DOSLChhattisgarh Workspace

Overview

CRYSTAL GREEN PHASE- II

BHATIA VATIKA · RAIGARH
Units85
Booked46 of 85As of 2021-03-31
Construction progress100%As of 2021-03-31
Completion2023-06-30Revised · Proposed 2022-12-31
Registered on2018-07-13
Approvals2

Sections

Property title & search report
Approvals2 approvals
Contract & costs2 cost heads · 11 quarters
Technical report
Site & area3 site details · 1 unit type
Construction & progress4 progress details · 11 quarters
Developer & finance
Developer4 developer details
The evidence
Sources79 documents · 5 source links

Registration

Registration

PromoterBHATIA VATIKA
DistrictRAIGARH
RegulatorCG RERA
Registration numberPCGRERA130718000519
Registered on2018-07-13
Project typePlotted Development
Status (as filed)Ongoing
Proposed completion2022-12-31
Revised completion2023-06-30