1 | 1 |
| B-25 | 1 | 1 |
| B-26 | 1 | 1 |
| B-27 | 1 | 1 |
| B-28 | 1 | 1 |
| B-29 | 1 | 1 |
| B-31 | 1 | 1 |
| B-32 | 1 | 1 |
| B-33 | 1 | 1 |
| B-34 | 1 | 1 |
| B-35 | 1 | 1 |
| B-36 | 1 | 1 |
| B-37 | 1 | 1 |
| B-38 | 1 | 1 |
| B-39 | 1 | 1 |
| B-40 | 1 | 1 |
| B-41 | 1 | 1 |
| B-42 | 1 | 1 |
| B-43 | 1 | 1 |
| B-44 | 1 | 1 |
| B-45 | 1 | 1 |
| B-46 | 1 | 1 |
| B-47 | 1 | 1 |
| B-48 | 1 | 1 |
| B-49 | 1 | 1 |
| B-50 | 1 | 1 |
| B-51 | 1 | 1 |
| B-52 | 1 | 1 |
| B-53 | 1 | 1 |
| B-54 | 1 | 1 |
| B-55 | 1 | 1 |
| B-56 | 1 | 1 |
| B-57 | 1 | 1 |
| B-58 | 1 | 1 |
| B-59 | 1 | 1 |
| B-62 | 1 | 1 |
| B-63 | 1 | 1 |
| B-64 | 1 | 1 |
| B-65 | 1 | 1 |
| B-68 | 1 | 1 |
| B-73 | 1 | 1 |
| B-74 | 1 | 1 |
| B-75 | 1 | 1 |
| C-1 | 1 | 1 |
| C-2 | 1 | 1 |
| C-3 | 1 | 1 |
| C-4 | 1 | 1 |
| C-5 | 1 | 1 |
| C-6 | 1 | 1 |
| C-7 | 1 | 1 |
| C-8 | 1 | 1 |
| C-9 | 1 | 1 |
| C-10 | 1 | 1 |
| C-11 | 1 | 1 |
| C-12 | 1 | 1 |
| C-13 | 1 | 1 |
| C-15 | 1 | 1 |
| C-16 | 1 | 1 |
| C-17 | 1 | 1 |
| C-18 | 1 | 1 |
| C-19 | 1 | 1 |
| C-20 | 1 | 1 |
| C-21 | 1 | 1 |
| C-22 | 1 | 1 |
| C-23 | 1 | 1 |
| C-24 | 1 | 1 |
| C-25 | 1 | 1 |
| C-26 | 1 | 1 |
| C-27 | 1 | 1 |
| C-28 | 1 | 1 |
| C-29 | 1 | 1 |
| C-30 | 1 | 1 |
| C-31 | 1 | 1 |
| C-32 | 1 | 1 |
| C-33 | 1 | 1 |
| C-34 | 1 | 1 |
| C-35 | 1 | 1 |
| C-36 | 1 | 1 |
| C-37 | 1 | 1 |
| C-38 | 1 | 1 |
| D-1 | 1 | 1 |
| D-2 | 1 | 1 |
| D-3 | 1 | 1 |
| D-4 | 1 | 1 |
| D-5 | 1 | 1 |
| D-6 | 1 | 1 |
| D-7 | 1 | 1 |
| D-8 | 1 | 1 |
| L-1 | 1 | 1 |
| L-2 | 1 | 1 |
| L-3 | 1 | 1 |
| L-4 | 1 | 1 |
| L-5 | 1 | 1 |
| L-6 | 1 | 1 |
| L-7 | 1 | 1 |
| L-8 | 1 | 1 |
| L-9 | 1 | 1 |
| L-10 | 1 | 1 |
| L-12 | 1 | 1 |
| L-13 | 1 | 1 |
| L-30 | 1 | 1 |
| C-40 | 1 | 1 |
| C-41 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-12-31 | |
| Proposed completion | 2021-04-29 | |
| Revised completion | 2026-10-04 |
Quarterly progress
| 2018-Q3 | 25% |
| 2018-Q4 | 0% |
| 2019-Q1 | 0% |
| 2019-Q2 | 0% |
| 2019-Q3 | 0% |
| 2019-Q4 | 0% |
| 2020-Q1 | 1% |
| 2020-Q2 | 0% |
| 2020-Q3 | 0% |
| 2020-Q4 | 6% |
| 2021-Q1 | 6% |
| 2021-Q2 | 6% |
| 2021-Q3 | 6% |
| 2021-Q4 | 13% |
| 2022-Q1 | 17% |
| 2022-Q2 | 31% |
| 2022-Q3 | 37% |
| 2022-Q4 | 42% |
| 2023-Q1 | 59% |
| 2023-Q2 | 64% |
| 2023-Q3 | 71% |
| 2023-Q4 | 79% |
| 2024-Q1 | 81% |
| 2024-Q2 | 88% |
| 2024-Q3 | 92% |
| 2024-Q4 | 93% |
| 2025-Q1 | 99% |
| 2025-Q2 | 99% |
| 2025-Q3 | 99% |
| 2025-Q4 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CHOUHAN HOUSING PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=Mjk=
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities