Overview
CONFIDENT LAKESIDE
Confident Projects Residential · Ernakulam
Units154
Booked48 of 154
Construction progress1%
Completion2031-05-20Proposed
Registered on2025-12-23
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 3 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 41 documents · 5 source links |
Registration
Registration
| Promoter | Confident Projects Residential | |
|---|---|---|
| District | Ernakulam | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/ERN/170/2025 | |
| Registered on | 2025-12-23 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2031-05-20 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/119772/2025 | 2025-11-11 | 2030-11-10 | KIZHAKKAMBALAM GRAMA PANCHAYAT |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,788 | |
|---|---|---|
| Built-up (m²) | 19,876.59 | |
| Towers | 0 | |
| Units | 154 | |
| Booked | 48 |
Unit types
| Type | Units | Booked | Tower |
|---|---|---|---|
| 2BHK | 77 | 35 | CONFIDENT LAKESIDE |
| 3BHK | 77 | 13 | CONFIDENT LAKESIDE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 1% | |
|---|---|---|
| Start | 2026-01-20 | |
| Proposed completion | 2031-05-20 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Confident Projects Residential | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | YES BANK | |
| Other projects in this city pack | 48 |
Professional firms
| Role | Firm |
|---|---|
| CA | LV & Co Chartered Accountants |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/12034
- https://rera.kerala.gov.in/projects?district=595&page=6
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=YmpK7k%2FJwa%2FQJ92UOtQeVqQharhUEvrv%2B5Ec0LNGfKQNH%2Fpsysg5ewcSQLaGMHG3R1xO8Bw0IQ7bbUSV3r%2FY%2FWxWK%2FSjFeKCBkRaedt4fEfsO9vTq93eCQTFQFZXVEj%2BqOOVKku3udsNhOOCvKAiTYQFeiXLMYFxexCxKl1ze%2F3jzCp8URrjtg%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=12034&Division=1&UserID=30156&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Signed project certificate · 2025-12-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2025-11-21
- Copy of Valid Building Permit · 2025-11-20
- Detailed technical specifications to be adopted in the project · 2025-11-24 · Sign in to download
- Layout approval plan · 2025-11-21
- Layout approval plan · 2025-11-21
- Layout approval plan · 2025-11-21
- Layout approval plan · 2025-11-21
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2025-11-27 · Sign in to download
- Site Plan / Site Map · 2025-11-21
- Other · 2025-11-27 · Sign in to download
- Other · 2025-11-27 · Sign in to download
- Other · 2025-11-27 · Sign in to download
- Other · 2025-11-27 · Sign in to download
- Other · 2025-11-27 · Sign in to download
- Clearance from Airport Authority of India · 2025-11-21 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2025-11-20 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2025-11-20 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2025-11-20
- Consent to establish (Clearance from Pollution Control Board) · 2025-11-20 · Sign in to download
- Environment Clearance · 2025-11-24 · Sign in to download
- Initial NOC from Fire and Rescue department · 2025-11-20
- Others · 2025-11-20 · Sign in to download
- Others · 2025-11-20 · Sign in to download
- Charts and the project schedule · 2025-11-27 · Sign in to download
- List and details of common amenities · 2025-11-24 · Sign in to download
- Other Plans to be executed in the proposed project · 2025-11-28
- Plan for Drinking water service to be executed in the proposed project · 2025-11-28
- Plan of firefighting to be executed in the proposed project · 2025-11-20
- Plan of Use of renewable energy to be executed in the proposed project · 2025-11-28