Building plan (Local Planning Authority)Sanctioned 28 Jul 2022No. STRRPA/TPCC/12/22-23
RERA extensionsNone on the filingFiling read 31 Oct 2026
Land conversionConverted, 9 of 9 parcelsDates and authorities below
Permits
Approval letters
Building plan (Local Planning Authority)
Sanctioned 28 Jul 2022 · No. STRRPA/TPCC/12/22-23
Power NOC
Filed with the registration
Fire department
Disputes & cases
Are there court cases or buyer complaints on this project?
Locked
Cases on the land
Cases on the builder
RERA complaints
Builder's other projects
Filed onCase no.Filed atWhat it's aboutStatus
₹ ••,•••
•• %
•• ••• ••••
Contract & costs
What does a buyer commit to?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Payments
Agreement for sale
Late-payment interest
SBI MCLR + 2%
Interest the builder pays on late possession
SBI MCLR + 2%
Not verified yet: Forfeiture, agreement; Forfeiture, allotment letter; Transfer fee; Maintenance included; Agreement and allotment letter; Payment plan; Due on signing; Due within 15 days; Each construction stage; Floors in payment plan; Agreement for sale.
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
This project
Unit sizes
Unit mix filed
3 BHK + Media Room · avg 216 m²
Location & risks
What is the location like?
Groundwater, taluk average21.3 m below groundAnekal taluk, July 2023
Water supply, as filedBorewell, Local authority (Gramapanchayathi Karyalaya Mugaluru)Declared by the promoter
Metro, operationalabout 13.5 kmBommasandra
Construction & progress
How is it being built, and when will it be ready?
Review1 to review · 1 clear
Completion100%As of Q2 2026-27, promoter's return
StructureRCC framed structureAs specified
Progress
Completion, as the promoter reported it
Developer
Can the developer deliver?
Clear1 clear
Sold85 / 137As of Q2 2026-27
Sold in Q2 2026-273✓ClearClear
Funding
Estimated cost
Loan & collateral
Can it be financed?
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Conditions
Collateral checks
Developer's project loan
No borrowing declared
Building plan
Sanctioned 28 Jul 2022
Escrow bank
HDFC · RICHMOND ROAD
Stage
Progress as reported, by quarter
Data room
Documents filed for this project
Locked
194 documents filed with K-RERA for this project
DocumentFolderPagesFiled
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Unlock this full report
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Unlock this full report₹99 for this report · opens Title & ownership, Disputes & cases and DocumentsUnlock
Survey plots · KGIS cadastral
Imagery: Esri, Vantor, Earthstar Geographics
Satellite map with the 4 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 4 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Divine Meadows in the interactive atlas
•• ••• ••••
Title
Title report
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Not verified yet
Survey sketch
Survey sketch filed with K-RERA
Not verified yet
Sketch, sanction and mutation vs KGIS map
₹ ••,•••
•• %
•• ••• ••••
•••••
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
Not verified yet
Unlock this full report
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Not verified yet: Recent price, super built-up; Recent price, carpet; Phase 1 → Phase 2; Gross yield, per sq ft; Price per sq ft, super built-up; Form 4 certified totals; Agreements in the Form 4 sold list; Carpet vs rest, by type; Transactions in this project; East Bengaluru, past year; Bengaluru, past year; East Bengaluru since 2022; This project vs East Bengaluru; By quarter; Registered sale price per sq ft, by year; Transactions around this project; Carpet price, projects within 4 km; Filed prices nearby; Median rent, 3 km; Rents and yields.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Storm drain, primary
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Electricity · Pathways Canopied with Trees · Outdoor Gym · Multi-Purpose Lawn · Seating Area with Pavilion · Play Area for kids · Water Features · Event Lawn
Electricity, built
0%
Outdoor Sports facility, built
0%
Half Basketball Court, built
0%
Pedestrian Walkways, built
0%
Amphitheater, built
0%
Butterfly Garden, built
0%
Elders Corner, built
0%
Landscaped Greenery, built
0%
Jogging Tracks, built
0%
Covered parking per unit
1.99 (272 covered spaces for 137 units)
Power backup
Not declared
Around it
Water
Groundwater, Anekal taluk average
Not verified yet: Nearest high-tension line, Kitchen handover, Sewage plant, Nearest city water main, Ground level.
As the promoter reported it
Site photos filed with K-RERA, Q2 2026-27
Work left
By component, Q2 2026-27
Quarterly return, Q2 2026-27
Main structure
100% · planned by 27 Feb 2025
Electrical and plumbing finishing
100% · planned by 17 Jun 2025
Completion
100%
Dates
Dates
Filed dates
Schedule end
17 Oct 2025
RERA completion date
15 Aug 2026
!Review
Completion date, agreement
15 Aug 2026
Work began, as filed
1 Oct 2022
Specified structure
What the promoter specified · not an inspection
Structure
RCC framed structure
Building heights, fire NOC
9.9 m filed
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Not verified yet: Possession, agreement; Structural safety certificate; Internal roads; Club house; Completion, accountant; Foundation; Wall material; Wall thickness; Concrete / steel grade; Windows; Flooring; Toilet tiles, spec vs brochure; Wiring; Sanctioned load per villa; Sewage plant; Design consultants (Form 6); Fire safety; Environmental clearance.
Land · ₹16.74 Cr 11.6%Development · ₹127.38 Cr 88.4%
Form 4
Estimated cost, at registration
₹144.11 Cr
Estimated cost, engineer's certificate
₹123.75 Cr
Sales
Sold vs unsold, Q2 2026-27
Sold (85) 62%Unsold (52) 38%
Sold per quarter
K-RERA inventory
Sold, Q3 2025-26
79 / 137 · 58 available
Sold, Q4 2025-26
80 / 137 · 57 available
Sold, Q1 2026-27
82 / 137 · 55 available
Sold, Q2 2026-27
85 / 137 · 52 available
Unsold, Q2 2026-27
52
Sold in Q4 2025-26
1
Sold in Q1 2026-27
2
Sold in Q2 2026-27
3
Compliance
Escrow, Q2 2026-27
Escrow and filings
Escrow bank
HDFC · RICHMOND ROAD
Designated account, collected
₹12.93 Cr in Q2 2026-27
Designated account, withdrawn
₹9.79 Cr in Q2 2026-27 (76% of that quarter's deposits)
Share of collections deposited in escrow
75.69%
Share of collections the promoter declared for escrow
70%
Not verified yet: Receivable, sold villas; Cost left; Cost left vs buyer dues; Cost incurred; Collected from buyers; Land cost revision; Unregistered agreements, over 10% paid; Average schedule slip; DOSL builder track.
Site photos, Q2 2026-27
Not verified yet: Value; Max loan; Borrower margin; Example unit; Calculation; Records searched to; Unregistered agreements, over 10% paid; Sale deed in favour of.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220, 110 and 66 kV
Its corridor, to scale
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, primary
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Anekal taluk average, July 2023: 21.3 m below ground
What it means
20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class
Through the year
January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several)
Water supply, as filed
Borewell, Local authority (Gramapanchayathi Karyalaya Mugaluru)
Distances
Within 3 km of the filed pin
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220, 110 and 66 kV
Its corridor, to scale
Approximate location: the filed pin, good to the neighbourhood, not the plot