Overview
CONSTRUCTION OF 63 NO LIG & 29 NO. EWS HOUSES UNDRE ATAL VIHAR YOJNA AT JORATAL
CHHATTISGARH HOUSING BOARD DIVISION-KAWARDHA · KABIRDHAM
Units92
Booked68 of 92As of 2026-06-30
Construction progress20%As of 2026-06-30
Completion2030-04-04Revised · Proposed 2029-12-04
Registered on2025-01-10
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 2 cost heads · 6 quarters |
| Technical report | |
| Site & area | 3 site details · 92 unit types |
| Construction & progress | 4 progress details · 6 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 44 documents · 8 source links |
Registration
Registration
| Promoter | CHHATTISGARH HOUSING BOARD DIVISION-KAWARDHA | |
|---|---|---|
| District | KABIRDHAM | |
| Regulator | CG RERA | |
| Registration number | PCGRERA100125001865 | |
| Registered on | 2025-01-10 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2029-12-04 | |
| Revised completion | 2030-04-04 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,48,94,000 | |
|---|---|---|
| Construction | ₹15,61,93,000 |
Quarterly money flows
| 2025-Q1 | ₹2,46,610 |
| 2025-Q2 | ₹8,27,820 |
| 2025-Q3 | ₹11,44,684.6 |
| 2025-Q4 | ₹58,52,161.1 |
| 2026-Q1 | ₹15,04,476.5 |
| 2026-Q2 | ₹46,01,315.2 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 92 | |
|---|---|---|
| Booked | 68 | |
| Booked as of | 2026-06-30 |
Unit types
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 104 | 1 | 0 |
| 1BHK | 104 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
| 1BHK | 56.1 | 1 | 1 |
| 1BHK | 56.1 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 20% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2029-12-04 | |
| Revised completion | 2030-04-04 |
Quarterly progress
| 2025-Q1 | 1% |
| 2025-Q2 | 1% |
| 2025-Q3 | 1% |
| 2025-Q4 | 1% |
| 2026-Q1 | 12% |
| 2026-Q2 | 20% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CHHATTISGARH HOUSING BOARD DIVISION-KAWARDHA | |
|---|---|---|
| Type | Authority | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MjI5OA==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Development Permission from competent authorities
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Agent Details
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Development Permission from competent authorities