Overview
DEVENDRA ENCLAVE
SHRISTI HOMES PVT LTD · Patna
Units42
Completion2020-10-20Proposed
Registered on2018-12-11
Cases1
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 42 documents · 20 source links |
Registration
Registration
| Promoter | SHRISTI HOMES PVT LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00323-1/217/R-288/2018 | |
| Registered on | 2018-12-11 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2020-10-20 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status |
|---|---|---|---|
| RERA/CC/315/2024 | RERA Bihar | Complaint | Pending |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹97,50,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,454.6 | |
|---|---|---|
| Built-up (m²) | 3,631.34 | |
| FAR | 2.5 | |
| Towers | 0 | |
| Units | 42 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 18 | DEVENDRA ENCLAVE |
| 3 BHK | 24 | DEVENDRA ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-05-10 | |
|---|---|---|
| Proposed completion | 2020-10-20 |
Quarterly progress
| 2022-Q3 | 2023-01-15 |
| 2022-Q2 | 2023-01-15 |
| 2022-Q1 | 2023-01-15 |
| 2021-Q4 | 2022-02-22 |
| 2021-Q3 | 2022-02-22 |
| 2021-Q2 | 2022-02-22 |
| 2021-Q1 | 2022-02-22 |
| 2020-Q4 | 2022-02-22 |
| 2020-Q3 | 2022-02-22 |
| 2020-Q2 | 2022-02-22 |
| 2020-Q1 | 2022-02-22 |
| 2019-Q4 | 2022-02-22 |
| 2019-Q3 | 2022-02-22 |
| 2019-Q2 | 2022-02-22 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHRISTI HOMES PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF INDIA | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP294201800323-1
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP294201800323-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Registration certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Q2-Jul to Sep / 2022-2023 · 2023-01-15
- Q1-Apr to Jun / 2022-2023 · 2023-01-15
- Q4-Jan to Mar / 2021-2022 · 2023-01-15
- Q3-Oct to Dec / 2021-2022 · 2022-02-22
- Q2-Jul to Sep / 2021-2022 · 2022-02-22
- Q1-Apr to Jun / 2021-2022 · 2022-02-22
- Q4-Jan to Mar / 2020-2021 · 2022-02-22
- Q3-Oct to Dec / 2020-2021 · 2022-02-22
- Q2-Jul to Sep / 2020-2021 · 2022-02-22
- Q1-Apr to Jun / 2020-2021 · 2022-02-22
- Q4-Jan to Mar / 2019-2020 · 2022-02-22
- Q3-Oct to Dec / 2019-2020 · 2022-02-22
- Q2-Jul to Sep / 2019-2020 · 2022-02-22
- Q1-Apr to Jun / 2019-2020 · 2022-02-22
- Case proceeding RERA/CC/315/2024 · 2024-08-21 · Sign in to download
- Other · 2026-07-22 · Sign in to download
- Other · 2026-07-13 · Sign in to download
- Other · 2026-06-24 · Sign in to download
- Other · 2026-06-18 · Sign in to download
- Other · 2026-05-19 · Sign in to download
- Other · 2026-03-12 · Sign in to download
- Other · 2026-02-06 · Sign in to download
- Other · 2026-01-05 · Sign in to download
- Other · 2025-11-26 · Sign in to download
- Other · 2025-11-05 · Sign in to download
- Other · 2025-09-26 · Sign in to download
- Other · 2025-08-29 · Sign in to download
- Other · 2025-08-07 · Sign in to download
- Other · 2024-09-03 · Sign in to download
- RERA/CC/315/2024 · Sign in to download
- 2022-Q3 · 2023-01-15
- 2022-Q2 · 2023-01-15
- 2022-Q1 · 2023-01-15
- 2021-Q4 · 2022-02-22
- 2021-Q3 · 2022-02-22
- 2021-Q2 · 2022-02-22
- 2021-Q1 · 2022-02-22
- 2020-Q4 · 2022-02-22
- 2020-Q3 · 2022-02-22
- 2020-Q2 · 2022-02-22
- 2020-Q1 · 2022-02-22
- 2019-Q4 · 2022-02-22
- 2019-Q3 · 2022-02-22
- 2019-Q2 · 2022-02-22