Overview
COMMERCIAL COLONY
EXPERION DEVELOPERS PVT. LTD. & OTHERS · Gurugram
Units0
Completion2021-03-31Revised · Proposed 2021-03-31
Registered on2017-10-23
Valid to2018-10-22
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 1 unit type |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 23 documents · 3 source links |
Registration
Registration
| Promoter | EXPERION DEVELOPERS PVT. LTD. & OTHERS | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 329 OF 2017 DATED 23.10.2017 | |
| Registered on | 2017-10-23 | |
| Valid to | 2018-10-22 | |
| Status (as filed) | Registered | |
| Proposed completion | 2021-03-31 | |
| Revised completion | 2021-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | License No. 63 of 2008 dated 20.03.2008 and License No. 92 of 2010 dated 30.10.2010 | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | |||
| I. OCCUPATION CERTIFICATE | 2019-01-15 | ||
| II. OCCUPATION CERTIFICATE | 2022-05-31 | ||
| III. BUILDING PLAN APPROVAL | 2015-12-07 | ||
| IV. ENVIRONMENT CLEARANCE APPROVAL | 2013-10-23 | ||
| V. FOREST NOC | 2013-01-10 | ||
| VI. FIRE FIGHTING APPROVAL | 2017-03-29 | ||
| VII. AIRPORT HEIGHT CLEARANCE APPROVAL | 2015-07-01 | ||
| VIII. SERVICE PLAN ESTIMATE APPROVAL | 2018-09-11 | ||
| IX. ELECTRICITY APPROVAL | 2016-10-21 | ||
| X. HUDA CONSTRUCTION WATER NOC | 2013-08-21 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹40,00,000 | |
|---|---|---|
| Construction | ₹1,32,61,33,000 | |
| Total | ₹3,00,85,27,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,985.081 | |
|---|---|---|
| FAR | 1.87 | |
| Units | 0 |
Unit types
| Type | Units |
|---|---|
| 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-10-23 | |
|---|---|---|
| Proposed completion | 2021-03-31 | |
| Revised completion | 2021-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | EXPERION DEVELOPERS PVT. LTD. & OTHERS | |
|---|---|---|
| Escrow bank | ICICI BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2383
- https://nominatim.openstreetmap.org/search?q=sector+15%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-10-23
- WATER CONNECTION APPROVAL · 2023-03-01
- ZONING PLAN · 2023-03-15
- ELECTRICITY APPROVAL · 2023-03-15
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2023-03-15 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2023-03-01 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2023-03-01 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2023-03-01
- OCCUPATION CERTIFICATE · 2023-03-01 · Sign in to download
- FIRE FIGHTING · 2023-03-15 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2023-03-01
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2023-03-16 · Sign in to download
- FOREST APPROVAL · 2023-03-01
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2023-03-01
- APPROVED SERVICE ESTIMATE · 2023-03-15 · Sign in to download
- ENVIRONMENT CLEARANCE APPROVAL · 2023-03-01
- ARAVALI NOC · 2023-03-15
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2023-03-15
- REGISTERED DEVELOPMENT AGREEMENT · 2023-03-15 · Sign in to download
- AIRPORT HEIGHT CLEARANCE APPROVAL · 2023-03-15
- OC uploaded · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download
- Oc uploaded · 2023-08-08 · Sign in to download