Overview
Eastwood Village
Eastwood Infra Pvt Ltd · Kapurthala
Units182
Completion2025-12-31Proposed
Valid to2026-12-31
Approvals19
Sections
| Property title & search report | |
|---|---|
| Approvals | 19 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 182 unit types |
| Construction & progress | 2 progress details · 21 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 51 documents · 44 source links |
Registration
Registration
| Promoter | Eastwood Infra Pvt Ltd | |
|---|---|---|
| District | Kapurthala | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-KPT40-PC0154 | |
| Valid to | 2026-12-31 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2025-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Permissions (Received) | 2025-05-27 |
| CLU Certificate | ||
| CLU Certificate | ||
| Electric Substation NOC | Permissions (Received) | 2022-05-10 |
| Electric Substation NOC | Permissions (Applied) | 2025-04-14 |
| Environment Clearance certificate/ NOC | Permissions (Received) | 2022-04-25 |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2020-10-08 |
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2023-08-23 |
| NOC from NHAI/ PWD | Permissions (Received) | 2023-02-09 |
| Other Document (All NOCs of Project) | 2021-06-04 | |
| Other Document (NOC from BDPO Department) | Permissions (Received) | 2023-08-28 |
| Other Document (NOC from Drainage Department) | Permissions (Received) | 2023-08-25 |
| Other Document (NOC from Forest Department) | Permissions (Received) | 2023-08-08 |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Applied) | 2025-04-17 |
| Pollution Clearance from Punjab Pollution Control Board | 2021-02-17 | |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Received) | 2025-06-18 |
| Pollution Clearance from Punjab Pollution Control Board | Permissions (Received) | 2025-06-18 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹26,04,50,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 40,442.93 | |
|---|---|---|
| Towers | 3 | |
| Maximum floors | 5 | |
| Units | 182 |
Unit types
| SHOP No.A1 | 277.89 | 1 | PHASE-I |
| SHOP No.A2 | 97.72 | 1 | PHASE-I |
| SHOP No.A3 | 97.72 | 1 | PHASE-I |
| SHOP No.A4 | 97.72 | 1 | PHASE-I |
| SHOP NO.A5 | 97.72 | 1 | PHASE-I |
| SHOP No.A6 | 71.66 | 1 | PHASE-I |
| SHOP No.A7 | 71.66 | 1 | PHASE-I |
| SHOP No.A8 | 71.66 | 1 | PHASE-I |
| SHOP No.A9 | 71.66 | 1 | PHASE-I |
| SHOP No.A10 | 71.66 | 1 | PHASE-I |
| SHOP No.A11 | 71.66 | 1 | PHASE-I |
| SHOP No.A12 | 71.66 | 1 | PHASE-I |
| SHOP No.A13 | 84.31 | 1 | PHASE-I |
| SHOP No.A14 | 84.31 | 1 | PHASE-I |
| SHOP No.A15 | 84.31 | 1 | PHASE-I |
| SHOP No.A16 | 84.31 | 1 | PHASE-I |
| SHOP No.A17 | 80.27 | 1 | PHASE-I |
| SHOP No.A18 | 80.27 | 1 | PHASE-I |
| SHOP No.A19 | 62.58 | 1 | PHASE-I |
| SHOP No.A20 | 62.58 | 1 | PHASE-I |
| SHOP No.A21 | 62.58 | 1 | PHASE-I |
| SHOP No.A22 | 60.46 | 1 | PHASE-I |
| SHOP No.A23 | 679.23 | 1 | PHASE-I |
| SHOP No.A24 | 60.46 | 1 | PHASE-I |
| SHOP No.A25 | 62.58 | 1 | PHASE-I |
| SHOP No.A26 | 62.58 | 1 | PHASE-I |
| SHOP No.A27 | 62.58 | 1 | PHASE-I |
| SHOP No.A28 | 80.27 | 1 | PHASE-I |
| SHOP No.A29 | 80.27 | 1 | PHASE-I |
| SHOP No.A30 | 32.05 | 1 | PHASE-I |
| SHOP No.A31 | 89.15 | 1 | PHASE-I |
| SHOP No.A32 | 84.31 | 1 | PHASE-I |
| SHOP No.A33 | 84.31 | 1 | PHASE-I |
| SHOP No.A34 | 84.31 | 1 | PHASE-I |
| SHOP No.A35 | 84.31 | 1 | PHASE-I |
| SHOP No.A36 | 84.31 | 1 | PHASE-I |
| SHOP No.A37 | 84.31 | 1 | PHASE-I |
| SHOP No.A38 | 84.31 | 1 | PHASE-I |
| SHOP No.A39 | 84.31 | 1 | PHASE-I |
| SHOP No.A40 | 84.31 | 1 | PHASE-I |
| SHOP No.A41 | 151.76 | 1 | PHASE-I |
| SHOP NO.A42 | 193.7 | 1 | PHASE-I |
| SHOP NO.A43 | 394.29 | 1 | PHASE-I |
| SHOP No.A44 | 162.67 | 1 | PHASE-I |
| SHOP No.A45 | 85.09 | 1 | PHASE-I |
| SHOP No.A46 | 85.09 | 1 | PHASE-I |
| SHOP No.A47 | 85.09 | 1 | PHASE-I |
| SHOP No.A48 | 59.03 | 1 | PHASE-I |
| SHOP No.A49 | 59.03 | 1 | PHASE-I |
| SHOP No.A50 | 59.03 | 1 | PHASE-I |
| SHOP No.A51 | 59.03 | 1 | PHASE-I |
| SHOP No.A52 | 57.84 | 1 | PHASE-I |
| SHOP No.A53 | 57.84 | 1 | PHASE-I |
| SHOP No.A54 | 57.84 | 1 | PHASE-I |
| SHOP No.A55 | 69.44 | 1 | PHASE-I |
| SHOP No.A56 | 69.44 | 1 | PHASE-I |
| SHOP No.A57 | 69.44 | 1 | PHASE-I |
| SHOP No.A58 | 69.44 | 1 | PHASE-I |
| SHOP No.A59 | 55.04 | 1 | PHASE-I |
| SHOP No.A60 | 45.09 | 1 | PHASE-I |
| SHOP No.A61 | 41.43 | 1 | PHASE-I |
| SHOP No.A62 | 51.98 | 1 | PHASE-I |
| SHOP No.A63 | 62 | 1 | PHASE-I |
| SHOP No.A64 | 62.01 | 1 | PHASE-I |
| SHOP No.A65 | 49.95 | 1 | PHASE-I |
| SHOP No.A66 | 49.95 | 1 | PHASE-I |
| SHOP No.A67 | 49.95 | 1 | PHASE-I |
| SHOP No.A68 | 47.82 | 1 | PHASE-I |
| SHOP No.A69 | 46.79 | 1 | PHASE-I |
| SHOP No.A70 | 46.79 | 1 | PHASE-I |
| SHOP No.A71 | 374.69 | 1 | PHASE-I |
| SHOP No.A72 | 46.79 | 1 | PHASE-I |
| SHOP No.A73 | 46.79 | 1 | PHASE-I |
| SHOP No.A74 | 47.82 | 1 | PHASE-I |
| SHOP No.A75 | 49.95 | 1 | PHASE-I |
| SHOP No.A76 | 49.95 | 1 | PHASE-I |
| SHOP No.A77 | 49.95 | 1 | PHASE-I |
| SHOP No.A78 | 62.01 | 1 | PHASE-I |
| SHOP No.A79 | 62.01 | 1 | PHASE-I |
| SHOP No.A80 | 51.99 | 1 | PHASE-I |
| SHOP No.A81 | 41.15 | 1 | PHASE-I |
| SHOP No.A82 | 45.09 | 1 | PHASE-I |
| SHOP No.A83 | 55.12 | 1 | PHASE-I |
| SHOP No.A84 | 35.3 | 1 | PHASE-I |
| SHOP No.A85 | 72.66 | 1 | PHASE-I |
| SHOP No.A86 | 67.82 | 1 | PHASE-I |
| SHOP No.A87 | 69.44 | 1 | PHASE-I |
| SHOP No.A88 | 69.44 | 1 | PHASE-I |
| SHOP No.A89 | 69.44 | 1 | PHASE-I |
| SHOP No.A90 | 69.44 | 1 | PHASE-I |
| SHOP No.A91 | 69.44 | 1 | PHASE-I |
| SHOP No.A92 | 69.44 | 1 | PHASE-I |
| SHOP No.A93 | 69.44 | 1 | PHASE-I |
| SHOP No.A94 | 69.44 | 1 | PHASE-I |
| SHOP No.A95 | 431.12 | 1 | PHASE-I |
| Shop No.B1 | 102.33 | 1 | PHASE-II BLOCK-A |
| Shop No.B2 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B3 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B4 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B5 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B6 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop NO.B7 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B8 | 837.49 | 1 | PHASE-II BLOCK-A |
| Shop No.B9 | 39.48 | 1 | PHASE-II BLOCK-A |
| Shop No.B10 | 39.48 | 1 | PHASE-II BLOCK-A |
| Shop No.B11 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B12 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B13 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B14 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B15 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B16 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B17 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B18 | 82.55 | 1 | PHASE-II BLOCK-A |
| Shop No.B19 | 54.26 | 1 | PHASE-II BLOCK-A |
| Shop No.B20 | 54.26 | 1 | PHASE-II BLOCK-A |
| Shop No.B21 | 82.55 | 1 | PHASE-II BLOCK-A |
| Shop No.B22 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B23 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B24 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B25 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B26 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B27 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B28 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B29 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B30 | 71.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B31 | 80.68 | 1 | PHASE-II BLOCK-A |
| Shop No.B32 | 69.89 | 1 | PHASE-II BLOCK-A |
| Shop NO.B33 | 69.89 | 1 | PHASE-II BLOCK-A |
| Shop No.B34 | 89.17 | 1 | PHASE-II BLOCK-A |
| Shop No.B35 | 57.84 | 1 | PHASE-II BLOCK-A |
| Shop No.B36 | 57.84 | 1 | PHASE-II BLOCK-A |
| Shop No.B37 | 57.84 | 1 | PHASE-II BLOCK-A |
| Shop No.B38 | 57.84 | 1 | PHASE-II BLOCK-A |
| Shop No.B39 | 57.84 | 1 | PHASE-II BLOCK-A |
| Shop No.B40 | 57.84 | 1 | PHASE-II BLOCK-A |
| Shop No.B41 | 1,093.48 | 1 | PHASE-II BLOCK-A |
| Shop No.B42 | 53.05 | 1 | PHASE-II BLOCK-A |
| Shop No.B43 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B44 | 52.65 | 1 | PHASE-II BLOCK-A |
| Shop No.B45 | 52.65 | 1 | PHASE-II BLOCK-A |
| Shop No.B46 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B47 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B48 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B49 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B50 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B51 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B52 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B53 | 82.42 | 1 | PHASE-II BLOCK-A |
| Shop No.B54 | 54.26 | 1 | PHASE-II BLOCK-A |
| Shop No.B55 | 54.26 | 1 | PHASE-II BLOCK-A |
| Shop No.B56 | 82.55 | 1 | PHASE-II BLOCK-A |
| Shop No.B57 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B58 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B59 | 70.87 | 1 | PHASE-II BLOCK-A |
| Shop No.B60 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B61 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B62 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B63 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B64 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B65 | 55.07 | 1 | PHASE-II BLOCK-A |
| Shop No.B66 | 141.1 | 1 | PHASE-II BLOCK-A |
| Shop No.B67 | 56.66 | 1 | PHASE-II BLOCK-A |
| Shop No.B68 | 49.55 | 1 | PHASE-II BLOCK-A |
| Gaming Zone at Second Floor | 1,072.36 | 1 | PHASE-II BLOCK-A |
| AUDI-1 at Second and Third Floor | 309.48 | 1 | PHASE-II BLOCK-A |
| AUDI-2 at Second and Third Floor | 313.05 | 1 | PHASE-II BLOCK-A |
| AUDI-3 at Second and Third Floor | 319.16 | 1 | PHASE-II BLOCK-A |
| AUDI-4 at Second and Third Floor | 307.97 | 1 | PHASE-II BLOCK-A |
| Shop No.C1 | 167 | 1 | PHASE-II BLOCK-B |
| Shop No.C2 | 173.87 | 1 | PHASE-II BLOCK-B |
| Shop No.C3 | 173.87 | 1 | PHASE-II BLOCK-B |
| Shop No.C4 | 173.87 | 1 | PHASE-II BLOCK-B |
| Shop No.C5 | 173.87 | 1 | PHASE-II BLOCK-B |
| Shop No.C6 | 167 | 1 | PHASE-II BLOCK-B |
| Shop No.C7 | 151.32 | 1 | PHASE-II BLOCK-B |
| Shop NO.C8 | 157.54 | 1 | PHASE-II BLOCK-B |
| Shop No.C9 | 157.54 | 1 | PHASE-II BLOCK-B |
| Shop No.C10 | 157.54 | 1 | PHASE-II BLOCK-B |
| Shop No.C11 | 157.54 | 1 | PHASE-II BLOCK-B |
| Shop No.C12 | 151.32 | 1 | PHASE-II BLOCK-B |
| Shop No.C13 | 574.07 | 1 | PHASE-II BLOCK-B |
| Shop No.C14 | 574.07 | 1 | PHASE-II BLOCK-B |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-03-01 | |
|---|---|---|
| Proposed completion | 2025-12-31 |
Quarterly progress
| 2021-Q3 | 2021-12-15 |
| 2021-Q4 | 2022-01-11 |
| 2022-Q1 | 2022-04-29 |
| 2022-Q2 | 2022-08-09 |
| 2022-Q3 | 2022-11-10 |
| 2022-Q4 | 2023-03-01 |
| 2023-Q1 | 2023-08-18 |
| 2023-Q2 | 2023-11-02 |
| 2023-Q3 | 2025-09-25 |
| 2023-Q4 | 2025-09-25 |
| 2024-Q1 | 2025-09-25 |
| 2024-Q2 | 2025-09-25 |
| 2024-Q3 | 2025-09-25 |
| 2024-Q4 | 2025-09-25 |
| 2025-Q1 | 2025-09-25 |
| 2025-Q2 | 2025-09-25 |
| 2025-Q3 | 2025-10-16 |
| 2025-Q4 | 2026-01-11 |
| 2026-Q1 | 2026-04-10 |
| 2026-Q2 | 2026-07-15 |
| 2026-Q3 | 2026-10-15 |
Extensions
| Valid to |
|---|
| 2026-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Eastwood Infra Pvt Ltd | |
|---|---|---|
| Type | Company | |
| Escrow bank | Capital Small Finance Bank | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | MANINDER KAUR, SOFIA ARCHITECTS AND TOWN PLANNERS |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11283&inPromoter_ID=2097&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-27
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2022-05-10
- Electric Substation NOC · 2025-04-14
- Environment Clearance certificate/ NOC · 2022-04-25
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2020-10-08
- NOC from Fire Department/ Chief Fire Officer · 2023-08-23
- NOC from NHAI/ PWD · 2023-02-09
- Other Document (All NOCs of Project) · 2021-06-04
- Other Document (NOC from BDPO Department) · 2023-08-28
- Other Document (NOC from Drainage Department) · 2023-08-25
- Other Document (NOC from Forest Department) · 2023-08-08
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-17
- Pollution Clearance from Punjab Pollution Control Board · 2021-02-17
- Pollution Clearance from Punjab Pollution Control Board · 2025-06-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-06-18
- Project Land Khasra Report or Plan
- Extension of Registration Certificate · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-27
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2022-05-10
- Electric Substation NOC · 2025-04-14
- Environment Clearance certificate/ NOC · 2022-04-25
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2020-10-08
- NOC from Fire Department/ Chief Fire Officer · 2023-08-23
- NOC from NHAI/ PWD · 2023-02-09
- Other Document (All NOCs of Project) · 2021-06-04
- Other Document (NOC from BDPO Department) · 2023-08-28
- Other Document (NOC from Drainage Department) · 2023-08-25
- Other Document (NOC from Forest Department) · 2023-08-08
- Pollution Clearance from Punjab Pollution Control Board · 2025-04-17
- Pollution Clearance from Punjab Pollution Control Board · 2021-02-17
- Pollution Clearance from Punjab Pollution Control Board · 2025-06-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-06-18
- Extension order · Sign in to download
- 2021-Q3 · 2021-12-15
- 2021-Q4 · 2022-01-11
- 2022-Q1 · 2022-04-29
- 2022-Q2 · 2022-08-09
- 2022-Q3 · 2022-11-10
- 2022-Q4 · 2023-03-01
- 2023-Q1 · 2023-08-18
- 2023-Q2 · 2023-11-02
- 2023-Q3 · 2025-09-25
- 2023-Q4 · 2025-09-25
- 2024-Q1 · 2025-09-25
- 2024-Q2 · 2025-09-25
- 2024-Q3 · 2025-09-25
- 2024-Q4 · 2025-09-25
- 2025-Q1 · 2025-09-25
- 2025-Q2 · 2025-09-25
- 2025-Q3 · 2025-10-16
- 2025-Q4 · 2026-01-11
- 2026-Q1 · 2026-04-10
- 2026-Q2 · 2026-07-15
- 2026-Q3 · 2026-10-15