Overview
DD SILICON VALLEY
DESAI HOMES · Kakkanad
Units146
Booked0 of 146
Construction progress15%
Completion2031-04-30Proposed
Registered on2026-06-16
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 22 unit types |
| Construction & progress | 3 progress details · 2 quarters |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 36 documents · 6 source links |
Registration
Registration
| Promoter | DESAI HOMES | |
|---|---|---|
| District | Ernakulam | |
| Locality | Kakkanad | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/ERN/093/2026 | |
| Registered on | 2026-06-16 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2031-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BA-308/2024 | 2023-04-05 | 2028-04-04 | Thrikkakra Municipaliity |
| Development Permit | BA-308/2014 | 2024-04-12 | 2028-04-11 | Thrikkkara Municipality |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,379.66 | |
|---|---|---|
| Built-up (m²) | 19,829.07 | |
| Towers | 0 | |
| Units | 146 | |
| Booked | 0 |
Unit types
| 2BHK | 18 | 0 | DD SILICON VALLEY |
| 2BHK | 18 | 0 | DD SILICON VALLEY |
| 2BHK | 1 | 0 | DD SILICON VALLEY |
| 2BHK | 1 | 0 | DD SILICON VALLEY |
| 2BHK | 1 | 0 | DD SILICON VALLEY |
| 2BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 11 | 0 | DD SILICON VALLEY |
| 3BHK | 11 | 0 | DD SILICON VALLEY |
| 3BHK | 22 | 0 | DD SILICON VALLEY |
| 3BHK | 11 | 0 | DD SILICON VALLEY |
| 3BHK | 33 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 2 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 1 | 0 | DD SILICON VALLEY |
| 3BHK | 2 | 0 | DD SILICON VALLEY |
| 4BHK | 6 | 0 | DD SILICON VALLEY |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 15% | |
|---|---|---|
| Start | 2026-02-25 | |
| Proposed completion | 2031-04-30 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DESAI HOMES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | The Federal Bank Ltd | |
| Other projects in this city pack | 8 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Jibu & Thomas Architects |
| Engineer | Geo Structurals P Ltd |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=kakkanad%2C+Ernakulam%2C+Kerala%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.kerala.gov.in/projects/12082
- https://rera.kerala.gov.in/projects?district=595&page=7
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=xqAaWDsjcfzIDUaUyqTMlrC%2BxeXnesBYnT%2Fli0efBjcSdsflBiPiWcnW8sFRfNiE012iLGnBxqeYBQItFGZ8NgcljI7Cob9ojQSRzUE6sP45%2B8X%2F6qdhM3wej5%2Fzlzi6B7x%2FjZQ5NpDY8qArBUanovwqujr%2FWQqwSNaxgDYf5CGDwh9e1GZ8yA%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=12082&Division=1&UserID=30171&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Signed project certificate · 2026-06-16
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-01-22
- Copy of Valid Building Permit · 2026-01-22
- Detailed technical specifications to be adopted in the project · 2026-02-17 · Sign in to download
- Layout approval plan · 2026-01-27
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2026-01-22 · Sign in to download
- Site Plan / Site Map · 2026-01-22
- Other · 2026-03-28 · Sign in to download
- Other · 2026-03-28 · Sign in to download
- Other · 2026-03-28 · Sign in to download
- Clearance from Airport Authority of India · 2026-01-22 · Sign in to download
- Clearance from Airport Authority of India · 2026-01-22 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2026-02-17 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2026-02-17 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2026-02-11
- Consent to establish (Clearance from Pollution Control Board) · 2026-01-22 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2026-03-03 · Sign in to download
- Environment Clearance · 2026-02-17 · Sign in to download
- Initial NOC from Fire and Rescue department · 2026-01-22
- List and details of common amenities · 2026-02-17 · Sign in to download
- Plan of firefighting to be executed in the proposed project · 2026-01-29
- Plan of firefighting to be executed in the proposed project · 2026-01-29
- Plan of firefighting to be executed in the proposed project · 2026-01-29
- Plan of firefighting to be executed in the proposed project · 2026-01-29
- Plan of firefighting to be executed in the proposed project · 2026-01-29
- Plan of firefighting to be executed in the proposed project · 2026-01-29
- Plan of Use of renewable energy to be executed in the proposed project · 2026-01-22