DOSLChhattisgarh Workspace

Overview

DREAM HOMES

DREAM GROUP · RAIPUR
Units83
Booked75 of 83As of 2025-09-30
Construction progress100%As of 2025-09-30
Completion2026-03-30Revised · Proposed 2024-06-30
Registered on2019-06-19
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 26 quarters
Technical report
Site & area3 site details · 105 unit types
Construction & progress4 progress details · 26 quarters
Developer & finance
Developer3 developer details
The evidence
Sources146 documents · 6 source links

Registration

Registration

PromoterDREAM GROUP
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA190619000991
Registered on2019-06-19
Project typeGroup Housing
Status (as filed)New
Proposed completion2024-06-30
Revised completion2026-03-30