Overview
Construction of two hundred fifty six flats at Madhuban Bapudham Scheme
GHAZIABAD DEVELOPMENT AUTHORITY · Ghaziabad
Units256
Completion2019-05-31Proposed
Registered on2018-09-14
Valid to2019-05-31
Approvals1
Complaints7As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 7 project complaints · 98 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 20 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 6 documents · 7 source links |
Registration
Registration
| Promoter | GHAZIABAD DEVELOPMENT AUTHORITY | |
|---|---|---|
| District | Ghaziabad | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ17106 | |
| Registered on | 2018-09-14 | |
| Valid to | 2019-05-31 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2019-05-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | memo/niyojan/2016 | 2016-08-05 | 2021-08-04 | Ghaziabad Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 7 | |
|---|---|---|
| Promoter | 98 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹10,05,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 6,100 | |
|---|---|---|
| Towers | 5 | |
| Maximum floors | 3 | |
| Units | 256 |
Unit types
| 1 BHK | 25.8 | 16 | Tower One | GF |
| 1 BHK | 25.8 | 16 | Tower One | 1 |
| 1 BHK | 25.8 | 16 | Tower One | 2 |
| 1 BHK | 25.8 | 16 | Tower One | 3 |
| 1 BHK | 25.8 | 16 | Tower Two | GF |
| 1 BHK | 25.8 | 16 | Tower Two | 1 |
| 1 BHK | 25.8 | 16 | Tower Two | 2 |
| 1 BHK | 25.8 | 16 | Tower Two | 3 |
| 1 BHK | 25.8 | 16 | Tower Three | GF |
| 1 BHK | 25.8 | 16 | Tower Three | 1 |
| 1 BHK | 25.8 | 16 | Tower Three | 2 |
| 1 BHK | 25.8 | 16 | Tower Three | 3 |
| 1 BHK | 25.8 | 8 | Tower Four A | GF |
| 1 BHK | 25.8 | 8 | Tower Four A | 1 |
| 1 BHK | 25.8 | 8 | Tower Four A | 2 |
| 1 BHK | 25.8 | 8 | Tower Four A | 3 |
| 1 BHK | 25.8 | 8 | Tower Four B | GF |
| 1 BHK | 25.8 | 8 | Tower Four B | 1 |
| 1 BHK | 25.8 | 8 | Tower Four B | 2 |
| 1 BHK | 25.8 | 8 | Tower Four B | 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-06-27 | |
|---|---|---|
| Proposed completion | 2019-05-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GHAZIABAD DEVELOPMENT AUTHORITY | |
|---|---|---|
| Type | Other | |
| Escrow bank | PNB | |
| Other projects in this city pack | 23 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=+NAb6ft/NAk=&hfFlag=q5Tk0QUeJB8oatkp/Oqbxw==&NPJ6RAme=a89NPbir64thsZSAfZ5px3evF3bdTygqLkI+Vo1j6InB5uUyW5Wk+7q/G68/F8pEnqFKLmqN3OTLdRZqKn/DbRYA2diQYSC7lmlnqdJVzXE=&PaURJEMAN4=ZL9MNERkNdZli7v0iX8O6A==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GHAZIABAD
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=%2BNAb6ft/NAk=
- Commencement Certificate · 2018-08-24
- Other Plan(If Any) · 2018-08-24
- Waste Disposal Plan · 2018-08-24
- Water Supply Plan · 2019-01-03
- Electricity Supply Plan · 2018-08-24
- Development Work Plan · 2019-01-03