Overview
DHB PRIME
DREAM HOUSE BUILDESTATE PRIVATE LIMITED · Jaipur
Units86
Booked48 of 86As of 2024-12-31
Completion2025-06-30Revised · Proposed 2024-01-03
Registered on2024-01-12
Valid to2025-06-30
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 44 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 65 documents · 7 source links |
Registration
Registration
| Promoter | DREAM HOUSE BUILDESTATE PRIVATE LIMITED | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2024/2918 | |
| Registered on | 2024-01-12 | |
| Valid to | 2025-06-30 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2024-01-03 | |
| Revised completion | 2025-06-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,72,00,300 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹9,22,00,300 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2024-Q4 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 13,700 | |
|---|---|---|
| Built-up (m²) | 6,603.95 | |
| Towers | 86 | |
| Units | 86 | |
| Booked | 48 | |
| Booked as of | 2024-12-31 |
Unit types
| 76 | 1 | 0 |
| 78 | 1 | 0 |
| 53 | 1 | 0 |
| 75 | 1 | 0 |
| 19 | 1 | 0 |
| 20 | 1 | 0 |
| 21 | 1 | 0 |
| 22 | 1 | 0 |
| 30-39, 42-51, 54-64 | 31 | 0 |
| 23 | 1 | 0 |
| 52 | 1 | 0 |
| 24 | 1 | 0 |
| 25 | 1 | 0 |
| 27 | 1 | 0 |
| 26 | 1 | 0 |
| 29 | 1 | 0 |
| 28 | 1 | 0 |
| 74 | 1 | 0 |
| 77 | 1 | 0 |
| 73 | 1 | 0 |
| 11 | 1 | 0 |
| 6-9, 11 | 5 | 0 |
| 12,15 | 2 | 0 |
| 13 | 1 | 0 |
| 14 | 1 | 0 |
| 72 | 1 | 0 |
| 71 | 1 | 0 |
| 40 | 1 | 0 |
| 18 | 1 | 0 |
| 70 | 1 | 0 |
| 10 | 1 | 0 |
| 69 | 1 | 0 |
| 66 | 1 | 0 |
| 68 | 1 | 0 |
| 65 | 1 | 0 |
| 41 | 1 | 0 |
| 3 | 1 | 0 |
| 2 | 1 | 0 |
| 5 | 1 | 0 |
| 17 | 1 | 0 |
| 67 | 1 | 0 |
| 1 | 1 | 0 |
| 4 | 1 | 0 |
| S1-S8 | 8 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-01-03 | |
|---|---|---|
| Proposed completion | 2024-01-03 | |
| Revised completion | 2025-06-30 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2024-Q4 | 2025-01-30 | 48 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DREAM HOUSE BUILDESTATE PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LTD. | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://gisprod.rajasthan.gov.in/dynamicquery/rest/services/Rera/Rera/FeatureServer/0/query?objectIds=1001%2C1002%2C1003%2C1004%2C1005%2C1006%2C1007%2C1008%2C1009%2C1010%2C1011%2C1012%2C1013%2C1014%2C1015%2C1016%2C1017%2C1018%2C1019%2C1020%2C1021%2C1022%2C1023%2C1024%2C1025%2C1026%2C1027%2C1028%2C1029%2C1030%2C1031%2C1032%2C1033%2C1034%2C1035%2C1036%2C1037%2C1038%2C1039%2C1040%2C1041%2C1042%2C1043%2C1044%2C1045%2C1046%2C1047%2C1048%2C1049%2C1050%2C1051%2C1052%2C1053%2C1054%2C1055%2C1056%2C1057%2C1058%2C1059%2C1060%2C1061%2C1062%2C1063%2C1064%2C1065%2C1066%2C1067%2C1068%2C1069%2C1070%2C1071%2C1072%2C1073%2C1074%2C1075%2C1076%2C1077%2C1078%2C1079%2C1080%2C1081%2C1082%2C1083%2C1084%2C1085%2C1086%2C1087%2C1088%2C1089%2C1090%2C1091%2C1092%2C1093%2C1094%2C1095%2C1096%2C1097%2C1098%2C1099%2C1100%2C1101%2C1102%2C1103%2C1104%2C1105%2C1106%2C1107%2C1108%2C1109%2C1110%2C1111%2C1112%2C1113%2C1114%2C1115%2C1116%2C1117%2C1118%2C1119%2C1120%2C1121%2C1122%2C1123%2C1124%2C1125%2C1126%2C1127%2C1128%2C1129%2C1130%2C1131%2C1132%2C1133%2C1134%2C1135%2C1136%2C1137%2C1138%2C1139%2C1140%2C1141%2C1142%2C1143%2C1144%2C1145%2C1146%2C1147%2C1148%2C1149%2C1150%2C1151%2C1152%2C1153%2C1154%2C1155%2C1156%2C1157%2C1158%2C1159%2C1160%2C1161%2C1162%2C1163%2C1164%2C1165%2C1166%2C1167%2C1168%2C1169%2C1170%2C1171%2C1172%2C1173%2C1174%2C1175%2C1176%2C1177%2C1178%2C1179%2C1180%2C1181%2C1182%2C1183%2C1184%2C1185%2C1186%2C1187%2C1188%2C1189%2C1190%2C1191%2C1192%2C1193%2C1194%2C1195%2C1196%2C1197%2C1198%2C1199%2C1200%2C1201%2C1202%2C1203%2C1204%2C1205%2C1206%2C1207%2C1208%2C1209%2C1210%2C1211%2C1212%2C1213%2C1214%2C1215%2C1216%2C1217%2C1218%2C1219%2C1220%2C1221%2C1222%2C1223%2C1224%2C1225%2C1226%2C1227%2C1228%2C1229%2C1230%2C1231%2C1232%2C1233%2C1234%2C1235%2C1236%2C1237%2C1238%2C1239%2C1240%2C1241%2C1242%2C1243%2C1244%2C1245%2C1246%2C1247%2C1248%2C1249%2C1250&outFields=OBJECTID%2CPROJECT_ID%2CPROJECT_NAME%2CNAME_OF_THE_PROMOTER%2CCATEGORY_NAME%2CPROJECT_SUBTYPE%2CDISTRICT%2CTEHSIL%2CTOTAL_BUILDING_COUNT%2CTOTAL_NO_OF_FLOORS%2CPHASE_AREA%2CCREATED_DATE%2CLAST_EDITED_DATE%2CAPPLICATION_NO%2CREGISTRATION_NO%2CPINCODE&returnGeometry=true&outSR=4326&f=json
- https://rera.rajasthan.gov.in/ProjectDetail?id=DOW4uxTWmh4b89bZ05hZhw
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/DOW4uxTWmh4b89bZ05hZhw
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=DOW4uxTWmh4b89bZ05hZhw%3D%3D&QuarterIdEnc=fJ0qjqph7wECoDCiZzFW1g%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=oqAHCaHDg5Q%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- SitePlanPath · 2024-01-05
- Site_Plan_Doc_Sanctioned
- RCertificate
- MCAdata · Sign in to download
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2024-10-28 · Sign in to download
- R2_UploadDoc · 2024-10-28 · Sign in to download
- R3_UploadedPath · 2024-10-28 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download