Overview
COLONNADE
EMAAR INDIA LIMITED (FORMERLY KNOWN AS EMAAR MGF LAND LTD.) · Gurugram
Completion2021-12-31Revised · Proposed 2021-12-31
Registered on2017-08-28
Valid to2023-12-31
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 20 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 29 documents · 2 source links |
Registration
Registration
| Promoter | EMAAR INDIA LIMITED (FORMERLY KNOWN AS EMAAR MGF LAND LTD.) | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 156 OF 2017 DATED 28.08.2017 | |
| Registered on | 2017-08-28 | |
| Valid to | 2023-12-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2021-12-31 | |
| Revised completion | 2021-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 163 of 2008 | Town & Country Planning Department | |
| Layout Plan | 2020-09-02 | ||
| Building Plan | 2020-09-02 | ||
| I. LICENSE | 2008-08-19 | ||
| II. ENVIRONMENTAL CLEARANCE | 2016-09-15 | ||
| III. NOC FOR HEIGHT CLEARANCE | 2015-03-27 | ||
| IV. APPROVAL FOR FIRE FIGHTING | 2017-04-19 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,23,00,000 | |
|---|---|---|
| Construction | ₹1,46,40,00,000 | |
| Total | ₹2,45,61,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 350 |
|---|
Unit types
| Type |
|---|
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
| 10 |
| 11 |
| 12 |
| 13 |
| 14 |
| 15 |
| 16 |
| 17 |
| 18 |
| 19 |
| 20 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-09-01 | |
|---|---|---|
| Proposed completion | 2021-12-31 | |
| Revised completion | 2021-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | EMAAR INDIA LIMITED (FORMERLY KNOWN AS EMAAR MGF LAND LTD.) | |
|---|---|---|
| Type | Company | |
| Escrow bank | KOTAK MAHINDRA BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1303
- Registration Certificate · 2017-08-28
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-03-16
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-03-16
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-03-16
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2020-03-16 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-02-17 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2021-02-17 · Sign in to download
- LOI 2.25 ACRES COMMERCIAL · 2021-02-17 · Sign in to download
- NON ENCUMBRANCE CERTIFICATE · 2021-02-18 · Sign in to download
- BBA & ALLOTMENT LETTER · 2021-02-18 · Sign in to download
- BOARD RESOLUTION · 2021-02-18 · Sign in to download
- BUILDING PLAN REVISION PRINCIPLE APPROVAL · 2021-02-18
- CA CERTIFICATE OF SOURCES OF FUND · 2021-02-18 · Sign in to download
- ENVIRONMENT CLEARANCE · 2021-02-18
- FIRE FIGHTING SCHEME APPROVAL FOR 2.25 ACRES · 2021-02-18
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2021-02-18 · Sign in to download
- NOC AIRPORT AUTHORITY OF INDIA · 2021-02-18
- ANNUAL REPORT - 2019-20 · 2021-02-18 · Sign in to download
- BASEMENT 04 PLAN · 2021-02-18
- SITE PLAN-GARDEN HYDRANT AND FLUSHING LAYOUT SCHEME · 2021-02-18
- SITE PLAN-POWER SUPPLY · 2021-02-18
- SITE PLAN-ROAD LAYOUT SCHEME · 2021-02-18
- SITE PLAN-SEWERAGE LAYOUT SCHEME · 2021-02-18
- STREET LIGHT AND PARKING LAYOUT · 2021-02-18 · Sign in to download
- ANNUAL REPORT - 2017-18 · 2021-02-18 · Sign in to download
- ANNUAL REPORT 2018-19 · 2021-02-18 · Sign in to download
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/156 OF 2017/7(3)/25/2023/02 DATED 03.02.2023 · 2023-02-10 · Sign in to download
- OC uploaded · 2023-08-04 · Sign in to download
- CC uploaded · 2025-12-12 · Sign in to download