Overview
CITY OF DREAMS 4, KHARAR
Singla Builders and promoters limited · Sahibzada Ajit Singh Nagar (Mohali)
Units1
Completion2025-03-31Proposed
Valid to2027-01-26
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details · 18 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 11 documents · 23 source links |
Registration
Registration
| Promoter | Singla Builders and promoters limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS80-PR0781 | |
| Valid to | 2027-01-26 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2025-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| CLU Certificate |
| License to develop colony or society from Competent Authority |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹48,99,69,375 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 23,659.41 | |
|---|---|---|
| Units | 1 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| PLOTS | 12,744 | 1 | EWS SITE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-03-16 | |
|---|---|---|
| Proposed completion | 2025-03-31 |
Quarterly progress
| 2022-Q2 | 2022-11-24 |
| 2022-Q3 | 2022-11-24 |
| 2022-Q4 | 2023-05-12 |
| 2023-Q1 | 2023-05-12 |
| 2023-Q2 | 2023-08-25 |
| 2023-Q3 | 2024-01-18 |
| 2023-Q4 | 2024-01-18 |
| 2024-Q1 | 2024-10-15 |
| 2024-Q2 | 2024-10-15 |
| 2024-Q3 | 2024-10-15 |
| 2024-Q4 | 2025-02-24 |
| 2025-Q1 | 2025-04-15 |
| 2025-Q2 | 2025-07-15 |
| 2025-Q3 | 2026-05-15 |
| 2025-Q4 | 2026-05-15 |
| 2026-Q1 | 2026-05-15 |
| 2026-Q2 | 2026-07-25 |
| 2026-Q3 | 2026-10-13 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Singla Builders and promoters limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11169&inPromoter_ID=2001&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License to develop colony or society from Competent Authority
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- License to develop colony or society from Competent Authority
- 2022-Q2 · 2022-11-24
- 2022-Q3 · 2022-11-24
- 2022-Q4 · 2023-05-12
- 2023-Q1 · 2023-05-12
- 2023-Q2 · 2023-08-25
- 2023-Q3 · 2024-01-18
- 2023-Q4 · 2024-01-18
- 2024-Q1 · 2024-10-15
- 2024-Q2 · 2024-10-15
- 2024-Q3 · 2024-10-15
- 2024-Q4 · 2025-02-24
- 2025-Q1 · 2025-04-15
- 2025-Q2 · 2025-07-15
- 2025-Q3 · 2026-05-15
- 2025-Q4 · 2026-05-15
- 2026-Q1 · 2026-05-15
- 2026-Q2 · 2026-07-25
- 2026-Q3 · 2026-10-13