Overview
DWARIKAPURI
MAA KARMA DEVELOPERS · DURG
Construction progress100%As of 2022-06-30
Completion2024-09-15Revised · Proposed 2023-12-15
Registered on2018-06-05
Approvals5
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 16 quarters |
| Technical report | |
| Site & area | 5 unit types |
| Construction & progress | 4 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 73 documents · 11 source links |
Registration
Registration
| Promoter | MAA KARMA DEVELOPERS | |
|---|---|---|
| District | DURG | |
| Regulator | CG RERA | |
| Registration number | PCGRERA050618000038 | |
| Registered on | 2018-06-05 | |
| Project type | Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2023-12-15 | |
| Revised completion | 2024-09-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| M-COM-2021-01565 | CG RERA | Complaint | Disposed | 2023-05-12 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹8,00,00,000 | |
|---|---|---|
| Construction | ₹22,50,00,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹0 |
| 2020-Q1 | ₹0 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹0 |
| 2021-Q4 | ₹0 |
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹29,86,710 |
Site & area
What does the land measure?
Site & area
Unit types
| 3BHK | 107.17 | 24 | 20 |
| 2BHK | 76.79 | 36 | 15 |
| 2BK | 52.21 | 24 | 0 |
| 3BHK | 127.4 | 65 | 45 |
| 1BHK | 41.7 | 17 | 7 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2022-06-30 | |
| Proposed completion | 2023-12-15 | |
| Revised completion | 2024-09-15 |
Quarterly progress
| 2018-Q3 | 40% |
| 2018-Q4 | 41% |
| 2019-Q1 | 45% |
| 2019-Q2 | 46% |
| 2019-Q3 | 48% |
| 2019-Q4 | 48% |
| 2020-Q1 | 53% |
| 2020-Q2 | 77% |
| 2020-Q3 | 78% |
| 2020-Q4 | 81% |
| 2021-Q1 | 91% |
| 2021-Q2 | 91% |
| 2021-Q3 | 91% |
| 2021-Q4 | 98% |
| 2022-Q1 | 90% |
| 2022-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MAA KARMA DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Canara Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTA2
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Modified Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Agent Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Final order · 2023-05-12 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Development Permission from competent authorities
- M-COM-2021-01565 · Sign in to download