Overview
EDEN GARDEN II
BUILDERS ALLIANCE PVT. LTD · MOTU KA BASS
Units385
Booked118 of 385As of 2024-06-30
Completion2024-12-31Revised · Proposed 2022-12-01
Registered on2023-01-13
Valid to2024-12-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 62 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 24 documents · 7 source links |
Registration
Registration
| Promoter | BUILDERS ALLIANCE PVT. LTD | |
|---|---|---|
| District | Jaipur | |
| Locality | MOTU KA BASS | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2023/2343 | |
| Registered on | 2023-01-13 | |
| Valid to | 2024-12-31 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2022-12-01 | |
| Revised completion | 2024-12-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,55,80,791 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹19,55,80,791 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2024-Q2 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 94,494.09 | |
|---|---|---|
| Built-up (m²) | 45,359.26 | |
| Towers | 375 | |
| Units | 385 | |
| Booked | 118 | |
| Booked as of | 2024-06-30 |
Unit types
| Plot No. M- 1, 2, 3, 4, 5 | 5 | 0 |
| Plot No. M- 6 | 1 | 0 |
| Plot No. M- 7 | 1 | 0 |
| Plot 'M' - EWS/LIG - 8 | 1 | 0 |
| Plot 'M' - EWS/LIG - 9 | 1 | 0 |
| BLOCK 'M' - EWS/LIG - 10,11,12,13,14,15,16,17,22,23,24,25,26,27,28,29 | 16 | 0 |
| BLOCK 'M' - EWS/LIG - 18 | 1 | 0 |
| BLOCK 'M' - EWS/LIG - 19 | 1 | 0 |
| SHOP TYPE 1 No. 21 to 65 | 45 | 0 |
| SHOP TYPE 2 No. 1 to 20 | 20 | 0 |
| Plot 'O' - 38 to 44, 47 to 52, 55 TO 60, 63 to 69, 72 to 78, 81 to 86, 89 to 94, 97 to 103 | 52 | 0 |
| BLOCK 'O' No. 2 to 8, 11 to 17, 20 to 26, 29 to 35 | 28 | 0 |
| Plot 'O' 88 | 1 | 0 |
| BLOCK 'O' No. 106 to 110, 113 to 116, 119 to 122, 125 to 129 | 18 | 0 |
| Plot 'O' No. 45,62,79,96 | 4 | 0 |
| BLOCK 'O' No. 87 | 1 | 0 |
| BLOCK 'O' No. 132 to 143 | 12 | 0 |
| BLOCK 'O' No. 146 to 157 | 12 | 0 |
| BLOCK 'O' No. 9,28 | 2 | 0 |
| BLOCK 'O' No. 19 | 1 | 0 |
| BLOCK 'O' No. 46 | 1 | 0 |
| BLOCK 'O' No. 61, 95 | 2 | 0 |
| BLOCK 'O' No 80 | 1 | 0 |
| BLOCK 'O' No. 10, 27 | 2 | 0 |
| BLOCK 'O' No. 18 | 1 | 0 |
| BLOCK 'O' No. 144 | 1 | 0 |
| BLOCK 'O' No. 37,70,71, 104 | 4 | 0 |
| BLOCK 'O' No. 54 | 1 | 0 |
| BLOCK 'O' No. 1, 36 | 2 | 0 |
| BLOCK 'O' No. 111,124 | 2 | 0 |
| BLOCK 'O' No. 112,117,118,123 | 4 | 0 |
| BLOCK 'O' No. 53 | 1 | 0 |
| BLOCK 'O' No. 131 | 1 | 0 |
| BLOCK 'O' No. 105, 130 | 2 | 0 |
| BLOCK 'O' No. 160 to 163 | 4 | 0 |
| BLOCK 'O' No. 159 | 1 | 0 |
| BLOCK 'O' No. Y-1 | 1 | 0 |
| BLOCK 'N' No. 58 to 62, 65 to 68 | 19 | 0 |
| BLOCK 'N' No. 2 to 12 & 16 TO 27 | 23 | 0 |
| BLOCK 'N' No. 63 | 1 | 0 |
| BLOCK 'N' No. 30 TO 41 & 44 TO 55 | 24 | 0 |
| BLOCK 'N' No. 64 | 1 | 0 |
| BLOCK 'N' No. 57 | 1 | 0 |
| BLOCK 'N' No. 1, 28 | 2 | 0 |
| BLOCK 'N' No. 29, 56 | 2 | 0 |
| Plot 'M' - EWS/LIG 43,60 | 2 | 0 |
| Plot 'M' - EWS/LIG 51 | 1 | 0 |
| Plot 'M' - EWS/LIG 32 TO 41, 44 TO 50, 53 TO 59 | 24 | 0 |
| Plot 'M' - EWS/LIG 63 | 1 | 0 |
| Plot 'M' - EWS/LIG 80 | 1 | 0 |
| Plot 'M' - EWS/LIG 52 | 1 | 0 |
| Plot 'M' - EWS/LIG 21, 31 | 2 | 0 |
| Plot 'M' - EWS/LIG 70, 73 | 2 | 0 |
| Plot 'M' - EWS/LIG 20, 30 | 2 | 0 |
| Plot 'M' - EWS/LIG 71, 72 | 2 | 0 |
| Plot 'M' - EWS/LIG 64 TO 69 | 6 | 0 |
| Plot 'M' - EWS/LIG 74 TO 79 | 6 | 0 |
| PLOT NO. N-13 TO 15 | 3 | 0 |
| BLOCK 'N' No. 69 | 1 | 0 |
| BLOCK N NO. 42 & 43 | 2 | 0 |
| BLOCK 'O' No. 158 | 1 | 0 |
| BLOCK 'O' No. 145 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-12-01 | |
|---|---|---|
| Proposed completion | 2022-12-01 | |
| Revised completion | 2024-12-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2024-Q2 | 2024-07-31 | 118 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BUILDERS ALLIANCE PVT. LTD | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | KOTAK MAHINDRA BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=jaipur%2C+Jaipur%2C+Rajasthan%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.rajasthan.gov.in/ProjectDetail?id=G6rLKqdr0hjOYx7nZ4DNEQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/G6rLKqdr0hjOYx7nZ4DNEQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=G6rLKqdr0hjOYx7nZ4DNEQ%3D%3D&QuarterIdEnc=RXQtwfTEmtE0gcDePQWEOA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=iqU8h0fFYq0%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- Others
- SitePlanPath · 2022-12-27
- LayoutPlanPath · 2022-12-27
- SitePlanPath · 2022-12-28
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2024-07-27 · Sign in to download
- R2_UploadDoc · 2024-07-27 · Sign in to download
- R3_UploadedPath · 2024-07-30 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download