Overview
DAS ENCLAVE
SANKALP CONSTRUCTION · Patna
Units46
Booked25 of 46As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2025-11-30Proposed
Registered on2022-03-15
Valid to2025-11-30
Approvals5
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Disputes & cases | 2 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 2 unit types |
| Construction & progress | 4 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 33 documents · 22 source links |
Registration
Registration
| Promoter | SANKALP CONSTRUCTION | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00567-1/172/R-1294/2022 | |
| Registered on | 2022-03-15 | |
| Valid to | 2025-11-30 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2025-11-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance | 2026-06-21 | |
| Fire NOC | 2072-01-22 | BIHAR FIRE SERVICE AUTHORITY |
| Airport NOC | 2026-06-21 | |
| Water Supply Permission | 2026-06-21 | |
| Other approval | 2026-06-21 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status |
|---|---|---|---|
| RERA/C-CASE-118/2023 | RERA Bihar | ||
| RERA/CC/118/2023 | RERA Bihar | Complaint | Pending |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹15,47,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,087.97 | |
|---|---|---|
| Built-up (m²) | 5,238.03 | |
| FAR | 2.5 | |
| Towers | 1 | |
| Units | 46 | |
| Booked | 25 | |
| Booked as of | 2025-12-31 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 30 | DAS ENCLAVE |
| 2 BHK | 16 | DAS ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-12-31 | |
| Start | 2021-11-15 | |
| Proposed completion | 2025-11-30 |
Quarterly progress
| 2025-Q4 | 2026-01-15 | 100% | 25 |
| 2025-Q3 | 2025-10-15 | ||
| 2025-Q2 | 2025-10-15 | ||
| 2025-Q1 | 2025-04-14 | ||
| 2024-Q4 | 2025-01-13 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q2 | 2024-07-15 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2024-07-25 | ||
| 2022-Q4 | 2024-07-25 | ||
| 2022-Q3 | 2024-07-25 | ||
| 2022-Q2 | 2022-07-15 | ||
| 2022-Q1 | 2022-04-27 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SANKALP CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | CENTRAL BANK OF INDIA | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP306201800567-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP306201800567&ld=pan&pj=RERAP306201800567-1&f=2025-2026&q=3
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP306201800567-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-15
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-15
- Q1 (Apr - Jun) / 2025-2026 · 2025-10-15
- Q4-Jan to Mar / 2024-2025 · 2025-04-14
- Q3-Oct to Dec / 2024-2025 · 2025-01-13
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-07-15
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2024-07-25
- Q2-Jul to Sep / 2022-2023 · 2024-07-25
- Q1-Apr to Jun / 2022-2023 · 2022-07-15
- Q4-Jan to Mar / 2021-2022 · 2022-04-27
- Case proceeding RERA/C-CASE-118/2023 · Sign in to download
- Case proceeding RERA/CC/118/2023 · 2023-04-24 · Sign in to download
- Case proceeding RERA/CC/118/2023 · 2023-07-26 · Sign in to download
- Case proceeding RERA/CC/118/2023 · 2023-12-12 · Sign in to download
- Case proceeding RERA/CC/118/2023 · 2024-01-15 · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- RERA/C-CASE-118/2023 · Sign in to download
- RERA/CC/118/2023 · Sign in to download
- 2025-Q3 · 2025-10-15
- 2025-Q2 · 2025-10-15
- 2025-Q1 · 2025-04-14
- 2024-Q4 · 2025-01-13
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-07-15
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2024-07-25
- 2022-Q3 · 2024-07-25
- 2022-Q2 · 2022-07-15
- 2022-Q1 · 2022-04-27