Overview
ELDECO VIVIANA SELECT
ELDECO MAKSAD PROPERTIES LIMITED · Ludhiana
Units108
Completion2029-03-29Proposed
Valid to2029-03-29
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 23 unit types |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 50 documents · 25 source links |
Registration
Registration
| Promoter | ELDECO MAKSAD PROPERTIES LIMITED | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PR0968 | |
| Valid to | 2029-03-29 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-03-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | 2024-04-30 | |
| License as Promoter from competent Authority | 2024-03-30 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2024-01-23 | |
| NOC from NHAI/ PWD | 2023-12-27 | |
| Other Document (Drain NOC ) | 2024-01-05 | |
| Other Document (NOC from BDO) | Permissions (Received) | 2023-12-15 |
| Other Document (NOC from Tehsildar) | Permissions (Received) | 2023-12-18 |
| Other Document (NOC PSTCL) | Permissions (Received) | 2023-12-11 |
| Other Document (PWD Permission to Access Road) | 2024-02-05 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-01-23 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹46,39,06,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 40,417.642 | |
|---|---|---|
| Units | 108 |
Unit types
| 32-41 | 551.84 | 10 | COMMERCIAL PLOTS |
| School 2 | 2,024.022 | 1 | SCHOOL SITE |
| EWS 2 | 1,691.45 | 1 | EWS SITE |
| 131 - 137 | 275.91 | 7 | RESIDENTIAL PLOTS |
| 138 | 250.83 | 1 | RESIDENTIAL PLOTS |
| 145 | 176.45 | 1 | RESIDENTIAL PLOTS |
| 146 | 292.64 | 1 | RESIDENTIAL PLOTS |
| 147 - 156 | 292.64 | 10 | RESIDENTIAL PLOTS |
| 172 | 334.44 | 1 | RESIDENTIAL PLOTS |
| 130 | 294.73 | 1 | RESIDENTIAL PLOTS |
| 171 | 334.44 | 1 | RESIDENTIAL PLOTS |
| 173 | 275.91 | 1 | RESIDENTIAL PLOTS |
| 174 - 179 | 267.55 | 6 | RESIDENTIAL PLOTS |
| 180 - 185 | 275.91 | 6 | RESIDENTIAL PLOTS |
| 186 | 275.91 | 1 | RESIDENTIAL PLOTS |
| 139 - 144 | 259.197 | 6 | RESIDENTIAL PLOTS |
| 170 | 319.81 | 1 | RESIDENTIAL PLOTS |
| 4BHK(Plot No. 157) | 141.341 | 4 | RESIDENTIAL INDEPENDENT FLOORS |
| 4BHK(Plot No. 158 to 165) | 132.197 | 32 | RESIDENTIAL INDEPENDENT FLOORS |
| 4BHK(Plot No. 166) | 138.632 | 4 | RESIDENTIAL INDEPENDENT FLOORS |
| 4BHK(Plot No. 167) | 159.462 | 4 | RESIDENTIAL INDEPENDENT FLOORS |
| 4BHK(Plot No. 168) | 161.062 | 4 | RESIDENTIAL INDEPENDENT FLOORS |
| 4BHK(Plot No. 169) | 151.917 | 4 | RESIDENTIAL INDEPENDENT FLOORS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-05-01 | |
|---|---|---|
| Proposed completion | 2029-03-29 |
Quarterly progress
| 2024-Q2 | 2024-07-05 |
| 2024-Q3 | 2024-10-07 |
| 2024-Q4 | 2025-01-06 |
| 2025-Q1 | 2025-04-03 |
| 2025-Q2 | 2025-07-05 |
| 2025-Q3 | 2025-10-06 |
| 2025-Q4 | 2026-01-06 |
| 2026-Q1 | 2026-04-10 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ELDECO MAKSAD PROPERTIES LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11971&inPromoter_ID=2692&inPromoterType=2
- Registration Certificate
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Borewell Registration certificate from Central Ground Water Authority · 2024-02-01
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2024-04-30
- License as Promoter from competent Authority · 2024-03-30
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-01-23
- NOC from NHAI/ PWD · 2023-12-27
- Other Document () · 2024-05-24 · Sign in to download
- Other Document (Drain NOC ) · 2024-01-05
- Other Document (Forest) · 2024-01-02 · Sign in to download
- Other Document (Garbage Collection) · 2024-01-16 · Sign in to download
- Other Document (LOI by Glada) · 2024-01-25 · Sign in to download
- Other Document (NOC from BDO) · 2023-12-15
- Other Document (NOC from Tehsildar) · 2023-12-18
- Other Document (NOC PSTCL) · 2023-12-11
- Other Document (PWD Permission to Access Road) · 2024-02-05
- Other Document (Pyament Slip ) · 2024-05-24 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2024-01-23
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Environment Clearance certificate/ NOC · 2024-04-30
- License as Promoter from competent Authority · 2024-03-30
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-01-23
- NOC from NHAI/ PWD · 2023-12-27
- Other Document (Drain NOC ) · 2024-01-05
- Other Document (NOC from BDO) · 2023-12-15
- Other Document (NOC from Tehsildar) · 2023-12-18
- Other Document (NOC PSTCL) · 2023-12-11
- Other Document (PWD Permission to Access Road) · 2024-02-05
- Pollution Clearance from Punjab Pollution Control Board · 2024-01-23
- 2024-Q2 · 2024-07-05
- 2024-Q3 · 2024-10-07
- 2024-Q4 · 2025-01-06
- 2025-Q1 · 2025-04-03
- 2025-Q2 · 2025-07-05
- 2025-Q3 · 2025-10-06
- 2025-Q4 · 2026-01-06
- 2026-Q1 · 2026-04-10
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-15