DOWNTOWN ARCADE
BEYOND CONSTRUCTIONS · Krishna
Units15
Completion2026-05-03Proposed
Registered on2023-08-14
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 15 unit types |
| Construction & progress | 2 progress details · 2 quarters |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 24 documents · 9 source links |
Registration
Registration
| Promoter | BEYOND CONSTRUCTIONS | |
|---|---|---|
| District | Krishna | |
| Regulator | AP RERA | |
| Registration number | P06160073895 | |
| Registered on | 2023-08-14 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2026-05-03 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1168/0561/B/VJA/GLPD/2023 | 2023-05-03 | Commissioner,APCRDA |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,03,45,000 | |
|---|---|---|
| Construction | ₹4,00,73,000 | |
| Total | ₹6,04,18,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 747.61 | |
|---|---|---|
| Built-up (m²) | 2,066.34 | |
| Towers | 1 | |
| Units | 15 |
Unit types
| 3BHK | 88.94 | 1 | A BLOCK | FIRST FLOOR |
| 2BHK | 70.59 | 1 | A BLOCK | FIRST FLOOR |
| 3BHK | 81.21 | 1 | A BLOCK | FIRST FLOOR |
| 3BHK | 88.94 | 1 | A BLOCK | FOURTH FLOOR |
| 2BHK | 70.59 | 1 | A BLOCK | FOURTH FLOOR |
| 3BHK | 81.21 | 1 | A BLOCK | FOURTH FLOOR |
| 3BHK | 88.94 | 1 | A BLOCK | GROUND FLOOR |
| 2BHK | 70.59 | 1 | A BLOCK | GROUND FLOOR |
| 3BHK | 81.21 | 1 | A BLOCK | GROUND FLOOR |
| 3BHK | 88.94 | 1 | A BLOCK | SECOND FLOOR |
| 2BHK | 70.59 | 1 | A BLOCK | SECOND FLOOR |
| 3BHK | 81.21 | 1 | A BLOCK | SECOND FLOOR |
| 3BHK | 88.94 | 1 | A BLOCK | THIRD FLOOR |
| 2BHK | 70.59 | 1 | A BLOCK | THIRD FLOOR |
| 3BHK | 81.21 | 1 | A BLOCK | THIRD FLOOR |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-05-03 | |
|---|---|---|
| Proposed completion | 2026-05-03 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2023-Q3 | 2023-10-21 |
| 2023-Q4 | 2024-01-22 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BEYOND CONSTRUCTIONS | |
|---|---|---|
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFSeNJh4bBGMcGRLYh3yTt2UIPSmIemkRO0mrd0AxOj9gNzPsLY+tSNh6P5VhbKNI6mECgZGFCmrwjsJ0TLhwOa76b04tOIMQ9s7SG48cWGyq
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE