Overview
Elite City
M.K Land Developers · Jalandhar
Units126
Completion2019-12-31Proposed
Valid to2020-12-31
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details · 32 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 16 documents · 38 source links |
Registration
Registration
| Promoter | M.K Land Developers | |
|---|---|---|
| District | Jalandhar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-JAL33-PR0363 | |
| Valid to | 2020-12-31 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2019-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date |
|---|---|
| Application for Occupancy/ Completion/ Phase Completion Certificate | 2016-12-21 |
| CLU Certificate | |
| License to develop colony or society from Competent Authority |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹5,17,42,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 49,331.18 | |
|---|---|---|
| Units | 126 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| RESIDENTIAL PLOTS | 180 | 126 | ELITE CITY |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2011-08-30 | |
|---|---|---|
| Proposed completion | 2019-12-31 |
Quarterly progress
| 2018-Q2 | 2022-01-27 |
| 2018-Q3 | 2022-01-27 |
| 2018-Q4 | 2022-01-27 |
| 2019-Q1 | 2022-01-27 |
| 2019-Q2 | 2022-01-27 |
| 2019-Q3 | 2022-01-27 |
| 2019-Q4 | 2022-01-27 |
| 2020-Q1 | 2022-01-27 |
| 2020-Q2 | 2022-01-27 |
| 2020-Q3 | 2022-01-27 |
| 2020-Q4 | 2022-01-27 |
| 2021-Q1 | 2022-01-27 |
| 2021-Q2 | 2022-01-27 |
| 2021-Q3 | 2022-01-27 |
| 2021-Q4 | 2022-01-27 |
| 2022-Q1 | 2022-05-28 |
| 2022-Q2 | 2023-01-10 |
| 2022-Q3 | 2023-01-10 |
| 2022-Q4 | 2023-01-10 |
| 2023-Q3 | 2023-12-01 |
| 2023-Q4 | 2024-05-13 |
| 2024-Q1 | 2024-05-13 |
| 2024-Q2 | 2024-09-26 |
| 2024-Q3 | 2025-02-21 |
| 2024-Q4 | 2025-02-21 |
| 2025-Q1 | 2025-05-01 |
| 2025-Q2 | 2025-07-31 |
| 2025-Q3 | 2026-01-19 |
| 2025-Q4 | 2026-01-19 |
| 2026-Q1 | 2026-05-25 |
| 2026-Q2 | 2026-08-22 |
| 2026-Q3 | 2026-10-10 |
Extensions
| Valid to |
|---|
| 2020-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M.K Land Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10706&inPromoter_ID=1586&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2016-12-21
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License to develop colony or society from Competent Authority
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2016-12-21
- CLU Certificate
- License to develop colony or society from Competent Authority
- Extension order · Sign in to download
- 2018-Q2 · 2022-01-27
- 2018-Q3 · 2022-01-27
- 2018-Q4 · 2022-01-27
- 2019-Q1 · 2022-01-27
- 2019-Q2 · 2022-01-27
- 2019-Q3 · 2022-01-27
- 2019-Q4 · 2022-01-27
- 2020-Q1 · 2022-01-27
- 2020-Q2 · 2022-01-27
- 2020-Q3 · 2022-01-27
- 2020-Q4 · 2022-01-27
- 2021-Q1 · 2022-01-27
- 2021-Q2 · 2022-01-27
- 2021-Q3 · 2022-01-27
- 2021-Q4 · 2022-01-27
- 2022-Q1 · 2022-05-28
- 2022-Q2 · 2023-01-10
- 2022-Q3 · 2023-01-10
- 2022-Q4 · 2023-01-10
- 2023-Q3 · 2023-12-01
- 2023-Q4 · 2024-05-13
- 2024-Q1 · 2024-05-13
- 2024-Q2 · 2024-09-26
- 2024-Q3 · 2025-02-21
- 2024-Q4 · 2025-02-21
- 2025-Q1 · 2025-05-01
- 2025-Q2 · 2025-07-31
- 2025-Q3 · 2026-01-19
- 2025-Q4 · 2026-01-19
- 2026-Q1 · 2026-05-25
- 2026-Q2 · 2026-08-22
- 2026-Q3 · 2026-10-10