Overview
DADRI LAND AND FINANCE
DADRI LAND & FINANCE · Bhiwani
Units237
Completion2024-06-09Proposed
Valid to2024-06-09
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 2 source links |
Registration
Registration
| Promoter | DADRI LAND & FINANCE | |
|---|---|---|
| District | Bhiwani | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-BHW-283-2021 | |
| Valid to | 2024-06-09 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-06-09 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 05 OF 2019(24-01-2019) | Town & Country Planning Department | |
| Layout Plan | 2019-01-24 | ||
| Building Plan | 2020-02-04 | ||
| I. LAYOUT | 2019-01-25 | ||
| II. DEMARCATION | 2019-06-21 | ||
| III. ZONING | 2019-11-05 | ||
| IV. SERVICE PLAN ESTIMATES | 2019-07-26 | ||
| V. ELECTRICAL PLAN | 2020-01-07 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹89,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹4,69,56,500 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 46,158.44 | |
|---|---|---|
| FAR | 65 | |
| Units | 237 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Plot | 237 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-06-09 | |
|---|---|---|
| Proposed completion | 2024-06-09 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DADRI LAND & FINANCE | |
|---|---|---|
| Type | Company | |
| Escrow bank | PUNJAB NATIONAL BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/view_project/project_preview_open/1441
- Registration Certificate
- (Supplementary Document) · 2020-12-23 · Sign in to download
- (Supplementary Document) · 2020-12-24 · Sign in to download
- (Supplementary Document) · 2020-12-24 · Sign in to download
- (Supplementary Document) · 2020-12-24 · Sign in to download
- (Supplementary Document) · 2020-12-24 · Sign in to download
- (Supplementary Document) · 2020-12-23 · Sign in to download
- (Supplementary Document) · 2020-12-24 · Sign in to download
- (Supplementary Document) · 2020-12-24 · Sign in to download
- (Supplementary Document) · 2021-01-02 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-09-02 · Sign in to download
- DEMARCATION PLAN · 2020-09-02
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-09-02
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2020-09-02 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2020-09-02
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-09-02
- ZONING PLAN · 2020-09-02
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-09-02
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2020-09-02
- LETTER OF INTENT · 2020-09-02 · Sign in to download
- (Supplementary Document) · 2021-02-09 · Sign in to download
- (Supplementary Document) · 2021-07-15 · Sign in to download
- (Supplementary Document) · 2021-07-15 · Sign in to download
- (Supplementary Document) · 2021-07-15 · Sign in to download
- (Supplementary Document) · 2021-09-11 · Sign in to download
- COMPLETION CERTIFICATE · 2022-08-02 · Sign in to download