Overview
DPR COMPLEX
SURJ HOMES · Patna
Units53
Booked16 of 53As of 2026-03-31
Construction progress85%As of 2026-03-31
Completion2022-05-31Proposed
Registered on2019-08-28
Valid to2022-05-31
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 1 unit type |
| Construction & progress | 4 progress details · 26 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 38 documents · 30 source links |
Registration
Registration
| Promoter | SURJ HOMES | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00900-3/965/R-747/2019 | |
| Registered on | 2019-08-28 | |
| Valid to | 2022-05-31 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2022-05-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| Fire NOC | Office of the State Fire Officer-cum Director, Bihar,patna |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,10,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,366.76 | |
|---|---|---|
| Built-up (m²) | 5,872.29 | |
| FAR | 2.49 | |
| Towers | 2 | |
| Units | 53 | |
| Booked | 16 | |
| Booked as of | 2026-03-31 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 53 | DPR COMPLEX |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 85% | |
|---|---|---|
| As of | 2026-03-31 | |
| Start | 2019-05-16 | |
| Proposed completion | 2022-05-31 |
Quarterly progress
| 2026-Q1 | 2026-04-26 | 85% | 16 |
| 2025-Q4 | 2026-01-18 | ||
| 2025-Q3 | 2025-10-15 | ||
| 2025-Q2 | 2025-08-08 | ||
| 2025-Q1 | 2025-04-13 | ||
| 2024-Q4 | 2025-01-14 | ||
| 2024-Q3 | 2024-10-14 | ||
| 2024-Q2 | 2024-07-13 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-21 | ||
| 2022-Q4 | 2023-03-30 | ||
| 2022-Q3 | 2023-03-30 | ||
| 2022-Q2 | 2022-07-14 | ||
| 2022-Q1 | 2022-04-15 | ||
| 2021-Q4 | 2022-03-16 | ||
| 2021-Q3 | 2022-03-16 | ||
| 2021-Q2 | 2022-03-16 | ||
| 2021-Q1 | 2022-03-14 | ||
| 2020-Q4 | 2022-03-14 | ||
| 2020-Q3 | 2022-03-14 | ||
| 2020-Q2 | 2022-03-14 | ||
| 2020-Q1 | 2022-03-14 | ||
| 2019-Q4 | 2022-03-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SURJ HOMES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP249201800900-3
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP249201800900&ld=pan&pj=RERAP249201800900-3&f=2025-2026&q=4
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP249201800900-3
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Registration certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Area Development Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-26
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-18
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-15
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-08
- Q4-Jan to Mar / 2024-2025 · 2025-04-13
- Q3-Oct to Dec / 2024-2025 · 2025-01-14
- Q2-Jul to Sep / 2024-2025 · 2024-10-14
- Q1-Apr to Jun / 2024-2025 · 2024-07-13
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-21
- Q3-Oct to Dec / 2022-2023 · 2023-03-30
- Q2-Jul to Sep / 2022-2023 · 2023-03-30
- Q1-Apr to Jun / 2022-2023 · 2022-07-14
- Q4-Jan to Mar / 2021-2022 · 2022-04-15
- Q3-Oct to Dec / 2021-2022 · 2022-03-16
- Q2-Jul to Sep / 2021-2022 · 2022-03-16
- Q1-Apr to Jun / 2021-2022 · 2022-03-16
- Q4-Jan to Mar / 2020-2021 · 2022-03-14
- Q3-Oct to Dec / 2020-2021 · 2022-03-14
- Q2-Jul to Sep / 2020-2021 · 2022-03-14
- Q1-Apr to Jun / 2020-2021 · 2022-03-14
- Q4-Jan to Mar / 2019-2020 · 2022-03-14
- Q3-Oct to Dec / 2019-2020 · 2022-03-14
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- 2025-Q4 · 2026-01-18
- 2025-Q3 · 2025-10-15
- 2025-Q2 · 2025-08-08
- 2025-Q1 · 2025-04-13
- 2024-Q4 · 2025-01-14
- 2024-Q3 · 2024-10-14
- 2024-Q2 · 2024-07-13
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-21
- 2022-Q4 · 2023-03-30
- 2022-Q3 · 2023-03-30
- 2022-Q2 · 2022-07-14
- 2022-Q1 · 2022-04-15
- 2021-Q4 · 2022-03-16
- 2021-Q3 · 2022-03-16
- 2021-Q2 · 2022-03-16
- 2021-Q1 · 2022-03-14
- 2020-Q4 · 2022-03-14
- 2020-Q3 · 2022-03-14
- 2020-Q2 · 2022-03-14
- 2020-Q1 · 2022-03-14
- 2019-Q4 · 2022-03-14