Overview
CITY REAL ESTATE
CITY REAL ESTATE (BAHADUR SINGH, KULVINDER SINGH, GANESH DUTT DEWEDI, SHIVANGI SHARMA, JASBIR SINGH SAINI, NIRMALA DEVI, SANTOSH KUMARI, CHARNO DEVI) · Una
Units110
Registered on2023-05-08
Valid to2024-11-08
Approvals7
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Disputes & cases | 0 project complaints |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 32 unit types |
| Construction & progress | 13 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 39 documents · 34 source links |
Registration
Registration
| Promoter | CITY REAL ESTATE (BAHADUR SINGH, KULVINDER SINGH, GANESH DUTT DEWEDI, SHIVANGI SHARMA, JASBIR SINGH SAINI, NIRMALA DEVI, SANTOSH KUMARI, CHARNO DEVI) | |
|---|---|---|
| District | Una | |
| Regulator | Himachal Pradesh Real Estate Regulatory Authority | |
| Registration number | HPRERAUNA2023056/P | |
| Registered on | 2023-05-08 | |
| Valid to | 2024-11-08 | |
| Project type | Plotted (Residential) | |
| Status (as filed) | New Project Launch |
Approvals
Is it approved for its use?
Approvals
Approvals
| Plan sanction | 3050 | Special Area Development Authority (SADA) |
| Structural Stability Certificate | ||
| NOC/Consent to Operate from Pollution Control Board | ||
| Sanctioned Letter by TCP/ULB(s)/Local Authority * | ||
| Sanctioned Location Plan * | ||
| Sanctioned Site Plan * | ||
| Sanctioned Building Plan * |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,70,00,000 | |
|---|---|---|
| Construction | ₹90,00,000 | |
| Total | ₹2,60,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 37,024 | |
|---|---|---|
| Units | 110 |
Unit types
| 64 | 1 | BLOCK-1 |
| 59 | 1 | BLOCK-2 |
| 31, 42, 43 AND 54 | 4 | BLOCK-3 |
| 56, 57, 58, 65, 66 AND 67 | 6 | BLOCK-4 |
| 32, 33, 34, 35, 38, 39, 40, 41, 44, 45, 46, 47, 50, 51, 52 AND 53 | 16 | BLOCK-5 |
| 36, 37, 48 AND 49 | 4 | BLOCK-6 |
| 25 AND 26 | 2 | BLOCK -7 |
| 69, 72 AND 73 | 3 | BLOCK-8 |
| 1, 2, 3, 6, 7, 8, 9, 10, 11, 12, 13, 16, 17, 18, 19, 20, 21, 22, 23, 24, 27, 28, 29 AND 30 | 24 | BLOCK-9 |
| 4, 5, 14 AND 15 | 4 | BLOCK-10 |
| 70, 71 AND 74 | 3 | BLOCK -11 |
| 68 | 1 | BLOCK -12 |
| 55 | 1 | BLOCK -13 |
| 63 | 1 | BLOCK -14 |
| 62 | 1 | BLOCK -15 |
| 61 | 1 | BLOCK -16 |
| 60 | 1 | BLOCK -17 |
| 1 TO 15 | 15 | LIG |
| 1 | 1 | EWS -1 |
| 2 | 1 | EWS -2 |
| 3 | 1 | EWS -3 |
| 4 | 1 | EWS -4 |
| 1 TO 8 | 8 | SHOPS |
| 9 | 1 | SHOP |
| 10 | 1 | SHOP |
| 11 | 1 | SHOP |
| 12 | 1 | SHOP |
| 13 | 1 | SHOP |
| 14 | 1 | SHOP |
| 15 | 1 | SHOP |
| 16 | 1 | SHOP |
| 17 | 1 | SHOP |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Quarterly progress
| Quarter |
|---|
| 2023-Q2 |
| 2023-Q3 |
| 2023-Q4 |
| 2024-Q1 |
| 2024-Q2 |
| 2024-Q3 |
| 2024-Q4 |
| 2025-Q1 |
| 2025-Q2 |
| 2025-Q3 |
| 2025-Q4 |
| 2026-Q1 |
| 2026-Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CITY REAL ESTATE (BAHADUR SINGH, KULVINDER SINGH, GANESH DUTT DEWEDI, SHIVANGI SHARMA, JASBIR SINGH SAINI, NIRMALA DEVI, SANTOSH KUMARI, CHARNO DEVI) | |
|---|---|---|
| Type | Other | |
| Escrow bank | UCO BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://hprera.nic.in/Complaints/Litigation/Litigation_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D
- https://hprera.nic.in/Home/PRGrid
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2023-24
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2024-25
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2025-26
- https://hprera.nic.in/Home/ProjectsQPR?FnYr=2026-27
- https://hprera.nic.in/Project/ProjectRegistration/AssociatedVendors_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/BankDetails_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/Documents_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/InventoryDetails_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/PastProjectDetails_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/Payment_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/ProjectDetails_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/Project/ProjectRegistration/PromotorDetails_PreviewPV?qs=f3fIU7vFXK1PDlMT4n74b27izFWnRjZWhc2wsy8TJSA1V42kcMc%2FDfj796RJGwwYvKIxKkp%2FTX9Gh7htueH4XH5HwWNKBstymlQ%2FWyyzki3u2Y6z8INBtg%3D%3D&UpdatedChangeDets=N
- https://hprera.nic.in/PublicDashboard/GetFilteredProjectsPV?DistrictList%5B0%5D.Selected=false&DistrictList%5B0%5D.Value=18&DistrictList%5B1%5D.Selected=false&DistrictList%5B1%5D.Value=24&DistrictList%5B2%5D.Selected=false&DistrictList%5B2%5D.Value=20&DistrictList%5B3%5D.Selected=false&DistrictList%5B3%5D.Value=23&DistrictList%5B4%5D.Selected=false&DistrictList%5B4%5D.Value=25&DistrictList%5B5%5D.Selected=false&DistrictList%5B5%5D.Value=22&DistrictList%5B6%5D.Selected=false&DistrictList%5B6%5D.Value=26&DistrictList%5B7%5D.Selected=false&DistrictList%5B7%5D.Value=21&DistrictList%5B8%5D.Selected=false&DistrictList%5B8%5D.Value=15&DistrictList%5B9%5D.Selected=false&DistrictList%5B9%5D.Value=17&DistrictList%5B10%5D.Selected=false&DistrictList%5B10%5D.Value=16&DistrictList%5B11%5D.Selected=false&DistrictList%5B11%5D.Value=19&PlottedTypeList%5B0%5D.Selected=false&PlottedTypeList%5B0%5D.Value=P&PlottedTypeList%5B1%5D.Selected=false&PlottedTypeList%5B1%5D.Value=F&PlottedTypeList%5B2%5D.Selected=false&PlottedTypeList%5B2%5D.Value=M&ResidentialTypeList%5B0%5D.Selected=false&ResidentialTypeList%5B0%5D.Value=R&ResidentialTypeList%5B1%5D.Selected=false&ResidentialTypeList%5B1%5D.Value=C&ResidentialTypeList%5B2%5D.Selected=false&ResidentialTypeList%5B2%5D.Value=M&AreaFrom=&AreaUpto=&SearchText=
- Registration No. · Sign in to download
- GSTIN No. · Sign in to download
- BAHADUR SINGH Gender : · Sign in to download
- KULVINDER KAUR Gender : · Sign in to download
- GANESH DUTT DEWEDI Gender : · Sign in to download
- SHIVANGI SHARMA Gender : · Sign in to download
- JASBIR SINGH SAINI Gender : · Sign in to download
- NIRMALA DEVI Gender : · Sign in to download
- SANTOSH KUMARI Gender : · Sign in to download
- CHARNO DEVI Gender : · Sign in to download
- BAHADUR SINGH Gender : · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2023-04-28 · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2023-04-28 · Sign in to download
- Income Tax Return (ITR) Acknowledgement * · 2023-04-28 · Sign in to download
- Project Report · 2022-10-10 · Sign in to download
- Brochure of the Project · 2022-10-10 · Sign in to download
- Structural Stability Certificate · 2023-01-03
- NOC/Consent to Operate from Pollution Control Board · 2023-04-05
- demarcation report · 2022-12-09 · Sign in to download
- Declaration from Promoter · 2023-03-20 · Sign in to download
- Sanctioned Letter by TCP/ULB(s)/Local Authority * · 2022-10-14
- Sanctioned Location Plan * · 2022-09-27
- Documents/Drawings document · 2022-09-27
- Sanctioned Site Plan * · 2022-09-27
- Sanctioned Building Plan * · 2022-10-14
- Project Specifications * · 2022-09-27 · Sign in to download
- Undertaking Regarding Past Project · 2022-09-27 · Sign in to download
- GPA · 2023-03-21 · Sign in to download
- Payment Receipt UTI NO - CNRBR52023040352797053 (RERA Fees) · 2023-04-29 · Sign in to download
- Park · 2022-10-26 · Sign in to download
- Civic Facilities and Amenities · 2022-09-27 · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Consent Letter · Sign in to download
- Certificate · Sign in to download
- Account Details Proof · Sign in to download
- Bank Draft · Sign in to download
- Structural Stability Certificate
- NOC/Consent to Operate from Pollution Control Board
- Sanctioned Letter by TCP/ULB(s)/Local Authority *
- Sanctioned Location Plan *
- Sanctioned Site Plan *
- Sanctioned Building Plan *
- 2023-Q2
- 2023-Q3
- 2023-Q4
- 2024-Q1
- 2024-Q2
- 2024-Q3
- 2024-Q4
- 2025-Q1
- 2025-Q2
- 2025-Q3
- 2025-Q4
- 2026-Q1
- 2026-Q2