CONSTRUCTION OF 63 NO LIG & 29 NO. EWS HOUSES UNDRE ATAL VIHAR YOJNA AT JORATAL

CHHATTISGARH HOUSING BOARD DIVISION-KAWARDHA · KABIRDHAM
Units92
Booked68 of 92As of 2026-06-30
Construction progress20%As of 2026-06-30
Completion2030-04-04Revised · Proposed 2029-12-04
Registered on2025-01-10
Approvals5

Sections

Property title & search report
Approvals5 approvals
Contract & costs2 cost heads · 6 quarters
Technical report
Site & area3 site details · 92 unit types
Construction & progress4 progress details · 6 quarters
Developer & finance
Developer3 developer details
The evidence
Sources44 documents · 8 source links

Registration

Registration

PromoterCHHATTISGARH HOUSING BOARD DIVISION-KAWARDHA
DistrictKABIRDHAM
RegulatorCG RERA
Registration numberPCGRERA100125001865
Registered on2025-01-10
Project typeGroup Housing
Status (as filed)New
Proposed completion2029-12-04
Revised completion2030-04-04