Overview
CONDOR ASTER -2
CONDOR BUILDERS PVT LTD · Pin Code 695583
Units51
Booked30 of 51
Construction progress6%
Completion2030-07-31Proposed
Registered on2026-04-23
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 4 unit types |
| Construction & progress | 3 progress details · 3 quarters |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 42 documents · 5 source links |
Registration
Registration
| Promoter | CONDOR BUILDERS PVT LTD | |
|---|---|---|
| District | Thiruvananthapuram | |
| Locality | Pin Code 695583 | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/TVM/056/2026 | |
| Registered on | 2026-04-23 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2030-07-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/55604/2025 | 2025-07-23 | 2030-07-22 | THIRUVANANTHAPURAM CORPORATION |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,476 | |
|---|---|---|
| Built-up (m²) | 11,067.77 | |
| Towers | 0 | |
| Units | 51 | |
| Booked | 30 |
Unit types
| 2BHK | 12 | 5 | CONDOR ASTER -2 |
| 3BHK | 13 | 10 | CONDOR ASTER -2 |
| 3BHK | 13 | 6 | CONDOR ASTER -2 |
| 3BHK | 13 | 9 | CONDOR ASTER -2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 6% | |
|---|---|---|
| Start | 2026-01-01 | |
| Proposed completion | 2030-07-31 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CONDOR BUILDERS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF BARODA | |
| Other projects in this city pack | 4 |
Professional firms
| Role | Firm |
|---|---|
| Architect | JCJR PARTNERSHIP |
| Engineer | FELLOW OF INSTIUTE OF ENGINEERS |
| CA | SRIDHAR AND CO |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/12043
- https://rera.kerala.gov.in/projects?district=601&page=5
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=qj7T%2Bt0TYA2XMhnyUz1PJUcRYmPJNHILbpIDlnAlQSLSizLIitOWJ0HZ2t%2BEhr2pmhCSGpZUzw4RV%2F1eGfZ2fsqib30pfO5O6yn%2B7KyyXOeW6GFGyk%2BKYq1pKrsCxv5auSyJ9i4MwNq2g%2FoNA%2FBQF3KEmq4pzq1boooW617JvDdBo0xXqi2hXg%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=12043&Division=1&UserID=30153&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2026-04-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-29
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-06
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-06
- Copy of Valid Building Permit · 2025-11-29
- Detailed technical specifications to be adopted in the project · 2025-12-01 · Sign in to download
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2025-11-29 · Sign in to download
- Site Plan / Site Map · 2025-12-01
- Other · 2025-11-29 · Sign in to download
- Other · 2025-11-29 · Sign in to download
- Other · 2026-01-06 · Sign in to download
- Other · 2026-01-06 · Sign in to download
- Other · 2026-01-06 · Sign in to download
- Other · 2026-01-07 · Sign in to download
- Other · 2026-01-07 · Sign in to download
- Clearance from Airport Authority of India · 2025-11-29 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2026-01-06 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2026-01-06 · Sign in to download
- Environment Clearance · 2025-12-01 · Sign in to download
- Initial NOC from Fire and Rescue department · 2025-12-01
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Others · 2026-01-06 · Sign in to download
- Charts and the project schedule · 2025-12-01 · Sign in to download
- List and details of common amenities · 2025-12-01 · Sign in to download
- Other Plans to be executed in the proposed project · 2025-12-01
- Plan for Drinking water service to be executed in the proposed project · 2025-12-01
- Plan of firefighting to be executed in the proposed project · 2025-12-01
- Plan of Use of renewable energy to be executed in the proposed project · 2025-12-01